Non-Conformance Report (NCR)

Project Name: Al-Ahsa International Airport Contract No: ICAD-JO449/DACO/AL-AHSA AIRPORT


Location: PTB Ref. Clause
Process: ✓ Product:
NCR No: NCR-01
Major: ✓ Minor:
To: Project Manager – I Watt Designation: Project Manager
A. DETAILS OF NON – CONFORMITY
We have already given strict instructions to all supervisors that hot work or confined space work cannot be
allowed without approval from the HSE department. Your team was conducting brazing work with Hydrogen (H2)
gas without informing the HSE team. Although our team was inspected during the work, your team did not take
any safety precautions, and we had to stop the work. Afterward, without our permission, your team proceeded
with the brazing work. This is unacceptable and we cannot compromise on safety regulations.

Concession Rejection Acceptance


Target Completion Date:

Recommendation / Remarks (By The contractor is advised to submit the root cause, corrective action, and
Issuer of NCR) preventive action for the above-mentioned concerns.

Issued By: Mr. Usama Abushierah Received By:


Name Name
Signature Signature
Date: 06-Nov-23 Date:
B. ROOT CAUSE

C. CORRECTIVE ACTION

Action Taken Date:


Name: Designation: Sign.:
C. CORRECTIVE ACTION REVIEW

Name: Designation: Sign.:


NCR Closed By: Sign.: Date:

Site Photo’s
Brazing activity going on Hydrogen cylinders stored on the site without any safety precautions

The cylinders were previously stored horizontally. We have since instructed


for them to be stored upright