CONTRACT NUMBER
BI-10-00449
6601000192
METHOD OF STATEMENT
FOR
TILING WORK
Doc. No.: SRACO-CONST-DOC-MOS
Prepared by
SRACO COMPANY
For Approval
SAUDI ARAMCO
Prepared By-
Reviewed By- Approved By - Approved By-
Rev. No Date Revision History Construction
Construction Manager Project Manager SAPMT/SAIR
superintendent
1
UPGRADE SECURITY FACILITIES EAST WEST PUMP
STATIONS PACKAGE NUMBER: 2
CONTRACT NUMBER
BI-10-00449
6601000192
Table of Contents
1. OBJECTIVE
4. RESPONSIBILITIES
5. PROCEDURE / METHODOLOGY
6. QUALITY INSPECTION
1: OBJECTIVE
2
UPGRADE SECURITY FACILITIES EAST WEST PUMP
STATIONS PACKAGE NUMBER: 2
CONTRACT NUMBER
BI-10-00449
6601000192
The objective of this method statement is to define the general guidelines for tiling.
The purpose of this method statement is to define the work procedure for tiling. Works
shall be carried out in compliance with the drawings, project specifications, and
materials.
3
UPGRADE SECURITY FACILITIES EAST WEST PUMP
STATIONS PACKAGE NUMBER: 2
CONTRACT NUMBER
BI-10-00449
6601000192
4.4: Surveyor:
The surveyor will be mobilized to the site before starting any tile installation. Mark
the starting point with X and Y lines on the floor parallel to the walls as shown in IFC
drawings.
4
UPGRADE SECURITY FACILITIES EAST WEST PUMP
STATIONS PACKAGE NUMBER: 2
CONTRACT NUMBER
BI-10-00449
6601000192
TILE INSTALLATION
PREPARATION CERAMIC TILE:
Manual spreading and compaction to obtain uniform depth
and distribution. Remove stones and foreign materials.
Perform cutting of tile without marring visible surfaces.
Fit tile to an electrical outlet, piping, fixtures, and other
penetration as shown in the shop drawing.
Ceramic tiles are to be soaked in water for one hour before
setting in place.
FLOOR INSTALLATION:
Mark center lines for both axes as per the approved shop drawing.
Lay tiles having grained patterns in the same direction in all rooms, according to
the IFC finishing schedule.
Floor tiles are to be set in the same areas using thick wet mortar bedding on
uniformly distributed sand beds, each tile is to be beaten to ensure bedding of tiles.
Start installing tiles in one direction alongside the center line.
In wet areas provide slope to drains.
Tiles with any chips, cracks, or otherwise defective shall not be used for the work.
Fixing the tiles with equal vertical & horizontal space by using an approved plastic
cross spacer.
Remove the knocking and disturb tiles before starting joint grouting.
Filling the tile joints with approved grout.
5
UPGRADE SECURITY FACILITIES EAST WEST PUMP
STATIONS PACKAGE NUMBER: 2
CONTRACT NUMBER
BI-10-00449
6601000192
After completion of work remove and clean the extra grout/mortar or tools from
tiles and filled joints and allow to dry.
WALLS INSTALLATION:
Reconfirm the existing reference levels and position provided at the site by the site
surveyor.
All the joints (vertical & horizontal) must be unified.
Apply the adhesive to the back of the tile and tap it into place at a required level
position on the wall
Before placing the next tile take care to allow the correct joint width by placing the
correct spacers in all joints.
Joint Widths: Unless otherwise indicated, install tile with the following joint
widths: 04:06MM
Verify that tiles’ surface and verticality are within permissible limits.
Fill the tile joints with approved grout.
Site inspection of the complete wall area shall be undertaken.
After all work is complete the area will be cleaned all waste removed to designated
waste disposal areas.
Note:
Do not start joint grouting work till tiles are properly fixed to the surface.
Comply with TCNA's "Handbook for Ceramic, Glass, and Stone Tile Installation"
for TCNA installation methods specified in tile installation schedules. Comply
with parts of the ANSI A108 series "Specifications for Installation of Ceramic
Tile" that are referenced in TCNA installation methods, specified in tile
installation schedules, and apply to types of setting and grouting materials used.
Jointing Pattern: Lay tile in a grid pattern unless otherwise indicated. Lay out tile
work and center tile fields in both directions in each space or on each wall area.
Lay out tile work to minimize the use of pieces that are less than half of a tile.
Provide uniform joint widths unless otherwise indicated.
On walls, tiles must be extended from the false ceiling by 100 mm.
Before laying of tiles, Markings and Surface Preparation of Floor and Walls
should be inspected by QC.
6
UPGRADE SECURITY FACILITIES EAST WEST PUMP
STATIONS PACKAGE NUMBER: 2
CONTRACT NUMBER
BI-10-00449
6601000192
After completion of tile installation work, submit WIR for inspection and
approval.
6: QUALITY INSPECTION
6.1 Inspection Test Plan (ITP) specific to project requirements shall be made and
inspection activities are recorded either on the forms or given under “Related
Documents”.
6.2 He will ensure that the mock-up and materials are approved before starting the
work.
6.3 He will ensure that the approved inspection checklist is followed.
6.4 Keep a complete record of inspection reports with location and date.
CONTRACT NUMBER
BI-10-00449
6601000192
8.2 Provide gypsum mortar over polyethylene sheets on floors to prevent the tiles
from scratching and damage.
8.3 Provide temporary doors to control unauthorized personnel working inside.
8
UPGRADE SECURITY FACILITIES EAST WEST PUMP
STATIONS PACKAGE NUMBER: 2
CONTRACT NUMBER
BI-10-00449
6601000192
:CONTRACTOR
CONSTRUCTION MANAGER
SRACO COMPANY 0570876873
MR. MOHD SAQIB
● JSA-EW-PS04-
● JSA-EW-PS05-
● JSA-EW-PS06-
● JSA-EW-PS07-