Timeplan RFS Ubung Kaja-Area Bali

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

Milestone Unit Plan

1 UBUNG KAJA BALI


Survey Ls
Preparation Asplan drawing , Design , BoQ Etc Days 9
Forecast Material GuangHao Pcs 4
Forecast Material Lokal Pcs 4
Material Delivery from china Day 48
Searching internal resource , warehouse Day 14
Kick off Project with Partnet / Mitra / Mandor Day 2
Started Implementation Day 43
Quality check Day 7
Preparation Asbuild drawing , BoQ final & Etc Day 8

Total Manpower Person

Note :
Agustus
Actual Remaining
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

NOT YET
NOT YET
NOT YET
NOT YET
NOT YET
NOT YET
NOT YET
NOT YET
Sep-23
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

delivery from China


ep-23 Oct
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Oct Nove
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12
November
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31