1.4 SIESMIC ZONE - 2
L1
La, Lb ≤ 2'-0"
1.5 OTHER LOADS AS PER BNBC. n1,n2 : The number of bars which ore cut off for opening
Lb
n1
La
c
a) The number of extra bars > n1/2
a
(top and bottom bars)
L1
n2
L1
b) The number of extra bars > n2/2
(top and bottom bars)
a) TYPE: ALL CONCRETE COMPRESSIVE STRENGTH CONSIDERED AS FOLLOWS: c) The number of extra bars = 2-D12
I) f 'c = 3500 psi at 28 DAYS CYLINDER STRENGTH FOR STONE CHIPS AGAINST (top and bottom bars)
MIXING RATIO = 1:1½:3. (FOR COLUMN, FOOTING, UGWR & GRADE BEAM)
II) f 'c = 3000 psi at 28 DAYS CYLINDER STRENGTH FOR 1st CLAS PICKET BRICK CHIPS
Form and Bend angle Bend Used Location
AGAINST MIXING RATIO = 1:1½:3. (FOR BEAM, SLAB, STAIR, OHWT.) Bar hook
Extention (degree) Radius (r) Bar
III) f 'c = 2500 psi AT 28DAYS CYLINDER STRENGTH FOR NORMAL BRICK CHIPS MIXING RATIO 1:2:4 Primary db
10 r = 2 db
6 Lap splice
reinf. r to end of anchorage
(FOR LINTEL FALSE SLAB, BOUNDARY WALL, PARAPET, PARKING FLOOR, DROP WALL) 4db
25
db
6 Stirrups
b) MINIMUM CYLINDER STRENGTH BASED ON CYLINDER TEST OF tie/stirrups r 13 r = 1.25 db to fastening bar
12
DIAMETER D =150mm & HEIGHT 300mm 3"
diagonal hoop
6db≥
6
I) 28 DAYS STRENGTH AS SPECIFIED IN 2.1(a) Primary
db
r = 2.5 db to Bend-up for
r 0
II) 7 DAYS STRENGTH = 75% OF THE 28 DAYS STRENGTH. Main reinforcement reinf. 32 embedment
2db
db 8
r = 5 db Bend bar in
c) CURING OF R.C.C WORK: Slab to
slab
r
20
Stirrups/ties
I) CURING TIME MINIMUM 28 DAYS
II) METHOD OF CURING: Joint of stirrups / ties alternately
onat the main bars adjacent corners
* HORIZONTAL SURFACE - BY PONDING OF WATER of the column as shown.
* OTHER SURFACES-BY WRAPPING MOIST JUTE FABRIC AND
SPRINKLING WATER BY HOSE PIPE FREQUENTLY.
S 01