Professional Documents
Culture Documents
BSBPMG533 Student Book Topic 3
BSBPMG533 Student Book Topic 3
Table of Contents
Financial completion
As you reach the final stages of your project, you will need to ensure that you have allowed for the
occurrence of unexpected delays; not all aspects of your project will finish at the same time or even on
time at all. The project team may be waiting for certain project tasks to be completed; you will need to
allow the project team the time to refer to these areas that may still need to be completed (including
financial matters).
Due to the uncertainty of the start and finish dates of some of the project tasks, it may be
necessary to adjust the project’s reporting stage and finalisation schedule.
➢ Final payments
➢ Financial reports
➢ Variations statement.
Within the financial completion of any project, the future should be the focus – not necessarily what is
happening or has happened. Many reports that signify financial completion often focus on variances –
the differences between the planned results of the project and the actual results. In order to signify the
financial completion of your project, you will need to conduct the appropriate activities. By acquiring
the necessary signature at various stages within the project lifecycle, you are indicating the approval –
or the go-ahead. It is viewed as a project management milestone as it allows the project to progress
forward. By gaining the appropriate formal approval, you are acknowledging that a project deliverable
has been completed, reviewed and accepted.
Project area Planned outcome Actual outcome Variance Reason for variance
Page |4
The different project areas that may be included in the table above include:
➢ Internal labour
➢ External labour
➢ Materials
➢ Facilities
➢ Training.
Page |5
➢ Contingencies
➢ Variations.
You can use lists of estimated and actual costs associated with the project to determine whether the
project costs were managed effectively:
➢ Were the estimated costs roughly accurate?
For example, the budget for a store refurbishment project was set at $30,000.
Project outcome(s)
The project outcome is to complete a store refurbishment for a cost of around $30,000.
Cost estimations
This consisted of the following estimations:
➢ $15,000 for the builders
Project cost
This consisted of the following actual expenditure:
➢ $25,000 for the builders
The actual cost of the budget ended up at $36,000, $6,000 over the estimation.
➢ Lists of costs
This is because you need to understand what was spent and how this compares to the estimations and
budget.
Project cost-management
You would need to look at the records of total and individual costs to see:
➢ How much was spent overall
o builders: the building budget was overspent to a structural issue that needed
resolution. This was not part of a contingency plan, but the work needed to be
done, so the extra spend was approved
o the decorators cost less than expected because less time and material was
required; this means that the estimation was overestimated
➢ Contingencies
o problems with fixtures and fitting were expected, so additional funds were
allowed for this. This means that the additional spend on new shelves was
approved and justified, and the budget was adjusted accordingly.
If the project cost-management had failed to accommodate the additional expenditure, then it would
have been less effective.
In order to review the outcomes of your project, you could also use the records that are available.
➢ Cash flows
➢ Cost-management plans
➢ Quotations
Page |8
By reviewing these records, you will be able to determine how effective your cost-management was.
Project completion
Example of a project completion report:
➢ Agreed changes
➢ Deliverables
➢ Final costs
➢ Risk assessment
➢ Recommended improvements
➢ Final date.
The person that may be required to sign the report off could be:
➢ The funding body
➢ The management
What did the organisation get for the amount of money that was spent whilst completing the project?
Essentially, the answer to this question can be achieved by reviewing the cost-management issues. The
reviewing of cost-management issues is an essential part of project management. Remember that the
level of detail that is required will depend on the project itself or the organisation. Any issues that have
occurred within the cost-management of a project, along with their outcomes and solutions, need to be
communicated.
➢ Schedule
➢ Quality
➢ Budget
➢ Functionality.
You may also need to look at the management of your project; were their methods appropriate? Did
the management have the necessary experience and/or knowledge?
Documenting improvements
Any improvements that are highlighted when reviewing any cost-management issues should be
documented appropriately. The focus of any review is the future; procedures should be adapted in
order to strive for success. Specific cost-management recommendations should be made for future
projects that may be similar.
The way that you document future improvements may depend on the organisational procedures that
are in place. Details of the suggested improvements may need to be included within the project
finalisation documentation. The documentation of suggested improvements can be used for future
projects.
P a g e | 11
References
These suggested references are for further reading and do not necessarily represent the contents of
this unit.
Websites
Budget planning: https://opentextbc.ca/projectmanagement/chapter/chapter-12-budget-planning-
project-management/
Publications
Friedman, L., and Miles, S. (2006) Stakeholders Theory and Practice. Oxford University Press.
All references accessed on and correct as of 15th June 2021, unless otherwise stated.