Notes 8 Concrete Buildup Est&Ten SBEC3313 Space
Notes 8 Concrete Buildup Est&Ten SBEC3313 Space
Notes/Assumptions
rate per m3; manual mix
Materials
1m3 cement 1.28ton/m3 x RM304/ton 389.12
2m3 sand 1.52ton/m3 x RM50/ton 152.00
4m3 aggregate 1.60ton/m3 x RM40/ton 256.00
797.12
Add
Shrinkage 40% 318.85
1,115.97
Labour
Mixing manually 5 hours
Load and place concrete 2.5 hours
7.5 hours x RM5/hr 37.50
196.92
Plants/Machineries
N/A 0.00
196.92
Add
Overheads & Profit 20% 39.38
236.30 /m3