HUTAMA – EUROASIATIC – UTTAM KSO

PROYEK PENGEMBANGAN DAN MODERN


ISASI PABRIK GULA DJATIROTO
WEEKLY MEETING PEKAN 137

SELASA, 20 Agustus 2019


HUTAMA – EUROASIATIC – UTTAM KSO

Sr. Description Qty. Qty.


No. (As on 09.08.2019) (As on 17.08.2019)
1 Total Container 500 Nos 500 Nos
2 Container in transit from India to 15 Nos 10 Nos
Surabaya, Indonesia
3 Container under custom clearance 2 Nos 4 Nos
at Surabaya
4 Container reach at Site 483 Nos 486 Nos

Sr. Description Qty.


No. (As on 17.08.2019)
1 Total Container 853 Nos.
2 All Percentage Onsite 62,01 %
3 Container reach at Site LC-1, LC-2, LC-3, LC-4, LC-5, LC-6, LC-7, 529 Nos.
LC-8.
HUTAMA – EUROASIATIC – UTTAM KSO
HUTAMA – EUROASIATIC – UTTAM KSO
HUTAMA – EUROASIATIC – UTTAM KSO
HUTAMA – EUROASIATIC – UTTAM KSO
HUTAMA – EUROASIATIC – UTTAM KSO

MILLING SEASON 2019


4500.00
4172.60

4000.00 3872.00
3697.50

3456.40
3500.00

3000.00 2886.30
2726.90 2730.90

2500.00 2258.40
1738.30
1811.80
1970.40 1977.60
2000.00

1500.00
1224.00
1000.80
1000.00 644.10 823.20
933.60
596.33
454.67
500.00 292.00
184.80
280.00
0.00 0.00 0.00 0.00
0.00 0.00
0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8/6/2019 8/7/2019 8/8/2019 8/9/2019 8/10/2019 8/11/2019 8/12/2019 8/13/2019 8/14/2019 8/15/2019 8/16/2019 8/17/2019 8/18/2019

Cane Crushed, TCD Mixed Juice % Cane ZK ampas Moisture % bagasse Brix % Mixed Juice Mixed Juice purity Pol % Filter cake

Final Molasses purity Steam consumption Sugar recovery Total losses Sugar Colour, ICUMSA Steam Flow, ton/day Gula(TON)
HUTAMA – EUROASIATIC – UTTAM KSO
This Week 137 This Week 138

1. Repaired Pump C Massecuite 1. Intstall guard for all Tank Mollases


Mechanical Seal
2. Wiring Cable Pump C Massecuite
3. Install Pipe AH&DL From Tank
This Week 137 This Week 138

1. Install Plateform Refinery 1. Install Plateform Refinery


2. Completed Bracing Column Refinery
This Week 137 This Week 138

1. Install Rockwall Body C CVP 1. Install Allumunium Completed All Body


This Week 137 This Week 138

1. Full Welding Bottom 1. Full Welding Pipe Washing Coil


2. Expand PipeT ube 2. Full Welding Pipe Cold Water Body
3. Install Structure Semikestner 3. Full Welding Pipe Cold Calendria
This Week 137 This Week 138

1. Assembly ID, FD, SA Fan 1. Erection Column C2, B2, B3, C3


2. Erection Structure Boiler 75 TPH 2. Assembly Motor SA Fan for 75
and 150
This Week 137 This Week 138

1. Erection Body Shell adding 3m 1. Full Welding Body Shell


2. Welding Inside & Outside Body Shell
Thank You
This Week 134

1. Connecting Cable To Panel


and Termination
HUTAMA – EUROASIATIC – UTTAM KSO

This Week 135

1. Full Welding Pipe


HUTAMA – EUROASIATIC – UTTAM KSO

Sr. No. Description Qty. Qty.


(As on 20.07.2019) (As on 26.07.2019)
1 Total Container Requirement 244 Nos. 244 Nos.

2 Container in transit from India 0 Nos 0 Nos


to Surabaya , Indonesia
3 Container under custom clearan 1 Nos 0 Nos
ce at Surabaya
4 Container reach at Site 243 Nos 244 Nos

5 Outstanding estimation (nos) fr 0 Nos 0 Nos


om India

Sesuai Dengan Kesepakatan Top Management Meeting Outs


tanding Container 56 nos
HUTAMA – EUROASIATIC – UTTAM KSO
HUTAMA – EUROASIATIC – UTTAM KSO
HUTAMA – EUROASIATIC – UTTAM KSO
HUTAMA – EUROASIATIC – UTTAM KSO

This Week 134 This Week 135

1. Tipler No. 2, 4, 5 Calibration and Tera 1. Tipler No.6 Fabrication Frame


2. Tipler No. 6 Fabrication and Erection
HUTAMA – EUROASIATIC – UTTAM KSO

This Week 134

1. Inspection Welding Support


2. Inspection Bolt and Nut
HUTAMA – EUROASIATIC – UTTAM KSO

This Week 134 This Week 135

1. Install Rotary Screen Wash Pump


1. Connecting Cable to Panel PDB
and Piping.
This Week 134 This Week 135

1. Inpection Bolt and Nut 1. Connecting Cabel to Panel Control


2. Inpection All Welding Support 2. Connecting Cable Sensor Donnaly Chute