Project Title: Design & Construction of A Community Health Centre Cum

Social Welfare Facilities at Pak Wo Road,North District


Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

1. Contract Status &Time Spent


Starting Date 13/08/2020
Completion Date 09/07/2023
Contract Period 1060 days
Granted EOT 197calendar days
Extended time for completion 1257 calendar days
Extended Completion Date 16/11/2023
Day Elapsed 1012 calendar days
Day Remaining 245 calendar days
Percentage of Day Elapsed 80.5%
Percentage of Day Remaining 19.5%

2. Major Site Activities & Progress in the Reporting Period


2.1 Monitoring System
Monitoring had been carried out by YL in accordance with the approved monitoring plan in the reporting period. The
readings at various monitoring points were taken twice per week (except VCP1/VCP1a to VCP5/VCP5a) by Patrick
Yuen Land Surveyor Co., Ltd (the independent surveying firm).The monitoring check points readings extracted from
the survey reports are summarized in the table below:-

Monitoring Points Range of Alert Alarm Action


Reading Level Level Level
+10mm to -3mm 12.5mm 17mm 25mm
Ground settlement check points
Settlement Note: + ve. is uplifted
(GSM1 to GSM20)
-ve. is settled
Settlement marks on existing +9mm to -4mm 12.5mm 17mm 25mm
structure or utilities Settlement
(BUSM1 toBUSM6, BUSM7A, Note: + ve. is uplifted
BUSM8 to BUSM17)( -ve. is settled
Vibration monitoring points Max. peak VCP6 N/A 8 10 15
(VCP6 to VCP10) particle VCP7 N/A
(VCP1/VCP1a to velocity(PP VCP8 N/A
VCP5/VCP5a) V) VCP9 N/A
(mm/sec) VCP10 N/A
PZ1 DRY to +5.99mpd +7.0mPD +7.5mPD +8.0mPD
Piezometers & Ground PZ2 Piezometer removed +10.4mPD +10.9mPD +11.4mPD
Standpipe Water
PZ3 Piezometer removed +10.4mPD +10.9mPD +11.4mPD
Level
PZ4 +6.61mpd to +6.64mpd
(PZ1 to PZ5) +6.76mpd to +6.99mpd +7.0mPD +7.5mPD +8.0mPD
PZ5
Tilting markers on existing structure 1:1504~1:1175 1:1000 1:750 1:500
(TM1A, TM2 to TM7)
Horizontal movement monitoring points 5mm~11mm 25mm 34mm 50mm
(HMMP1 to HMMP5)

Page 1 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Notes:
i) BUSM12 on the 400 dia. fresh water pipe at the junction of Wai Ping Close and Wai Wo Street has not been installed due
to the permissions from relevant authorities had not received in the reporting period.
ii) Vibration monitoring points (VCP1 to VCP5) were relocated to the NSRson 7/4/2021 and renamed as VCP1a to VCP5a
for monitoring vibration during the piling period continuously in real time.
iii) The monitoring device at VCP2/2a was out of order and the monitoring device at VCP3/3a was relocated to the location
VCP2/2a.
iv) Tilting marker TM1 & Building settlement marker no. BUSM7 (Plastic tape markers) located at street Lamp post of Pak
Wo Street were reported damaged on 29/10/2021. New tilting marker TM1A & Building settlement markers BUSM7A
were installed on the same street lamp post and new position of the markers surveyed on 29/10/2021.

2.2 Steel H-Pile Installation Works


a). Pitching/driving of total 340 nos. steel H-piles commenced on 12/01/2021 and completed on
12/06/2021.
b). 51nos.steel H-piles were selected by ArchSD for PDA (restrike) test. Restrike test was commenced on
16/07/2021and completed on 24/07/2021.
c). 23 nos. steel H-piles were selected by ArchSDon 05/08/2021for CAPWAP analysisto assess the
allowable load capacity.
d). The following statics pile load tests were carried out from 16/08/2021 to 11/09/2021.
Pile Load Test
Steel H pile, Test Pile No. Date start Date finish Result
a)PC25-P1
b)PC15-P3 16-08-2021 19-08-2021 Satisfactory
c)PC17-P4
d)PC25-P3 28-08-2021 31-08-2021 Satisfactory
e)PC15-P4
f)PC34-P3 08-09-2021 11-09-2021 Satisfactory
The results of all tested steel H-piles (6 no.) were found to be satisfactory.

2.3 Pile Cap & Strap Beam Construction


100% (51 out of 51 no.) of pile cap concreting completed.
During the reporting period, pile cap no. PC42 and associated strap beams no.SB68, SB71completed the
concreting.

2.4 Concrete Column Construction


2.4.1 From pile cap to G/F level (+9.4mpd)
100% (51 out of 51 no.) of column concreting completed. During the reporting period, column numbers C42,
C43 were concreted.
2.4.2 From G/F (+9.4mpd) to 1/F (+15.9mpd)
100% (45 out of 45 no.) of column concreting completed.
2.4.3 From 1/F (+15.9mpd) to 2/F level (+20.4mpd)
100% (45 out of 45 no.) of column concreting completed.
2.4.4 From 2/F (+20.4mpd) to 3/F level (+24.9mpd)
100% (39 out of 39 no.) of column concreting completed.
Page 2 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

2.4.5 From 3/F (+24.9mpd) to 4/F level (+29.4mpd)


100% (39 out of 39 no.) of column concreting completed.
2.4.6 From 4/F (+29.4mpd) to 5/F level (+33.9mpd)
100% (39 out of 39 no.) of column concreting completed.
2.4.7 From 5/F (+33.9mpd) to 6/F level (+38.4mpd)
100% (32 out of 32 no.) of column concreting completed.
2.4.8 From 6/F (+38.4mpd) to 7/F level (+42.9mpd)
100% (32 out of 32 no.) of column concreting completed.
2.4.9 From 7/F (+42.9mpd) to 8/F level (+47.4mpd)
66% (21 out of 32 no.) of column concreting completed. during the reporting period. Concreting of column
number C15 to C30, C39 & C42 completed during the reporting period.

2.5 Ground Floor Beam & Slab construction (at level +9.4mpd)
100% Beam & slab concreting completed.

2.6 1/F Beam & slab construction (at level +15.9mpd)


100% Beam & slab concreting completed.

2.7 2/F Beam & slab construction (at level +20.4mpd)


100% Beam & slab concreting completed.

2.8 3/F Beam & slab construction (at level +24.9mpd)


100% Beam & slab concreting completed.

2.9 4/F Beam & slab construction (at level +29.4mpd)


100% Beam & slab concreting completed.

2.9 5/F Beam & slab construction (at level +33.9mpd)


100% Beam & slab concreting completed. During the reporting period, the following areas of 5/F beam & slab
were concreted: gridline 1 to 7, E to H.

2.10 6/F Beam & slab construction (at level +38.4mpd)


100% Beam & slab concreting completed. During the reporting period, the following areas of 6/F beam & slab
were concreted: gridline 4 to 7, E to H.

Page 3 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

2.11 7/F Beam & slab construction (at level +42.9mpd)


100% Beam & slab concreting completed. During the reporting period, the following areas of 7/F beam & slab
were concreted: gridline 1 to 7, A to H.
2.12 8/F Beam & slab construction (at level +47.4mpd)
25% Beam & slab concreting completed. During the reporting period, the following areas of 8/F beam & slab
were concreted: gridline 4 to 7, B to E.
2.13 Fence Wall construction (located at northern & north-eastern site boundary)
15% of Fence wall (wall base & stem only) concreting completed. During the reporting period, no concreting
activity was carried out.

2.14 Retaining Wall Construction (located at western site boundary adjacent to Pak Wo Road)
a) 100% (10 out of 10 Bays) base slab of retaining wall concreting completed.
b) 100% (10 out of 10 Bays) wall stem of retaining wall concreting completed.
c) 100 % (28 out of 28 nos.) short cantilever beams (RWCB for supporting surface channel) concreting
completed.
d) 100% (27 out of 27 nos.) cantilever beams (RWCB for supporting the 2.5m high fence wall) concreting
completed. During the reporting period, cantilever beam no. RWCB32 to RWCB35, RWCB41 and
associated concrete tie beams no. RWB5 to RWB8, RWB14, and RWB15 completed the concreting.

2.15 Underground Manhole Construction


During the reporting period, no underground manhole concreting activity was carried out.

2.16 Tower crane floor climbing


On late October,2022, the mast of the tower crane was climbed up 13.5m from G/F level(+9.4mpd) and finally
supported on two steel collars which were installed at 2/F level (+20.4mpd) & 5/F level (+33.9mpd)

2.15 Excavation & Lateral Support (ELS) Works


2.15.1 Northern steel sheet pile wall ( wall adjacent to Fanling Highway)
100% (161 out of 161 numbers) of steel sheet piles were driven to their design toe level.

2.15.2 Western steel sheet pile wall (wall adjacent to Pak Wo Road)
a) 100% (168 out of 168 numbers) of steel sheet piles were driven to their design toe level.
b) 100% layer 1, layer 2 steel waling& steel struts (8 numbers) installation completed.
(Located at gridline 1A to 1E)
c) 100% of steel waling (1 layer) & corner struts (4 numbers) installation completed.
(Located at gridline 1E to 1G)

Page 4 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

2.15.3 Southern steel sheet pile wall (wall adjacent to Wai Ping Close)
a) 100%of steel sheet piles were driven to their design toe level.
b) Gridline 1G to 2G
100% steel waling (1 layer) & corner struts (4 numbers) installation completed.
e) Gridline 2H to 4H
100% steel waling (1 layer) & corner struts (4 numbers) installation completed.
f) Gridline 4H to 7H
100% steel waling (1 layer) & corner struts (7 numbers) installation completed.

2.15.4 Eastern steel sheet pile wall (wall adjacent to Wai Wo Street)
a) 100%of steel sheet piles were driven to their design toe level.
b) Gridline 7F to 7H
100% steel waling (1 layer) & corner struts (7 numbers) installation completed.

2.16 G/F on grade Slab construction


90% on-grade slab concreting completed. During the reporting period, on grade reinforced concrete slabs
number S77 & S78 were concreted.

3 Safety & Environmental Issues on Site


To ensure the safety systems of work on site are followed properly, the RE team has enhanced the safety
supervision by i) participating the weekly safety walks; ii) carrying out spot checking of high risk construction
activities on site; and iii) conducting daily review with the Contractor of all high risk activities.

4 Quality Control and Workmanship Issues on Site


The workmanship/quality control of the construction works were found satisfactory in general. No major
defects/ non-conforming items were observed during routine inspection in the reporting period.

5 Material Sampling/Testing & Others


5.1 The permission for the use of 135 nos. steel sheet piles (Batch 2), 2 nos. 10mm thick steel plates, 2 nos. 20mm
thick steel plates and 10 nos. 100x100x6mm steel angles (Batch 1) was granted by RE on 20/07/2021.
5.2 Steel sheet pile, FSP -III, S355GP, 400 widths x12m long (Batch 3) was delivered to site on October, 2021 and
steel samples were taken to test at the Public Works Laboratories. The result of the steel sheet pile material test
was found to be satisfactory.
5.3 Steel reinforcing bar (Batch 1) for pile cap construction was delivered to site on September, 2021. Steel rebar
samples were tested at Public Works Laboratories and the result of the steel rebar material test was found to be

Page 5 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

satisfactory.
5.4 Steel fabric (B503) for carriageway road widening works – test samples of the steel mesh were tested at
HOKLAS laboratory and the results of the steel mesh rebar test were found to be satisfactory.
5.5 Steel reinforcing bar (Batch 2) for precast concrete element construction was delivered to YLW site (located in
mainland China) on September, 2021. Test samples of the steel rebar were tested at HOKLAS laboratory &
Public Works Laboratories, the test results of the steel rebar were found to be satisfactory.
5.6 Steel reinforcing bar (Batch 3) for pile cap construction delivered to site on December, 2021. Steel rebar samples
send to Public Works Laboratories for testing, the test results of the steel rebar were found to be satisfactory.
5.7 Steel reinforcing bar (Batch 4) for pile cap construction delivered to site on late December, 2021. Test samples of
the steel rebar were tested at HOKLAS laboratory & Public Works Laboratories.
5.8 Steel reinforcing bar (Batch 5) for pile cap construction delivered to site on January, 2022.Test samples of the steel
rebar were sent to Public Works Laboratories for testing.
5.9 Steel fabric B503 and A193 for on grade concrete slab were tested at HOKLAS laboratory and the test results of
the steel mesh rebar were found to be satisfactory.
5.10 Steel fabric C503 & A193 (Batch 2) for external Driveway & Car parking area were tested at HOKLAS
laboratory and the test results of the steel mesh rebar were found to be satisfactory.
5.11 Steel reinforcing bar (Batch 1) for superstructure construction delivered to off-site storage yard on May 2022.Test
samples of the steel rebar were sent to Public Works Laboratories for testing and the test result was found to be
satisfactory.
5.12 Steel fabric C503 & A193 (Batch 3) for ground floor on grade concrete slab delivered to site on May, 2022.
Test sample of the steel fabric was sent to Public Works Laboratories for testing, the test result was found to be
satisfactory.
5.13 Hot rolled Steel H-beam (254x254x73kg) for lagging UC of excavation and lateral support works delivered to site
on May,2022. Test sample of the steel H-beam was sent to Public Works Laboratories for testing, the test results of
the steel H-beam were found to be satisfactory.
5.14 Steel reinforcing bar (Batch 2) for superstructure construction was delivered to off-site storage yard on June
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bar was found to be satisfactory.
5.15 Steel reinforcing bar (Batch 3) for superstructure construction was delivered to off-site storage yard on July
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bars (diameter of 12mm, 16mm, 20mm, 25mm, 40mm ) was found to be satisfactory. Steel bar samples of 10mm
diameter do not meet the permissible deviation requirement as specified in CS2:2012, Table 3 - Permissible
deviation from nominal mass. Additional or new batch of 10mm diameter steel bar need to be sent to Public
Works laboratory for testing.
5.16 Steel plates (grade S275J0 – 16mm, 20mm thick) were sent to Public Works Laboratories for testing, the test
result of the steel plates (customer test request no. SP-7) was found to be satisfactory.

Page 6 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

5.17 Steel reinforcing bar (Batch 4) for superstructure construction was delivered to off-site storage yard on July
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bars (diameter of 10mm, 16mm, and 40mm) was found to be satisfactory. However, steel bar samples of 12mm
diameter do not meet the permissible deviation requirement as specified in CS2:2012, Table 3 - Permissible
deviation from nominal mass. Additional steel bar (12mm diameter) was re-tested and re-test result of the steel bar
(mass per meter length) was found to be satisfactory.
5.18 Steel plates (grade S275J0 – 5mm, 12mm, 16mm, 25mm thick & grade S355J0 – 20mm thick) were sent to
Public Works Laboratories for testing in August 2022, the test result of the steel plates (customer test request no.
SP-8, SP-9) was found to be satisfactory.
5.19 Steel reinforcing bar (Batch 5 & 6) for superstructure construction was delivered to off-site storage yard on
August 2022.Steel bar sample was sent to PWL for testing and the test result was found to be satisfactory.
5.20 Soil samples of imported soil for backfilling proposed by the Contractor were tested in August, 2022 by Public
Work Laboratories. The preliminary results are as follows: Particle size distribution of soil and chemical analysis
(total Sulphate content) of soil comply with ASD specification. However, the liquid limit of the soil does not
comply with ASD specification. Additional soil samples were sent to PWL for retesting on September, 2022. The
result of retesting the soil sample (liquid limit of soil) is found to be satisfactory.
5.21 Steel reinforcing bar (Batch 7) for superstructure construction was delivered to off-site storage yard on October
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bar is found to be satisfactory.
5.22 Steel reinforcing bar (Batch 8) for superstructure construction was delivered to off-site storage yard on November
2022. Test samples of the steel rebar were sent to Public Works Laboratories for testing. The preliminary test results
of the steel rebar (bar diameter of 12mm, 16mm, 25mm) were found to be satisfactory. For 10mm diameter bar, test
sample does not comply with the tensile strength & total elongation at maximum force requirements specified in
CS2:2021, hence the test result is not satisfactory.
5.23 Steel angles of sizes 50x50x5mm, 30x30x5mm(grade S275J0) and 125x75x8mm(grade S355J0) for Aluminum
blade, Louvre, Aluminum Cladding (Batch 1) were delivered to off-site storage yard on November,2022. Test
samples of the steel angles were sent to Public Works Laboratories for testing. The preliminary test results of the
50x50x5mm, 30x30x5mm & 125x75x8mm were found to be satisfactory. For 75x50x5mm thick steel angle, the
tensile strength of the test sample is found to be lower than minimum tensile strength requirement specified in BS EN
10025-2:2004, hence the test result is not satisfactory.
5.24 Steel plate of the following thickness (10mm, 12mm, 16mm, 2mm, 3mm, 4mm, 5mm, 6mm, 8mm, 20mm – grade
S275J0) & 12mm thick (grade S355J0) were delivered to site on December,2022. Test samples of the steel plates
were sent to Public Works Laboratories for testing. The preliminary test results of the steel plates were found to be
satisfactory.
5.25 Steel reinforcing bar (Batch 9 & 10) for superstructure construction was delivered to off-site storage yard on
December 2022 & January,2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing,

Page 7 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

the test result of the steel bar (bar diameter of 12mm, 16mm, 25mm, 32mm, 40mm) is found to be satisfactory.
5.26 Steel reinforcing bar (Batch 11) for superstructure construction was delivered to off-site storage yard on January,
2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing and the test result of the
steel bar is found to be satisfactory.
5.27 Steel reinforcing bar (Batch 12) for superstructure construction was delivered to off-site storage yard on January,
2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the
steel bar (10mm diameter) is found to be satisfactory.
5.28 Steel reinforcing bar (Batch 13) for superstructure construction was delivered to off-site storage yard on February,
2023. Test samples of the steel rebar (12mm & 16mm diameter) were sent to Public Works Laboratories for testing
and the test result of the steel bar is found to be satisfactory.
5.29 A steel angle of sizes 75x50x5mm (grade S275J0) was delivered to off-site storage yard on January, 2023. Test
samples of the steel angles were sent to Public Works Laboratories for testing, the test results of the steel angle was
found to be satisfactory.
5.30 Steel channel of sizes 200x90x 30.3kg/m (grade S355J0) was delivered to off-site storage yard on January, 2023.
Test samples of the steel channel were sent to Public Works Laboratories for testing, the preliminary test results of
the steel angle was found to be satisfactory.
5.31 Steel reinforcing bar (Batch 14) for superstructure construction was delivered to off-site storage yard on February
2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing. The preliminary test results
of the steel rebar (bar diameter of 12mm, 40mm) were found to be satisfactory. For 32mm diameter bar, test sample
does not comply with the tensile/yield strength ratio requirements specified in CS2:2021, hence the test result is not
satisfactory. The 32 diameter steel bar sample was retest on early March, 2023 and the tensile test result was found to
be satisfactory.
5.32 Steel reinforcing bar (Batch 15) (bar diameter of 12mm, 16mm, 25mm,32mm &40mm) for superstructure
construction was delivered to off-site storage yard on March, 2023. Test samples of the steel rebar were sent
to Public Works Laboratories for testing and the tensile test result was found to be satisfactory.
5.33 Hot rolled Steel H-beam (305x305x97kg/m & 152x152x30kg/m – file no. HB-5) for structural steelworks
was delivered to site on March, 2023. Test sample of the steel H-beam was sent to Public Works Laboratories
for testing, the test results of the steel H-beam were found to be satisfactory.
5.34 Steel angle of sizes 50x50x6mm, 75x50x5mm, 100x100x8mm - file no.SA-5 (grade S275J0) was delivered
to off-site storage yard on March, 2023. Test samples of the steel angles were sent to Public Works
Laboratories for testing, the test results of the steel angle was found to be satisfactory.
5.35 Steel channel of size 150x75x 17.9kg/m - file no. SCC-4 (grade S275J0) was delivered to off-site storage
yard on March, 2023. Test samples of the steel angles were sent to Public Works Laboratories for testing, the
test results of the steel angle was found to be satisfactory.
5.36 Steel plate of thickness 5mm, 6mm, 8mm, 10mm &12mm – file no. SP-12 (grade S275J0) was delivered to
site on March, 2023. Test samples of the steel plates were sent to Public Works Laboratories for testing and

Page 8 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

the test results of the steel plates were found to be satisfactory.


5.37 Steel reinforcing bar (Batch 16) (bar diameter of 10mm, 12mm, 25mm & 40mm) for superstructure
construction was delivered to off-site storage yard on late March, 2023. Test samples of the steel rebar were
sent to Public Works Laboratories for testing & the preliminary test result was found to be satisfactory.
5.38 Steel angle of sizes 40x40x4mm, 75x50x5mm, 100x100x8mm - file no.SA-6 (grade S275J0) was delivered
to off-site storage yard on March, 2023. Test samples of the steel angles were sent to Public Works
Laboratories for testing, the test results of the steel angle was found to be satisfactory.
5.39 Steel angle of sizes 150 x 100 x 10mm, 100 x 50 x 6mm - file no.SA-7 (grade S275J0) was delivered to
off-site storage yard on April, 2023. Test samples of the steel angles were sent to Public Works Laboratories
for testing, the test results of the steel angle was found to be satisfactory.
5.40 Steel channels of size 127 x 64 x 14.9kg/m & 78 x 38 x 6.7kg/m - file no. SCC-5 (grade S275J0) was
delivered to off-site storage yard on April, 2023. Test samples of the steel angles were sent to Public Works
Laboratories for testing & the test results of the steel channel was found to be satisfactory.
5.41 Steel reinforcing bar (Batch 17) (bar diameter of 12mm, 32mm & 40mm) for superstructure construction
was delivered to off-site storage yard on May, 2023. Test samples of the steel rebar were sent to Public
Works Laboratories for testing & the preliminary test result was found to be satisfactory.
5.42 Steel angle of sizes 25 x 25 x 5mm,- file no.SA-8 (grade S275J0) was delivered to off-site storage yard on April,
2023. Test samples of the steel angles were sent to Public Works Laboratories for testing, the preliminary test results
of the steel angle was found to be satisfactory.
5.43 Steel reinforcing bar (Batch 18) (bar diameter of 12mm, 16mm & 40mm) for superstructure construction was
delivered to off-site storage yard on May, 2023. Test samples of the steel rebar were sent to Public Works
Laboratories for testing

5.43 Material/ITAP /Method Statement Submissions & Approval Status (Structural)

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
305mm × 305mm × 223kg/m Steel YL/MS/S/001 07/10/2020 29/10/2020
H-Piles (BS EN10025-2 Grade S450J0)
(Batch 1)
LC-600 Welding Electrode YL/MS/S/002 07/10/2020 29/10/2020
305mm × 305mm × 223kg/m Steel YL/MS/S/003 11/11/2020 17/11/2020
H-Piles (BS EN10025-2 Grade S450J0)
(Batch 2)
Release Agent for Timber Formwork YL/MS/S/004 23/10/2020 29/10/2020

Material
Release Agent for Steel Formwork YL/MS/S/005 23/10/2020 29/10/2020

Concrete Surface Retarder YL/MS/S/006 23/10/2020 29/10/2020

Page 9 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
Non-shrink Grout YL/MS/S/007 23/10/2020 30/10/2020
HY200 Injection Adhesive YL/MS/S/008 23/10/2020 (withdrawn)
Expanded Polyurethane Foam YL/MS/S/009 23/10/2020 30/10/2020
0.125mm Polythene Sheet YL/MS/S/010 23/10/2020 30/10/2020
Sealing Strip YL/MS/S/011 23/10/2020 30/10/2020
Dia. 25mm & 12mm Mild Steel Dowel YL/MS/S/012 23/10/2020 02/11/2020
Bars & PVC Sleeves
16mm × 2438mm × 6096mm YL/MS/S/013 25/11/2020 04/12/2020
Hot-rolled Steel Plate (BS EN10025-2
Grade S275J0)
(Batch 1)
305mm × 305mm × 223kg/m Steel YL/MS/S/014 17/12/2020 22/12/2020-
H-Piles (BS EN10025-2 Grade S450J0)
(Batch 3)

FSP IV 400mm × 12000mm Hot-rolled YL/MS/S/015 26/02/2021 04/03/2021


U-Sheet Pile (BS EN10248 Grade
S355GP) (Batch 1)
12mm × 2438mm × 4876mm YL/MS/S/016 26/02/2021 04/03/2021
Hot-rolled Steel Plate (BS EN10025-2
Grade S355J0) (Batch 1)

305mm × 305mm × 223kg/m Steel YL/MS/S/017 23/02/2021 12/03/2021


H-Piles (BS EN10025-2 Grade S450J0)
(Batch 4)
LB-52 Welding Electrode YL/MS/S/018 15/03/2021 16/03/2021

FSP IV 400mm x 12000mm Hot Rolled YL/MS/S/019a 25/06/2021 26/05/2021


U-Sheet Pile (BS EN 10248 Grade
S270GP) (Batch 2)
100mm × 100mm × 10mm Hot-rolled YL/MS/S/020 06/05/2021 23/05/2021
M.S. Angle (BS EN10025-2 S355J0)
(Batch 1)
10mm × 1219mm × 2438mm YL/MS/S/021 06/05/2021 26/05/2021
Hot-rolled Steel Plate (BS EN10025-2
S270J0) (Batch 1)
20mm × 1219mm × 2438mm YL/MS/S/022 06/05/2021 23/05/2021
Material Hot-rolled Steel Plate (BS EN10025-2
S270J0) (Batch 1)

305mm × 305mm × 223kg/m Steel YL/MS/S/023 06/05/2021 13/05/2021


H-Piles (BS EN10025-2 Grade S450J0)
(Batch 5)
Plastic Chairs & Cover Spacers YL/MS/S/024 02/07/2021 19/07/2021
E-Release 747 Release Agent YL/MS/S/025 02/07/2021 19/07/2021
NKC Release Agent YL/MS/S/026 02/07/2021 19/07/2021
Non-shrink Grout YL/MS/S/027 02/07/2021 (Withdrawn on
30/07/2021)
Bonding Agent YL/MS/S/028 02/07/2021 (Withdrawn on
30/07/2021)
Zinc Rich Epoxy Primer YL/MS/S/029 02/07/2021 (Withdrawn on
30/07/2021)
Tying Wire YL/MS/S/030 02/07/2021 (Withdrawn on
30/07/2021)
Horizontal Concrete Surface Retarder YL/MS/S/031 02/07/2021 19/07/2021
& Vertical Concrete Surface Retarder
Hot-dipped Galvanized Cast-in Anchors YL/MS/S/032 02/07/2021 (Withdrawn on
05/08/2021)
Injection Epoxy Resin YL/MS/S/033 02/07/2021 (Withdrawn on

Page 10 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
30/07/2021)
Concrete Mix YL/MS/S/037 to 41, 43 27/05/2021 08/07/2021
to 60
Concrete Mix YL/MS/S/42 27/05/2021 (Withdrawn on
21/06/2021)
50mm x 2438mm x 6096mm Hot-rolled YL/MS/S/061 22/07/2021 11/08/2021
Steel Plate (BS EN10025-2 Grade
S355J0)(Batch 1)
45D/20 75mm Slump Concrete Mix for YL/MS/S/062 02/09/2021 24/09/2021
Precast Element

45D/10+GGBS 100mm Slump YL/MS/S/063 02/09/2021 24/09/2021


Concrete Mix for Precast Element
Steel Wire for Substructure and YL/MS/S/064 02/09/2021 10/09/2021
Superstructure
Plastic Chairs & Cover Spacer for YL/MS/S/065 02/09/2021 (withdrawn) on
Substructure and Superstructure 27/09/2021
Concrete Spacer for Substructure YL/MS/S/066 02/09/2021 12/10/2021
and Superstructure
FSP III 400mm x 12000mm Hot Rolled YL/MS/S/067 16/08/2021 26/08/2021
U-Sheet Pile (BS EN 10248 Grade
S355GP) (Batch 3)
Steel Reinforcement Bar for Pile Cap YL/MS/S/068 06/09/2021 08/09/2021
(BS 4449:2005 and CS2:2012 (Class 2)
in Grade 500B)
B503 Steel Mesh for External YL/MS/S/069 27/09/2021 06/10/2021
Driveway and Car Parking Areas
Welding Solid Wire for Capping Plates YL/MS/S/070 27/09/2021 06/10/2021
40D20 PFA 75mm Slump Concrete YL/MS/S/071 03/11/2021 19/11/2021
Mix for External Driveway and Car
Parking Areas (Site B) (Ping Che Plant)
40D20 PFA 75mm Slump Concrete YL/MS/S/072 03/11/2021 19/11/2021
Mix for External Driveway and Car
Parking Areas (Site B) (New Tai Po
Material Plant)
40D20 PFA 75mm Slump Concrete Mix YL/MS/S/073 03/11/2021 19/11/2021
for External Driveway and Car Parking
Areas (Site B) (Tai Po Plant)
40D20 PFA 75mm Slump Concrete Mix YL/MS/S/074 withdrawn NA
for External Driveway and Car Parking
Areas (Site B) (Tai Po Plant)
Plastic Chairs & Cover Spacers for YL/MS/S/075 12/10/2021 12/10/2021
Substructure and Superstructure
(Version)
10mm x 1219mm x 2438mm Hot-rolled YL/MS/S/076 12/10/2021 21/10/2021
Steel Plate (BS EN 10025-2 Grade
S355J0) (Batch 2)
20mm x 1219mm x 2438mm Hot-rolled YL/MS/S/077 12/10/2021 21/10/2021
Steel Plate (BS EN 10025-2 Grade
S355J0) (Batch 2)
25mm x 1219mm x 2438mm Hot-rolled YL/MS/S/078 12/10/2021 21/10/2021
Steel Plate (BS EN 10025-2Grade
S355J0) (Batch 1)
152mm x 152mm x 30kg/m x 12m YL/MS/S/079 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 1)
254mm x 254mm x 73kg/m x 12m YL/MS/S/080 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN

Page 11 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
10025-2 Grade S355J0) (Batch 1)

254mm x 254mm x 167kg/m x 12m YL/MS/S/081 12/10/2021 21/10/2021


Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 1)
356mm x 368mm x 153kg/m x 12m YL/MS/S/082 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 1)
356mm x 368mm x 177kg/m x 12m YL/MS/S/083 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch
Materials1)
356mm x 406mm x 235kg/m x 12m YL/MS/S/084 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 1)
356mm x 406mm x 287kg/m x 12m YL/MS/S/085 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 1)
356mm x 406mm x 393kg/m x 12m YL/MS/S/086 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 1)
356mm x 406mm x 467kg/m x 12m YL/MS/S/087 12/10/2021 21/10/2021
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 1)
Steel Reinforcement Bar (YLW Batch 1) YL/MS/S/088 15/10/2021 23/11/2021
T10, T12, T16, T20, T25, T32 GRADE
500B
45D/20 75mm Slump Concrete Mix for YL/MS/S/089 18/10/2021 Withdrawn on
Precast Element (Aggregate Source: Hui 10/11/2021
Material
Zhou K.Wah Materials Co., Ltd45D/20
75mm Slump Concrete Mix for Precast 12/11/2021 30/11/2021
Element (Aggregate Source: Hui Zhou (Revised approved
K.Wah Materials Co., Ltd (K. Wah Aggregate source)
Quarry))
45D/10+GGBS 100mm Slump Concrete Mix 18/10/2021 Withdrawn on
YL/MS/S/090
for Precast Element (Aggregate Source: Hui 10/11/2021
Zhou K.Wah Materials Co., Ltd 12/11/2021 30/11/2021
approved
Granular Sub-Base Material YL/MS/S/091 29/11/2021 16/11/2021

M30 X 1m HDG Grade 10.9 Thread YL/MS/S/092 29/11/2021


Rods & Nuts for Steel Bracket
Inorganic Joint Filler YL/MS/S/093 29/11/2021 16/11/2021

16mm x 2438mm x 6069mm YL/MS/S/094 29/11/2021 13/12/2021


Hot rolled steel plate (BS EN10025
S275J0) (Batch 1)
Welding Electrode LB-52 YL/MS/S/095 24/02/2022 25/02/2022

Material submission of steel rebar YL/MS/S/096 13/12/2021 14/11/2021


(Batch 3)
20mm aggregates for Backfilling Works YL/MS/S/097 30/12/2021 14/11/2021

FSP III 0.4m x 12m Hot Rolled U-Sheet YL/MS/S/098 14/12/2021 03/01/2022
Pile Grade 355GP (Batch 4)
M30 Nuts for steel bracket YL/MS/S/099 14/12/2021 18/12/2021

Page 12 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
50mm x 2438mm x 6069mm YL/MS/S/0100 16/12/2021 03/01/2022
Hot rolled steel plate (BS EN10025-2
Grade S355J0) (Batch 2)
A193 Steel Mesh YL/MS/S/0101 22/12/2021 31/01/2022

C503 Steel Mesh YL/MS/S/0102 22/12/2021 08/12/2021

Steel Reinforcement bars (Batch 4) YL/MS/S/0103 23/12/2021 08/01/2021

150mmx 75mm x 18kg/m x 12 YL/MS/S/0104 23/12/2021 08/01/2022


Hot-rolled Steel Channel (BS EN
10025-2 Grade S355J0)
16 mm x 2438 mm x 6096 mm & 20mm YL/MS/S/0105 05/01/2021 13/01/2022
x 2438mm x 6096 mm Hot-rolled Steel
Plate (BS EN10025 S275J0)
HIT-RE100 Epoxy Adhesive YL/MS/S/0106 05/01/2021 24/02/2022

152mm x 152mm x 30kg/m x 12m YL/MS/S/0107 07/01/2021 13/01/2022


Hot-rolled Steel H-beam (BS EN
10025-2 Grade S355J0) (Batch 2)
Supplier’s Certification of Steel YL/MS/S/0108 19/01/2021 07/02/2022
Reinforcement Bars for Superstructure
& External Works
Steel Reinforcement Bar (Batch 5) YL/MS/S/0109 14/01/2021 21/01/2022

Joint Sealant, Bond Breaker & YL/MS/S/0110 to 112 19/01/2022 07/02/2022


Bituminous Paint
CHT711 Welding Electrode (at factory) YL/MS/S/0113 16/03/2022 19/04/2022

YLW Plant 45D+GGBS (Revised YL/MS/S/0114 4/03/2022 16/03/2022


aggregate Source)
Material YLW Plant 45D/20 (Revised aggregate 4/03/2022 16/03/2022
YL/MS/S/0115
Source)
Steel mesh A193 (Batch 2) YL/MS/S/0116 10/03/2022 25/03/2022

Steel mesh C503 (Batch 2) YL/MS/S/0117 10/03/2022 25/03/2022

T25 threaded to M20 bolt with Grade YL/MS/S/0118 11/04/2022 28/04/2022


10 Nuts (double nuts)
Inorganic joint filler for movement joint YL/MS/S/0119 12/04/2022 13/05/2022
in substructure, superstructure,
on-grade slab
A193 Steel Mesh for Ground Slab on YL/MS/S/0120 04/05/2022 13/05/2022
Grade (Batch 3)
Steel Reinforcement Bar YL/MS/S/0121 05/05/2022 11/05/2022
(Superstructure Batch 1)
254mm x 254mm x 73kg/m x 12m YL/MS/S/0122 09/05/2022 13/05/2022
Hot-rolled Steel H-Beam (BS EN
10025-2 Grade S355J0) (Batch 3)
PVC water stop YL/MS/S/0123 12/05/2022 14/06/2022

Dowel Bar YL/MS/S/0124 23/05/2022 01/06/2022

PVC water stop for Retaining wall stem YL/MS/S/0126 06/06/2022 14/06/2022
- expansion &contraction joint
construction
Zinc rich Primer YL/MS/S/0127 06/06/2022 14/06/2022

75mm diameter UPVC Pipe YL/MS/S/0128 07/06/2022 14/06/2022

150mm diameter Sub-soil Drain Pipe YL/MS/S/0129 14/06/2022 27/06/2022

Page 13 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
Non Woven Geo-textile Fabric YL/MS/S/0130 14/06/2022 27/06/2022

Single side Geo-textile YL/MS/S/0131 14/06/2022 27/06/2022

Additional Steel bar suppler certificates YL/MS/S/0132 17/06/2022 27/06/2022

Alternative PVC Water stop YL/MS/S/0135 22/06/2022 27/06/2022

5mm & 16mm thick steel plate YL/MS/S/0136 23/06/2022 16/08/2022

One part Polyurethane sealant YL/MS/S/0137 27/06/2022 14/07/2022

FireWrappingMesh YL/MS/S/0138 30/06/2022 26/07/2022

Inorganic joint filler YL/MS/S/0139 02/07/2022 26/07/2022

Steel rebar (for Superstructure Batch 3) YL/MS/S/0140 06/07/2022 08/07/2022

T20, T25, T32 threaded to M16, M20, YL/MS/S/0141 19/07/2022 25/07/2022


M22, M24 bolt with grade 8 double
nuts & washer
25mm thick steel plate grade S275J0 YL/MS/S/0142 08/07/2022 16/08/2022

150mm diameter Sub-soil Drain Pipe YL/MS/S/0143 08/07/2022 22/07/2022


(Alternative)
Material 12mm steel plate (BS EN1025 Grade YL/MS/S/0144 08/07/2022 16/08/2022
S275J0) (Alternative)
Steel rebar (for Superstructure Batch 4) YL/MS/S/0145 15/07/2022 N/A

254 x 254 x 73kg/m x 12m S355J0 Hot YL/MS/S/0146 22/07/2022 29/07/2022


rolled steel H-beam for hoisting beam
in CLP room
T25 steel bar threaded to M20 bolt with YL/MS/S/0147 04/08/2022 18/08/2022
grade 8 nuts for hoisting beam in CLP
room.
20mm hot rolled steel plate (BS YL/MS/S/0148 29/07/2022 04/08/2022
EN10025 S355J0) for hoisting beam in
CLP room.
Zinc rich primer for Dowel bar of YL/MS/S/0149 04/08/2022 04/08/2022
retaining wall
20mm aggregate (Alternative) for YL/MS/S/0150 05/08/2022 16/08/2022
retaining wall
Additional supplier of steel rebar for YL/MS/S/0151 15/08/2022 05/09/2022
superstructure & external works
Steel Reinforcement Bar YL/MS/S/0152 22/08/2022 05/09/2022
(Superstructure Batch 5)
254 x 254 x 73kg/m x 12m S355J0 Hot YL/MS/S/0153 25/08/2022 02/09/2022
rolled steel H-beam for hoisting beam
in CLP room
Cast-in Anchor channel with T-Head YL/MS/S/0154 29/08/2022 21/09/2022
Bolt
Granular Sub-base (Alternative) YL/MS/S/0155 31/08/2022 08/09/2022

T16 threaded M12bolt with grade 10 YL/MS/S/0156 06/09/2022 20/09/2022


Nuts (double nuts) & Metal Washers
(Batch 4)
Steel Reinforcement Bar YL/MS/S/0157 22/08/2022 05/09/2022
(Superstructure Batch 6)
hot rolled steel plate (12mm, 16mm, YL/MS/S/0158 24/08/2022 18/10/2022
20mm, 25mm) (BS EN10025 S275J0)
(Batch 2)
Steel Reinforcement Bar YL/MS/S/0159 30/08/2022 N/A
(Superstructure Batch 7)
Page 14 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
T32 threaded M30bolt with grade 10 YL/MS/S/0160 24/10/2022 03/11/2022
Nuts (double nuts) & Metal Washers
(Batch 5)
M16 Grade8.8, threaded rod with YL/MS/S/0161 31/10/2022 11/11/2022
grade 10 Nuts (double nuts) & Metal
Washers (Batch 6)
Steel Reinforcement Bar YL/MS/S/0162 14/11/2022 N/A
(Superstructure Batch 8)
Hot-rolled Steel angle for aluminium YL/MS/S/0163 15/11/2022 21/11/2022
blade, lourve, Aluminium Clading
(Batch 1)
Steel angle for all package of 1/F to 8/F YL/MS/S/0164 15/11/2022 29/11/2022
Batch 2)
Flat bar for all package of 1/F to 8/F YL/MS/S/0165 22/11/2022 29/11/2022
(Batch 1)
Embed steel plate for all package of 1/F YL/MS/S/0166 22/11/2022 29/11/2022
to 8/F (Batch 3)
Steel channel for all package of 1/F to YL/MS/S/0167 22/11/2022 29/11/2022
8/F (Batch 1)
Steel I Beam fir all package of 1/Fto YL/MS/S/0168 22/11/2022 29/11/2022
8/F (Batch 1)
Steel I beam for architectural works YL/MS/S/0169 23/11/2022 19/12/2022
Material (Batch 2)
Steel Reinforcement Bar YL/MS/S/0170 12/12/2022 29/11/2023
(Superstructure Batch 9)
Hot rolled staal angle for all package of YL/MS/S/0171 23/12/2022 19/12/2022
1/F to 8/F (Batch 3)
Steel Reinforcement Bar YL/MS/S/0172 09/01/2023 N/A
(Superstructure Batch 10)
Steel Reinforcement Bar YL/MS/S/0173 09/01/2023 N/A
(Superstructure Batch 11)
Steel Reinforcement Bar YL/MS/S/0174 30/01/2023 N/A
(Superstructure Batch 12)
T10,T12, T16, T20, T25, T32, T40 YL/MS/S/0175 02/02/2023 08/02/2023
High Tensile Deformed bar in grade
500B (additional supporter)
Steel plate for Architectural work YL/MS/S/0176 13/02/2023 N/A
(Batch 4)
Steel angle for Architectural YL/MS/S/0177 13/02/2023 N/A
works(Batch 4)
Steel channel for Architectural works YL/MS/S/0178 13/02/2023 N/A
(Batch 2)
Steel H-beam (UC) for Architectural YL/MS/S/0179 13/02/2023 N/A
works (Batch 1)
Steel Reinforcement Bar YL/MS/S/0180 13/02/2023 N/A
(Superstructure Batch 13)
Steel Reinforcement Bar YL/MS/S/0181 13/02/2023 N/A
(Superstructure Batch 14)
Steel angle of Architectural works YL/MS/S/0182 13/02/2023 N/A
(Batch 5)
Steel channel of Architectural works YL/MS/S/0183 28/02/2023 N/A
(Batch 3)
45D 10 175mm slump YL/MS/S/0184 28/02/2023 10/03/2023
45D 10 175mm slump (1) YL/MS/S/0185 01/03/2023 10/03/2023

Page 15 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
Steel Reinforcement Bar YL/MS/S/0186 01/03/2023 N/A
(Superstructure Batch 15)

Steel Reinforcement Bar YL/MS/S/0187 30/03/2023 N/A


(Superstructure Batch 16)
FSP IV Hot Rolled U-Sheet Pile (BS YL/MS/S/0188 30/03/2023 12/05/2023
EN10248 Grade S270 GP) (Batch 5)
Steel Reinforcement Bar YL/MS/S/0189 30/03/2023 N/A
(Superstructure Batch 17)
Steel plate for Architectural works YL/MS/S/0190 10/05/2023
Material (Batch 5)
PVC Water Stop YL/MS/S/0191 17/05/2023
Steel channel for BMU steel frame YL/MS/S/0192 18/05/2023
(Batch 1)
Steel H-Beam for BMU steel frame YL/MS/S/0193 18/05/2023
(Batch 1)
Steel plate for BMU steel frame (Batch YL/MS/S/0194 18/05/2023
1)
Steel Reinforcement Bar YL/MS/S/0195 18/05/2023 N/A
(Superstructure Batch 18)
ITAP for Demolition Works YLC/CHC/F03/00198 16/10/2020 03/11/2020
ITAP for Driven H-Piling Works YLC/CHC/F03/00257 30/10/2020 23/11/2020
ITAP for Sheet Piling Works YLC/CHC/F03/00606 02/03/2021 03/03/2021

ITAP for Construction of Pile Cap YLC/CHC/F03/00891 22/06/2021 13/07/2021


ITAP for ELS Works YLC/CHC/F03/01305 18/10/2021 04/11/2021
ITAP for Backfilling & Compaction YLC/CHC/F03/01306 18/10/2021 04/11/2021
Works
ITAP for Construction of Column, YLC/CHC/F03/01307 18/10/2021 10/11/2021
Beam, Wall & Slab
ITAP ITAP for MIC (structural works) YLC/CHC/F03/01340 30/11/2021 10/12/2021
ITAP for Construction of Precast YLC/CHC/F03/01440 27/01/2011 10/12/2021
Elements including MIC (at Factory)
Minor amendment of ITAP for YLC/CHC/F03/01743 13/01/2022 18/01/2022
construction of pile cap
Minor amendment of ITAP for YLC/CHC/F03/01696 13/01/2022 19/01/2022
construction of column, beam, wall &
slab
ITAP for retaining wall & Fence wall YLC/CHC/F03/02230 17/05/2022 26/05/2022
(Resubmission)
Method Statement for Driven Steel YLC/CHC/F03/00168 07/10/2020 18/12/2020
H-Pile Construction
General Installation Method Statement YLC/CHC/F03/00595 26/02/2021 03/03/2021
for Sheet Piles
Method Statement of Temporary YLC/CHC/F03/00807 25/5/2021 26/5/2021
Removal of Hoarding
Method Statement of Loading Test for YLC/CHC/F03/01941 06/07/2021 05/08/2021
Method Driven H-Piles
Statement General Installation Method Statement YLC/CHC/F03/01101 18/09/2021 10/09/2021
of Steel Sheet Piles commented
Method statement for Tree Felling YLC/CHC/F05/01101 16/08/2021 15/09/2021
Works for Area B (commented)
Method statement of Robotic cutting YLC/CHC/F03/01249 27/09/2021 06/10/2021
for Pile head & Robotic welding for
capping plate
General Installation Method Statement YLC/CHC/F03/01179 08/10/2021 17/09/2021
of Steel Sheet Piles (Rev.2)

Page 16 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
Method Statement of Precast Manhole YLC-CHC-F03/01192 17/09/2021 26/10/2021

Method Statement of Robotic Cutting YLC/CHC/F03/01249


for Pile Head & Robotic Welding for 25/10/2021 06/10/2021
Capping Plate
Method Statement for Backfilling of YLC/CHC/F03/01251 25/10/2021 06/01/2022
Retaining Wall
Method statement of Plate load test. YLC/CHC/F03/01331 22/10/2021 26/11/2021

Method statement for sealing formwork YLC/CHC/F03/01383 03/11/2021 17/11/2021


tie holes
Method Statement of ELS Installation YLC/CHC/F03/01401 09/11/2021 Commented on
30/11/2021
Remedial proposal for plug weld YLC/CHC/F03/01429 17/11/2021 18/11/2021

Method statement for curing of YLC/CHC/F03/01426 15/11/2021 06/12/2021


concrete structural element
Remedial Proposal for general Defects YLC/CHC/F03/01247 15/11/2021 06/12/2021
of Concrete Works
Method Statement of erection of Tower YLC/CHC/F03/01586 16/12/2021 Commented on
Crane (Rev.1) 15/12/2021
Method statement for General YLC/CHC/F03/01516 10/12/2021 07/12/2021
Backfilling (Rev.1)
Submission of Off-site Sampling YLC/CHC/F03/01656 30/12/2021 04/01/2022
Proposal of Steel Plates for Glass Curtain
Wall at Supplier's Certificated Site
Submission of Stock Management Plan YLC/CHC/F03/01671 31/12/2021 Withdrawn on
for Reinforcement Bar – Offsite 20/01/2022
Bending Yard at Kwan Tei
Submission of Method Statement of YLC/CHC/F03/01692 05/01/2022 Commented on
Post-drilled Re-bar 04/02/2022
Submission of Method Statement for YLC/CHC/F03/01748 17/01/2022 21/02/2022
Excavation & Lateral Support
Method Installation
Statement Submission of Method Statement for YLC/CHC/F03/01794 11/02/2022 11/02/2022
structural works of post-installed rebar
Submission of Method statement for YLC/CHC/F03/01870 22/02/2022 24/02/2022
Remedial works with Hilti
RE100/HY/HY200-R
Submission of LB-52 Welding YLC/CHC/F03/01880 24/02/2022 02/03/2022
electrode
Submission of construction joint details YLC/CHC/F03/01884 24/02/2022 for ASD
for G/F (Rev.1) information only
Submission of temporary falsework & YLC/CHC/F03/01888 25/02 2022 Temporary work
timber formwork design for beam & for ASD
slab of G/F (Rev.2) information only
Submission of Timber formwork design YLC-CHC-F03-01913 07/03/2022 Temporary work
for wall & column for ASD
information only
Submission of Temporary works for YLC-CHC-F03-01914 07/03/2022 Temporary work
G/F & 1/F MIC for ASD
information only
Submission of Method Statement for YLC-CHC-F03-01835 09/03/2022 24/03/2022
Tree Planting at Chi Wa Lane
Submission of Method statement of YLC/CHC/F03/01930 11/03/2022 24/03/2022
post-installed rebar for ELS steel
bracket
Submission of Method statement of YLC/CHC/F03/01612 29/03/2022 08/04/2022
Post installed rebar for G/F Bearing
wall near ST-6

Page 17 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
Submission of Preliminary Welding YLC/CHC/F03/02167 03/05/2022 06 05 2022
Procedure Specification for Embed
Fabrication at factory
Method statement of rectification for tie YLC/CHC/F03/02155 29/04/2022 11/05/2022
beam SB52
Incidence report for hacking off YLC/CHC/F03/02244 19/05/2022 20/05/2025
concrete of strap beam SB52.
Placing concrete to replace 200mm YLC/CHC/F03/02431 15/06/2022 24/06/2022
granular sub-base with 98% Relative
compaction requirement
Method statement for rectifying YLC/CHC/F03/02737 26/07/2022 26/07/2022
honeycomb concrete of FS Water Tank

Submission of Method Statement of YLC/CHC/F03/02826 09/08/2022 Withdrawn


Erection of Bamboo Scaffold YLC/CHC/F03/03043 08/09/2022 Withdrawn
YLC/CHC/F03/03100 17/09/2022 28/09/2022
Incident report of honey comb concrete YLC/CHC/F03/02827 09/08/2022 16/08/2022
found on water tank

Incident report & remedial proposal for YLC/CHC/F03/02845 09/08/2022 29/08/2022


Galvanized Dowel bar of Retaining
wall
Proposal for construction of Double YLC/CHC/F03/02931 22/08/2022 06/09/2022
slab at 1/F Transformer & LV Switch
room
Remedial proposal for lifting YLC/CHC/F03/02981 31/08/2022 Withdrawn
Method 26/09/2022
Headroom issue of CLP Transformer YLC/CHC/F03/03045 09/09/2022
Statement
on 2/F
Submission of Method Statement for YLC/CHC/F03/03196 05/10/2022 11/10/2022
Forming wall opening after Concreting
Method statement of retaining wall YLC/CHC/F03/03197 24/09/2022 11/10/2022
cantilever beam (RWCB) & tie beam
construction.
Method statement of retaining wall YLC/CHC/F03/04079 16/02/2023 02/03/2023
cantilever beam (RWCB) & tie beam
construction.
Method Statement of retaining wall YLC/CHC/F03/04207 03/3/2023 09/03/2023
cantilever beam (RWCB) and the
relative tie beam (RWB) construction
Method Statement of post-installed YLC/CHC/F03/04294 03/03/2023 09/03/2023
rebar of general plinth
Submission of Method Statement for YLC/CHC/F03/04290 16/03/2023 24/03/2023
Repairing Concrete Defects on
Structural Elements
Submission of Method Statement for YLC/CHC/F03/04295 18/03/2023 29/03/2023
Post-Installed Rebar of Staircase Corbel
at 2/F to 4/F ST-5

Submission of Remedial Proposal for YLC/CHC/F03/04448 13/04/2023


insufficient concrete cover around
window openings.
Submission of method statement of YLC/CHC/F03/04449 13/04/2023 27/4/202327/4/2023
replacing Dowel bar of façade.
Submission of Method Statement of YLC/CHC/F03/04687 5/5/2023
Concreting Refilling for PF331
Opening

Page 18 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Type of Submission Item YL’s Register No. Submission Approval


Submission /Ref No. Date Date
Submission of Method Statement of YLC/CHC/F03/04472 9/5/2023
Coring Opening at Retaining Wall for
Method Drainage Connection
Statement Submission of Method Statement for YLC/CHC/F03/04567 25/4/2023 4/5/2023
Forming Slab Opening after Concreting
at 1/F

6 Routine Minor Amendment (RMA) Form Issued

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-YL-0001 0001 1. Proposed relocation 26/11/2020 02/12/2020 10/12/2020
BUSM14 & BUSM15 to
Storm Water Pipe Gully
using monitoring detail 2,
since the two pipes could not
be found after 2m deep
excavation; and
2. Proposed adding BUSM17
to monitor the 150mm
diameter fresh water pipe
temporarily to act as
BUSM12, in consideration
of the duration of XP
application for installing
BUSM12.
RMA-YL-0002 0002 Propose relocation BUSM8 to an 03/12/2020 14/12/2020 18/12/2020
adjacent U-channel due to the
collision with piles.

RMA-YL-0003 0003 Propose additional detail of 10/12/2020 17/12/2020 22/12/2020


gantry plinth due to uneven
ground surface.

0004 1. Change to 3mm thick M.S. 12/12/2020 31/12/2020 07/01/2021


RMA-YL-0004 to plate referring to detail ‘1’ of
0007 AB/8238/EW011 and detail
‘C’ of AB/8238/EW013.
(refer to SK-0004);
2. Propose delete B8 due to
collision with B6. (refer to
SK-0005);
3. Change the concrete plinth
height to 1100mm due to site
condition. (refer to
SK-0006);and
4. Change the concrete plinth
width to 350mm due to site
Page 19 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
condition (refer to SK-0007).

RMA-YL-0005 0008 Propose moving concrete plinths 19/12/2020 31/12/2020 07/01/2021


due to collision with trees.
RMA-YL-0006 0013 Temporary change of hoarding at 26/01/2021 02/02/2021 19/02/2021
foundation stage due to collision
with piles.
RMA-YL-0007 0012 Additional Monitoring Points 15/01/2021 27/01/2021 18/02/2021
VCP6-VCP10.
RMA-YL-0008 0014 Relocation of Additional 18/02/2021 19/02/2021 19/02/2021
Monitoring Points VCP8.
RMA-YL-0009 Relocation of sheet piles due to 10/03/2021 17/03/2021 22/03/2021
0015& 0016 collision with PZ2 (DH26) and
PZ3 (DH27).
RMA-YL-0010 0017 Propose relocation monitoring 12/03/2021 08/04/2021 09/04/2021
points VCP1 to 5 to sensitive
structures and water carrying
services

RMA-YL-0011 0018 To specify the steel grade of steel 16/03/2021 22/03/2021 26/03/2021
splice plate for sheet piles.

RMA-YL-0012 0021 Since VM40 at VCP2/2a is out of 26/04/2021 14/05/2021 17/05/2021


order and in consideration of
current piling progress, proposed
monitoring device VM40 at
VCP3/3a relocated to more
sensitive location VCP2/2a.

RMA-YL-0013 0022 Propose placing maximum 7.5kPa 04/05/2021 14/05/2021 Withdrawn


construction materials (maximum on
3 layers of core box) on the catch 21/05/2021
platform of hoarding up to 2/F
superstructure construction.
RMA-YL-0014 0023 Proposed relocation of sheet pile 18/08/2021 18/08/2021 19/08/2021
to suit site condition
RMA-YL-0015 0027 Proposed relocation of sheet pile 20/09/2021 20/09/2021 20/09/2021
0028 to suit site condition

RMA-YL-0016 0029a 1) Change typical pile head 28/09/2021 04/10/2021 Withdrawn


To details on
0040a 2) Change Thickness of pile 05/10/2021
cap

RMA-YL-0017 0041a 1) Change typical pile head 29/09/2021 04/10/2021 Withdrawn


0042a details on
2) Change Thickness of pile 05/10/2021
cap

RMA-YL-0018 0043 Increase depth of pile cap PC21 08/10/2021 11/10/2021 15/10/2021

Page 20 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
0044 to suit site conditions.
RMA-YL-0019 0045 Increase depth of pile cap PC21 08/10/2021 08/10/2021
0046 to 1300mm to suit site conditions.
0047 Increase the amount of steel rebar
0048 for cap & tie beam
RMA-YL-0020 0027a Relocation of steel sheet pile due Withdrawn
0028a to conflict with PZ1
piezometer/standpipe
RMA-AECOM-0001 0009 1. Change the piling Layout of 05/01/2021 05/01/2021 06/01/2021
PC14 to tally with 1st
AIP/DDA foundation
submission.
2. Propose relocating Trial Pile
PC20-P1 to PC14-P6 due to
pre-boring will be required
for the original proposed
trial pile.
3. Propose relocating Trial Pile
PC20-P5 to PC14-P1 due to
pre-boring will be required
for the original proposed
trial pile.
RMA-AECOM-0002 0010 Propose relocating Trial Pile 06/01/2021 06/01/2021 07/01/2021
PC14-P6 to PC14-P7 due to
unforeseeable ground condition.
RMA-AECOM -0003 0011 Update PC28 to tally foundation 26/01/2021 26/01/2021 26/01/2021
submission. Propose relocating
Trial Pile PC01-P1 to PC28-P5 &
PC-08-P7 to PC23-P7.

RMA-AECOM -0004 0024 1) Change Façade Type 1a span 08/09/2021 09/09/2021 09/09/2021
to 0026 length
2) 2)Revise Upper & Lower
Beam Main bar size from
T16 to T12

RMA-AECOM -0005 0037 3) Change typical pile head


to details 29/09/2021 29/09/2021 29/09/2021
0040 4) Change Thickness of pile
cap
5) Change Depth of pile cap,
pile
Embedment length, c.o.l.
Tentative pile length from
c.o.l.
RMA-AECOM -0006 0045 Change co-ordinates of sheet pile
0046 setting out points from 12,18 to 15/10/2021 15/10/2021 15/10/2021
31, 34, 3.3, 3.4, 3.6 to 3.8

RMA-YL-0021 0049 Enlarge the excavation area at 20/10/20210 20/10/20210


ELS stage 3

Page 21 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-YL-0022 0050 Two concrete plinths added to 22/10/2021 22/10/2021 08/11/2021
reduce the span of member to
meet with ASD standard drawing
RMA-YL-0023 0045 1) Change co-ordinates of sheet 25/10/2021 25/10/2021 25/10/2021
0046 pile setting out points from
29, 30,& some points from
3.9 to 4.2
2) Change sheet pile type from
S355 FSPIII to S270 FSPIV
from setting out point 20-22.
RMA-YL-0024 0045a Adding breaking load details 24/11/2021 24/11/2021 24/11/2021
0046a for M30 grade 10.9 cast-in
0052 bolt to be 561KN in testing.
RMA-YL-0025 0055 Minor amendment on 09/12/2021 09/12/2021 09/12/2021
0070 changing rebar size & beam
depth
RMA-YL-0026 0072 Change the side bar of 14/12/2021 14/12/2021 14/12/2021
0073 SB8/SB24b, Change the
beam depth of SB9,
Change the top bar of B2 &
B4

RMA-YL-0027 0074 Adding breaking load details 14/12/2021 14/12/2021 14/12/2021


for M30 grade 10.9 cast-in
bolt to be 561KN in testing.
RMA-YL-0028 0072a Change the side bar of strap 17/12/2021 17/12/2021 21/12/2021
0073a beam SB9,
Add one more drawing for beam
B3, B4
Revised top & bottom bar of
beam B1 & B2
RMA-AECOM -0007 0055 Updated setting out point 2.4 25/11/2012 25/11/2021 02/12/2021
to 3.2
Updated Design slope profile
along Pak Wo Road
2 nos of notes for dewatering
& Typical bridge over details

RMA-AECOM -0008 0053 Revised the trimming details 23/11/2021 23/11/2021 21/12/2021
of the manhole when
opening greater than 500mm
RMA-AECOM -0009 - Provide RC checking of Pile 08/12/2021 08/12/2021 10/12/2021
cap for the linear
displacement of the piles.
Additional reinforcement is
not necessary.

RMA-AECOM -0010 0071 Revise the typo of links 13/12/2021 13/12/2021 14/12/2021
details of SB4
Delete side bar details of
SB14
Reduce the thickness of
SB14

Page 22 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-AECOM -0011 0074a, 0075 - 0080 Revised design toe level of 24/11/2021 24/11/2021 03/01/2022
steel sheet piles due to the
underground obstruction
encountered on site.
RMA-AECOM -0012 Checking the structural 17/12/2021 17/12/2021 17/01/2022
- adequacy pile cap steel bar
due to out of tolerance steel
H pile verticality
RMA-AECOM -0013 0074b Revised the embedment 12/01/2022 12/01/2022 13/01/2022
length of cast in bolt to
900mm
Increase the no. of cast-in
bolt to 14 number
RMA-AECOM -0014 0082 Revised side bar details of 30/12/2021 30/12/2021 31/12/2021
strap beams SB7 & SB7a.
RMA-AECOM -0015 Checking the structural 12/01/2022 12/01/2022 24/01/2022
- adequacy pile cap steel bar
due to out of tolerance steel
H pile verticality
RMA-AECOM -0016 0075a, 0078a, Revised the steel waling 17/01/2022 17/01/2022 08/02/2022
0079a levels (top layer) and carried
out the stability check of the
steel sheet piles.
RMA-AECOM -0017 0099, 0070a Revised the bearing wall 15/01/2022 15/01/2022 withdrawn
details & position of the wall
to comply with the General
Building Plan.
RMA-AECOM -0018 0051a Revised design toe level of 07/02/2022 07/02/2022 10/02/2022
steel sheet piles to avoid
conflict with existing
underground pipes & carried
out the stability check of the
steel sheet piles.
RMA-AECOM -0019 0063a, Checked the adequacy of 21/02/2022 21/02/2022 25/02/2022
0065a, pile cap PC-36, PC-37 steel
0070a bar as a result of column
C36, C37 revision.
Revised the thickness of pile
cap PC-28 from 1250 to
1300mm.
RMA-AECOM -0020 0079b, Revised design toe level of 11/03/2022 11/03/2022 14/03/2022
0102 steel sheet piles due to the
underground obstruction
encountered on site.
RMA-AECOM -0021 0074e, Revised the steel bracket 10/03/2022 10/03/2022 25/03/2022
0075b details to reinforced concrete
details.

RMA-AECOM -0022 0 Checking the structural 07/04/2022 07/04/2022 12/04/2022


adequacy pile cap steel bar
due to out of tolerance steel
H pile verticality
RMA-AECOM -0023 0102a ELS minor amendment on 27/04/2022 27/04/2022 12/05/2022
0079c steel sheet pile design toe

Page 23 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
level.

RMA-AECOM -0024 070b, 0144-0149 1) Proposed 500mm thick 27/04/2022 28/04/2022 12/05/2022
bearing wall carried by
strap beam SB52 added.
Ground Beams setting
out &slab top level
updated.
RMA-AECOM -0026 0143a, 0051c Revised design toe level of steel 12/07/2022 13/07/2022 18/07/2022
sheet piles due to the underground
obstruction encountered on site.
RMA-AECOM -0027 0149a, 0161-0167 Propose additional slab opening, 03/08/2022 04/09/2022 18/08/2022
hanger wall, bearing wall detail
and screen wall detail.
RMA-AECOM -0028 1)150mm diameter sub-soil drain 16/08/2022 16/08/2022 26/08/2022
is proposed as UPVC perforated
pipe in leakage collection system
2)Addition protection details for
the weephole is proposed.
RMA-AECOM -0029 SK-0172, SK-0173, Revise column C7 (1/F, 2/F), C8 02/09/2022 02/09/2022 13/09/2022
SK-0174, SK-0175 & (1/F, 2/F), C13 (2/F), C14 (1/F,
SK-0177, SK-0178, 2/F), C19 (2/F) Details
SK-0179
RMA-AECOM -0030 Checking the structural adequacy 29/08/2022 30/08/2022 11/10/2022
- pile cap steel bar due to out of
tolerance steel H pile verticality

RMA-AECOM -0031 0177a Revised the excavated level for 06/09/2022 06/09/2022 06/09/2022
steel wailing and strut (CS4C,
CS4D, CS4E, CS4F)
RMA-AECOM -0032 0187,0188 Amend the 2/F Framing Plan 15/09/2022 15/09/2022 31/10/2022

RMA-AECOM -0033 0166a,0189, 0190 Amend the Wall R.C. Detail 16/09/2022 16/09/2022 26/09/2022
GF-3F
RMA-AECOM -0034 0164a, 0192 Revised the beam size of 1B58 27/09/2022 27/09/2022 29/09/2022

RMA-AECOM -0035 0193,0194, Revised RC details of Beam 28/09/2022 13/10/2022 09/11/2022


0195 3B41, 3B160, 3B161, 3B167,
3B168
RMA-AECOM -0036 0196-0200 Amended the column RC details 30/09/2022 12/10/2022 12/10/2022
of PC-2F
RMA-AECOM -0037 0144a,0146a, Revised G/F framing plan, RC 13/10/2022 13/10/2022 31/10/2022
0147a details of GS27, GS27a, GB54
RMA-AECOM -0038 0164a, 0165a, Revised 1/F framing plan, RC 14/10/2022 14/10/2022 26/10/2022
0201, 0202, details of
0205, 0206 1S109a, 1S109b, 1S134, 1B183a,
1B212, 1B213, 1B337a
RMA-AECOM -0039 0203-0204 Revised the Precast Façade RC 11/10/2022 13/10/2022 Withdrawn
details of PF332.
RMA-AECOM -0040 0050a, 0207 Amend the Hoarding Layout and 13/10/2022 13/10/2022 26/10/2022
Detail
RMA-AECOM -0041 0144b, 0191a, Revise the r.c. detail for G/F 26/10/2022 26/10/2022 07/12/2022
0208-0210 Sprinkler Water Tank.

Page 24 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-AECOM -0043 0180c Propose the R.C. plinth detail 9/11/2022 9/11/2022 29/11/2022

RMA-AECOM -0044 0050b, 0216 Amend the Hoarding Layout and 21/11/2022 21/11/2022 28/11/2022
Detail

RMA-AECOM -0045 0050c Amend the Hoarding Layout and 08/12/2022 08/12/2022 withdrawn
Detail
RMA-AECOM -0046 0180d Propose the Sunken Slab Detail 30/12/2022 03/01/2023 21/02/2023

RMA-AECOM -0047 0220 Revise façade typical details. 04/01/2023 06//01/2023 21/03/2023

RMA-AECOM -0048 0162a Corbel typical details added 16/01/2023 18/01/2023 20/02/2023
Updated hanger wall RC details

RMA-AECOM-0049 225 1. Propose the Sunken Slab 28/02/2023 28/02/2023 08/03/2023


Extent and Location at 6/F
RMA-AECOM-0050 0228-0231 1. Update Details for Façade Type 21/02/2023 21/02/2023 09/03/2023
PF312, PF315
RMA-AECOM-0051 '0241 1. Add detail for Beam 5B185 21/02/2023 21/02/2023 22/02/2023

RMA-AECOM-0052 '0248-0251, 0222a 1. Update Details for Slab 27/02/2023 27/02/2023 10/03/2023
Openings (5/F)
RMA-AECOM-0053 '0286-0289, 0308, 1. RMA for 6/F slab 02/03/2023 02/03/2023 08/03/2023
0225a
RMA-AECOM-0054 '0290-0294, 0296 1. RMA for 7/F slab 03/03/2023 03/03/2023 09/03/2023

RMA-AECOM-0055 SK-0221a, SK-0318 1. Revise the 4/F slab R.C. details 06/03/2023 06/03/2023 10/03/2023
to SK-0324 according to the revised CBWD
opening
RMA-AECOM-0056 'SK-0225b 1. 6/F sunken slab 10/03/2023 10/03/2023 10/03/2023

RMA-AECOM-0057 'SK-0217a, SK-0325 - 1. Revise the 3/F slab R.C. details 13/03/2023 13/03/2023 04/04/2023
SK-0332 according to the revised CBWD
opening
RMA-AECOM-0058 'SK-0218 & 0219, 1. Revise the 2/F slab R.C. details 18/03/2023 18/03/2023 31/3/2023
SK-0333 to 0336 according to the revised CBWD
opening
RMA-AECOM-0059 'SK-0225c, SK0297a, 1. Revise the RC detail of 6F & 17/03/2023 17/03/2023 24/3/2023
SK302a-305a, 7F Beam due to the discrepancy
SK-311a of framing plan and the RC detail.
SK-313a-317a
RMA-AECOM-0060 'SK-0164c, 1. Revise the 1/F slab R.C. details 15/03/2023 15/03/2023 Comment on
SK-0165b, SK-0337, according to the revised CBWD
SK-0205a, SK-0206a, opening 20/3/23
SK-0340,

RMA-AECOM-0061 'SK-0338 & SK-0339 Propose the External Wall RC 17/03/2023 17/03/2023 31/3/2023
Detail
RMA-AECOM-0062 'SK-0341, SK0343, Amend the thickness of 1LS27 & 17/03/2023 17/03/2023 31/3/2023
SK-0344 1LS27

Page 25 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-AECOM-0063 'SK-0216a, 0268a, 1. Revise R.C detail for beams 23/03/2023 22/03/2023 Comment on
0282a, 0359, 0360 & located in 1/F, 2/F & 4/F 31/3/23
0361
RMA-AECOM-0064 'SK-0301a, 0302b, 1. Revise R.C. detail for beams 29/03/2023 29/03/2023 31/3/2023
0311b, 0315b, 0406 located in 7F and 7F framing plan
RMA-AECOM-0065 'SK-0409 1. Addition of R.C. details of 06/04/2023 06/04/2023 14/4/23
catch pit
RMA-AECOM-0066 'SK-0311c 1. Revise sunken slab location at 12/04/2023 12/04/2023 21/4/23
7F framing plan
RMA-AECOM-0067 'SK-0050c, 0008a, 1. Revise hoarding structural 03/05/2023 03/05/2023 Comment on
0437 design due to modification 18/5/23
of hoarding layout for water
lead in connection work by
WSD

RMA-AECOM-0068 '0280a, 0281a 1. Revise 8F Beam Column Joint 11/05/2023 11/05/2023 16/05/2023
design of C21, C25, C26, C38,
C39, C42, C43 due to
modification of connecting beam
level
RMA-AECOM-0069 'SK-0444 to 0448, 1. Revise 8F Beam and Slab R.C 12/05/2023 12/05/2023 16/05/2023
SK-0452 to 0459 Detail and Framing Plan.
RMA-YL-0029 056a 1) Change the rebar size of 22/12/2021 22/12/2021 15/05/2023
0058 PC08, PC12, and
0068a SB17&SB10.
0071 2) Delete drg. of PC11 from
0081 SK-56
3) Revise shear links of
SB5,SB15& SB14.
RMA-YL-0030 0083 - 0098 1) Change steel links of 01/06/2021 01/07/2021 12/01/2022
column from type E to type
N.
2) Add note no. 3
RMA-YL-0031 0082a 1) Amended the side bars from 13/01/2021 14/01/2021 12/01/2022
20 no. to 18 no.

RMA-YL-0032 0080a 1) Details for filling the gap 13/01/2021 14/01/2021 15/01/2021
between
Steel waling & steel sheet
pile wall added.
RMA-YL-0034 0074d, Revised the connection 10/03/2022 10/03/2022 14/04/2022
0100a details of the main &
secondary steel struts.
RMA-YL-0035 Steel bar details of 100mm 11/03/2022 11/03/2022 13/03/2022
- thick partition wall revised.
RMA-YL-0036 1) Revised the cut off level & 30/03/2022 30/03/2022 31/03/2022
0044a tentative pile length of steel
piles for Pile cap no. PC28
RMA-YL-0037 0104 1) Delete the anchor bar from 07/04/2022 07/04/2022 12/04/2022
precast wall type PF115
RMA-YL-0038 SK-0150 Types of hose reel added to 18/05/2022 19/05/2022 20/05/2022
SK-0151 MIC detail drawing.

Page 26 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-YL-0039 SK-0152 Typical details of 30/05/2022 01/06/2022 15/06/2022
strengthening the steel
walings& struts openings
so as to allow steel rebar to
pass through.
RMA-YL-0040 SK-0153 Revised rebar details of 30/05/2022 01/06/2022 15/06/2022
middle wall & thickness of
external wall.
RMA-YL-0041 SK-0154 to Revised the setting out of 13/07/2022 13/07/2022 20/07/2022
SK-0157 RWC21 to RWC28,
RWC8to RWC20
RMA-YL-0042 SK-0158 to Depth of Manhole Type F1 19/07/2022 19/07/2022 20/07/2022
SK-0159 revised.

RMA-YL-0043 Revised the max depth of 13/07/2022 13/07/2022 20/07/2022


SK-0160 manhole Type F1 in
accordance with DSD
standard drawing
RMA-YL-0044 SK-155a Revised setting out point of 26/07/2022 27/07/2022 03/08/2022
RWCB61 to avoid conflict
with steel strut
RMA-YL-0045 SK-161 Typical details of additional 29/07/2022 29/07/2022 Withdrawn
rebar for the 75mm On
non-structural part added. 26/08/2022

RMA-YL-0046 SK-102Bb, 170, 171 Proposed dividing Stage 7 24/08/2022 24/08/2022 26/08/2022
ELS working area into
Area A & Area B
RMA-YL-0047 SK-0082a,SK-0145a, Add lap length for 24/08/2022 24/08/2022 25/08/2022
construction joint of SB57,
SK-0176 SB62 & SB63

RMA-YL-0048 SK-155b Additional Non-Structural 27/08/2022 27/08/2022 29/08/2022


Reinforced Concrete to
Facilitate the Installation of
Waterstop at C.J of
Retaining Wall.
RMA-YL-0049 SK-180 Proposed further 05/09/2022 08/09/2022 13/09/2022
demarcation of stage 7 els
works into area A and B.
RMA-YL-0050 SK-168a Update the E.J an\d C.J 29/08/2022 29/08/2022 29/08/2022
Detail for Wall Base at
Retaining Wall
RMA-YL-0051 SK-186 propose a new typical 06/09/2022 06/09/2022 09/09/2022
drawing for partition wall
base

RMA-YL-0052 SL-0180a Revised typical details of 19/09/2022 14/10/2022 25/10/2022


plinth
(height between 100 mm -
200mm)
RMA-YL-0053 SL-0168b E.J. & C.J. details for wall 21/9/2022 14/10/2022 02/01/2023
stem of retaining wall
updated.

Page 27 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-YL-0054 SK-0062c Add lap length for 5/10/2022 13/10/2022 13/10/2022
SK-0073b construction joint of SB57,
SB62 & SB63.
RMA-YL-0055 SK-0073C Add lap length for 11/11/2022 01/11/2022 01/11/2022
SK-0082d construction joint of SB55,
Sk-0145b SB66& SB71
RMA-YL-0056 SK-0212 Revise the R.C Detail of 31/10/2022 31/10/2022 31/10/2022
1B151 & 1B152.
RMA-YL-0057 SK-0021a Add 5 more Ground 04/11/2022 04/11/2022 07/11/2022
Settlement Monitoring
(GSM) Point for better
monitoring theground
settlement during the edge
beam construction
RMA-YL-0058 SK-0213 Add typical detail for the 08/11/2022 08/11/2022 09/01/2023
mass fill concrete staircase.
RMA-YL-0059 SK-0180b Propose to revise the steel 17/11/2022 17/11/2022 21/11/2022
mesh for "Typical RC
Plinth Detail” – the plinth
height between 100 to
200mm" from A252 to
A193
RMA-YL-0060 SK-0223 & SK-0224 1. Propose to revise the layout 18/02/2023 18/02/2023 10/03/2023

and detail of fence wall footing


type 8a

RMA-YL-0061 SK-0231 - SK0240 Beam R.C details revised: 26 no. 02/02/2023 02/02/2023 08/03/2023
Beam of 5F
RMA-YL-0062 SK-0181 Beam R.C details revised: 10 no. 02/02/2023 02/02/2023 withdrawn
Beam of 5F
RMA-YL-0063 SK-0226 Revise the RC detail of max. span 10/02/2023 10/02/2023 22/02/2023
of RWCB from 1500 to 1750

RMA-YL-0064 SK-0180d Propose the 1m height RC plinth 10/02/2023 10/02/2023 27/02/2023


detail also apply with the
retaining wall RC plinth
RMA-YL-0065 SK-0243, SK-0242 24/02/2023 24/02/2023 10/03/2023
Bearing wall type & RC
SK-0223a details revised

RMA-YL-0066 SK-0162b 1. Add typical detail of 24/02/2023 24/02/2023 21003/2023

structural R.C 75mm cover.

RMA-YL-0067 SK-0252 to SK-0258 R.C. details of precast 24/02/2023 24/02/2023 withdrawn


façade revised.
RMA-YL-0068 SK-144d, SK-188a the external pedestrian 01/03/2023 01/03/2023 06/03/2023
ramp and FTNS Cable
Trench with Chequer Plate
will be defined as mass
RMA-YL-0069 SK-0232 to SK0240, 1. Due to the difficulty of 01/03/2023 01/03/2023 02/03/2023
SK0244 to SK-0246, rebar fixing, we would like
SK-0276 to SK-0285 to revise the R.C details of

Page 28 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
column and wall from 6F to
9F, all Type E links will be
revised as Type F links
RMA-YL-0070 SK-0299 & SK-300 1. Due to the drawing 28/02/2023 28/02/2023 10/03/2023
discrepency with
Architecture, we would like
to revise the R.C details of
Façade PF529, PF431,
PF532 &
RMA-YL-0071 SK-0342, SK-0345 to 1. Revise the rebar lapping 04/03/2023 04/03/2023 10/03/2023
SK-0358 detail of 6F & 7F Beam
and 6F slab due to the
difficulty of rebar fixing
and drawing discrepancy.
RMA-YL-0072 SK-0295 1. App the lappings for R.C 10/03/2023 10/03/2023 10/03/2023
detail of 2LS13
RMA-YL-0073 SK-0298 1. Revise the general 10/03/2023 10/03/2023 10/03/2023
concrete reuqirement
RMA-YL-0074 SK-0162c 1. Revise typical hanger 10/03/2023 10/03/2023 16/05/2023
wall R.C. details
RMA-YL-0075 SK-0342, SK-0345 to Amend R.C detail of 11/03/2023 11/03/2023 30/03/2023
SK-0358 PF501, PF502, PF503,
PF506, PF507, PF511,
PF530, PF504, PF505, &
PF533
RMA-YL-0076 (SK-0363, SK-0113a Amend R.C detail of 21/3/2023 24/3/2023 29/3/2023
to SK-0119a, PF115, PF116, PF117,
SK-0123a to PF118, PF119, PF120,
SK-0128a, SK-0363 PF121, PF122, PF123,
to 0370) PF127, PF 128,
RMA-YL-0077 (SK-0138a to 1. Amend the 2/F Façade 22/3/2023 24/3/2023 29/3/2023
SK0142a, SK-0371 to Layout Plan
SK-0378)
RMA-YL-0078 (SK-0382 - SK-0404), 1. Amend the R.C detial of 3/4/2023 3/4/2023 3/4/2023
PF601, PF602, PF603,
PF604, PF605, PF606,
PF607, PF611, PF621,
PF622, PF623,
RMA-YL-0079 (SK-0021b) Due to the construction of 31/3/2023 13/4/2023 21/04/2023
retaining wall, we would
like to propose to delete the
monitoring points of PZ-2
&
RMA-YL-0080 SK-0437 to 0443, 1. Add the lappings for 8/F 05/05/2023 05/05/2023 19/05/2023
SK-0350a, SK-0394a, slab R.C. details according
SK-0395a, SK-0397a, to the construction joint
SK-0417a, SK-0398a,
SK-0399a, SK-0352a,
SK-0403a,
RMA-YL-0081 SK-0291a, SK-0409, Add the lappings for 7/F 28/3/2023 30/3/2023 31/3/2023
SK-0410 slab R.C. details according
to the construction joint

Page 29 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Submission Date

RMA No. SK No. Amendment Descriptions ArchSD


To To Acknowledge
Designer/ ArchSD Date
Design
Checker
RMA-YL-0082 SK-0422 to SK-0434, 1. Amend the R.C detail of 31/3/2023 13/4/2023 19/04/2023
SK-0348a PF701, 702, 703, 704, 705,
706, 707, 801, 802, 803
RMA-YL-0083 SK-0444 to SK-0448 1. Add the lappings for 8/F 05/5/2023 05/5/2023 withdrawn
slab R.C. details according
to the construction joint

7 Concrete Cube Compressive Strength Test Reports


Summary of test reports - See APPENDIX CN1
A) Summary of 28days Concrete Cube Strength, Concrete Grade – 45D/20 + PFA, ,MixID is K0145D240
Cast in-situ concrete on site with statistical analysis of concrete compressive strength
B) Summary of 28days Concrete Cube Strength, Concrete Grade – 45D/20, MixID is K1945D120
Cast in-situ concrete on site with statistical analysis of concrete compressive strength
C) Summary of 28days Concrete Cube Strength, Concrete Grade – 45D/20, MixID is K2345D010
Cast in-situ concrete on site with statistical analysis of concrete compressive strength
D) Concrete Grade – 45D/20 + PFA MixID is K1945D070
Cast in-situ concrete on site with statistical analysis of concrete compressive strength
E) Concrete Grade – 45D/20 MixID is Y0145D040
YLW Precast Concrete manufactured at factory in mainland China with statistical analysis of concrete
compressive strength.
F) Concrete Grade – 45D/20 + GGBS MixID is Y0145D030
YLW Precast Concrete manufactured at factory in mainland China with statistical analysis of concrete
compressive strength.

8 Site Memorandum Issued


Site Memo No. Issue Date Subject Action/Reply
CHC/SM/001 23/11/2020 Approval to the Use of Steel H-Piles (Batch 1 & Batch NA
2)
CHC/SM/002 11/01/2021 Approval to the Use of 16mm Steel Plate (Batch 1) NA

CHC/SM/003 23/02/2021 Approval to the Use of Steel H-Piles (Batch 3) NA

CHC/SM/004 16/03/2021 Approval to the Use of Steel Sheet Pile (Batch 1)& NA
12mm Steel Plate (Batch 1)
CHC/SM/005 19/03/2021 Approval to the Use of Steel H-Piles (Batch 4) NA

CHC/SM/006 15/06/2021 Approval to the Use of Steel H-Piles (Batch 5) NA

Page 30 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Site Memo No. Issue Date Subject Action/Reply


CHC/SM/007 20/07/2021 Approval to the Use of Steel Sheet Pile (Batch 2) NA
&Steel Plate/Steel Angles (Batch 1)
CHC/SM/008 08/10/2021 Precautionary Measures for Tropical Storm Lionrock NA
CHC/SM/009 12/10/2021 Precautionary Measures for Severe Tropical Storm NA
Kompasu
CHC/SM/010 12/10/2021 Approval to the Use of FSPIII Steel Sheet Piles (Batch NA
3)
CHC/SM/011 12/10/2021 Approval to the Use of Hot Rolled Steel Plate (50mm NA
thick)(Batch 1)
CHC/SM/012 12/10/2021 Approval to the Use of Steel Reinforcing Bar for Pile NA
Cap (Batch 1)
CHC/SM/013 27/10/2021 Approval to the Use of steel fabric (B503) for the NA
reinforced concrete carriageway
CHC/SM/014 07/12/2021 Approval to the Use of Hot Rolled Steel Plate (10, 20, NA
25mm thick)
CHC/SM/015 18/12/2021 Approval to the Use of Structural Steel Sections NA

CHC/SM/016 03/01/2022 Approval to the Use of Steel Reinforcing Bar for Pile NA
Cap (Batch 3)
CHC/SM/017 13/01/2022 Approval to the Use of FSPIII Steel Sheet Piles NA

CHC/SM/018 18/01/2022 Approval to the Use of Hot Rolled Steel Plate (50mm NA
thick)(Batch 2)
CHC/SM/019 18/01/2022 Approval to the Use of Steel Reinforcing Bar for NA
Precast Concrete Units manufactured by YLW Concrete
Precast Products Company Ltd. in mainland China.
CHC/SM/020 28/01/2022 Approval to the Use of steel fabric (C503 & A193) for NA
on grade concrete slab construction.
CHC/SM/021 28/01/2022 Approval to the Use of Structural Steel Sections -150 x NA
75 steel channel
CHC/SM/022 29/04/2022 Approval to the Use of steel fabric (A193& C503) for NA
on grade concrete slab construction.
CHC/SM/023 02/06/2022 Approval to the Use of steel fabric (A193) for on grade NA
concrete slab construction.
CHC/SM/024 08/06/ 2022 Pile No.C30 – Concreting in Rainy day under Red NA
Rainstorm Warning
CHC/SM/025 16/06/2022 Approval to the Use of Structural Steel Sections NA

CHC/SM/026 02/07/2022 Precautionary Measures for Severe Tropical Storm NA


Chaba
CHC/SM/027 16/06/2022 1/F – Concrete Defect of FS Water Tank YL replied on 15/07/2022

CHC/SM/028 26/07/2022 Approval to the Use of Steel Reinforcing Bar for Pile NA
Cap (Batch 4)
CHC/SM/029 26/07/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 1)
CHC/SM/030 26/07/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 2)
CHC/SM/031 26/07/2022 Approval to the Use of Hot Rolled Steel Plate (16mm, NA
20mm thick) SP-7
CHC/SM/032 24/08/2022 Precautionary Measures for severe Tropical Storm NA
Ma-On
CHC/SM/033 12/10/2022 Approval to the Use of Structural Steel Plates (SP-8, NA
SP-9)
CHC/SM/034 17/10/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 3)
CHC/SM/035 17/10/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 4)
Page 31 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Site Memo No. Issue Date Subject Action/Reply


CHC/SM/036 18/10/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 5)
CHC/SM/037 18/10/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 6)
CHC/SM/038 19/10/2022 Approval to the Use of Structural Steel Sections N/A
254x254x132 kg/m
CHC/SM/039 26/10/2022 Pull out test report of threaded rod & nut (Batch 1) N/A
Bolting assemblies proposed for Glass wall & canopy.
CHC/SM/040 26/10/2022 Pull out test report of threaded rod & nut (Batch 2) N/A
Bolting assemblies proposed for Glass wall & canopy.
CHC/SM/041 26/10/2022 Pull out test report of threaded rod & nut N/A
Bolting assemblies proposed for Fence Wall.
CHC/SM/042 26/10/2022 Pull out test report of threaded rod & nut N/A
Bolting assemblies proposed for Hoisting Beam in
Transformer Room
CHC/SM/043 14/11/2022 Pull out test report of threaded rod & nut (14/11/2022) N/A
Bolting assemblies proposed for steelwork of this
building project.
Notice of non-conformance work – 3/F Floor Slab steel fixing
CHC/SM/044 28/11/2022 (Gridline 1 to 2, E to F)
YL replied on 28/11/2022
1/F Beam & slab construction – Working at height without
CHC/SM/045 01/12/2022 safe working platform
YL replied on 05/12/2023

Pull out test report of threaded rod & nut (Batch 5 & 6)
CHC/SM/046 16/12/2022 Bolting assemblies proposed for steel work of this building
N/A
project.
Test Report of Structural Steel Sections (Customer Request
CHC/SM/047 03/01/2023 No. SA-2)
N/A
Approval to the Use of Steel Reinforcing Bar for
CHC/SM/048 04/01/2023 Superstructure construction (Batch 7)
N/A
Test Report of Steel Reinforcing Bar for Superstructure
CHC/SM/049 04/01/2023 construction (Batch 8)
N/A

CHC/SM/050 19/01/2023 Notice of non-conformance work – column C30 YL replied on 20/01/2023


C31(4/F to 5/F) Fixing of steel bar
CHC/SM/051 19/01/2023 Notice of non-conformance work – Floor slab concrete YL replied on 20/01/2023
not cured (17/01/2023)
CHC/SM/052 31/01/2023 Notice of non-conformance work – 4/F -5F Hanger & YL replied on 04/02/2023
Parapet Wall steel fixing (Gridline 4-6, H-J)
CHC/SM/053 01/02/2023 Notice of non-conformance work – 4/F -5F CoreWall YL replied on 04/02/2023
W6 steel fixing (Gridline 5-H)
CHC/SM/054 09/02/2023 Retaining Wall Cantilever beam (RWCB ) & Tie YL replied on 10/02/2023
beam (RWB) temporary work construction.
CHC/SM/055 10/02/2023 Notice of non-conformance work –Floor Slab concrete YL replied on 10/02/2023
not cured (10/02/2023)
CHC/SM/056 10/02/2023 5/F - Concrete Defect of Column YL replied on 13/02/2023

CHC/SM/057 11 02 2023 4/F – Anchor bolt details for steel channels supporting YL replied on 13/02/2023
steel scaffold at shaft opening
CHC/SM/058 11/02/2023 5/F – Steel fixing of Façade Type PF519 , PF520 & YL replied on 16/02/2023
Concrete Post
CHC/SM/059 13/02/2023 5/F – Steel fixing of Partition wall (100mm thick) YL replied on 14/02/2023

CHC/SM/060 13/02/2023 Reminder for 5/F, steel fixing of Façade wall no. PF520 YL replied on 14/02/2023

CHC/SM/061 14/02/2023 Reminder for Steel Fixing Works – Substandard Steel YL replied on 14/02/2023
link is not allowed to be used for construction
CHC/SM/062 13/02/2023 5/F – Steel fixing of Façade Type PF516 to PF518 & YL replied on 14/02/2023
Concrete Posts
CHC/SM/063 13/02/2023 5/F – Steel fixing of Bearing wall (200mm thick) YL replied on 14/02/2023

CHC/SM/064 14/02/2023 Reminder for 5/F, steel fixing of Façade wall no. PF513 YL replied on 14/02/2023

Page 32 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Site Memo No. Issue Date Subject Action/Reply


CHC/SM/065 14/02/2023 5/F – Steel fixing of Façade Type PF528 & Concrete YL replied on 16/02/2023
Post
CHC/SM/066 15/02/2023 5/F – Steel fixing of Partition Wall (150mm thick) YL replied on 17/02/2023

CHC/SM/067 15/02/2023 5/F – Steel fixing of Bearing wall at staircase ST-5 YL replied on 24/02/2023
(200mm thick)
CHC/SM/068 15/02/2023 5/F – Steel fixing of Façade Type PF529 , PF530 & YL replied on 16/02/2023
Concrete Posts
CHC/SM/069 15/02/2023 5/F – Steel fixing of Façade Type PF529 , PF530 & YL replied on 16/02/2023
Concrete Posts
CHC/SM/070 15/02/2023 G/F - Concrete Defect of External Wall YL replied on 01/03/2023

CHC/SM/071 16/02/2023 Test Report of Structural Steel Sections (Customer N/A


Request No. SA-4)
CHC/SM/072 17/02/2023 G/F – Steel fixing for R.C. Plinth at Pump Room YL replied on 20/02/2023

CHC/SM/073 17/02/2023 2/F - Concrete Defect of Internal Wall YL replied on 24/02/2023

CHC/SM/074 17/02/2023 2/F - Concrete Defects of internal Wall (Honeycomb) YL replied on 24/02/2023
are covered up without carrying out an agreed repair
work inspection procedures
CHC/SM/075 20/02/2023 G/F - Concrete Defect of Internal Wall ( Clinical waste YL replied on 24/02/2023
storage room)
CHC/SM/076 20/02/2023 G/F - Concrete Defect of Internal Wall ( Chemical YL replied on 24/02/2023
waste store room)
CHC/SM/077 21/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 9)
CHC/SM/078 22/02/2023 1/F - Concrete Defect of Internal Wall (Lift shaft P1 to YL replied on 29/03/2023
P6)
CHC/SM/079 24/02/2023 G/F - Concrete Defect of Internal Wall (Van Car Park) YL replied on 04/03/2023

CHC/SM/080 24/02/2023 2/F – 3/F Formation of an opening in the Staircase YL not yet replied
(ST-5) Landing Slab
CHC/SM/081 27/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 10)
CHC/SM/082 27/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 11)
CHC/SM/083 27/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 12)
CHC/SM/084 28/02/2023 G/F - Concrete Defect of Internal Wall (Cable Duct YL replied on 04/03/2023
chamber)
CHC/SM/085 02/03/2023 G/F – Concrete Defect of Sprinkler Water Tank YL replied on 17/03/2023

CHC/SM/086 03/03/2023 G/F – Concrete Defect of BUM Store Room YL replied on 10/03/2023

CHC/SM/087 03/03/2023 2/F – Concrete Defect of Lift shaft no. P1 to P6 YL replied on 13/04/2023

CHC/SM/088 03/03/2023 2/F – Concrete Defect of Column No. C40 & C44 YL replied on 13/04/2023

CHC/SM/089 07/03/2023 1/F – Concrete Defect of Column No. C44 YL replied on 13/04/2023

CHC/SM/090 07/03/2023 1/F – Concrete Defect of Column No. C45 YL replied on 12/04/2023

CHC/SM/091 07/03/2023 1/F – Concrete Defect of Column No. C41 YL replied on 12/04/2023

CHC/SM/092 10/03/2023 1/F – Concrete Defect of Irrigation & Cleansing YL replied on 12/04/2023
Transfer Tank
CHC/SM/093 13/03/2023 G/F to 1/F - Concrete Defect of Staircase No.ST-2 YL replied on 06/04/2023

CHC/SM/094 13/03/2023 G/F to 1/F - Concrete Defect of Staircase No.ST-1 YL replied on 12/04/2023
(+9.35mpd to +12.9)
CHC/SM/095 13/03/2023 G/F to 1/F - Concrete Defect of Staircase No.ST-1 YL replied on 06/04/2023
(+12.9 to +14.0)

Page 33 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Site Memo No. Issue Date Subject Action/Reply

CHC/SM/096 22/03/2023 G/F to 2/F – Post installed Rebar failed at the Pull Out YL replied on 23/03/2023
Test
CHC/SM/097 22/03/2023 1/F to 2/F– Concrete Defect of Staircase No. ST-2 YL replied on 06/04/2023

CHC/SM/098 23/03/2023 1/F to 2/F– Concrete Defect of Staircase No. ST-4 YL replied on 14/04/2023
1/F to 2/F– Concrete Defect of Staircase No. ST-1
CHC/SM/099 23/03/2023 (+15.95mpd to +17.325mpd)
YL replied on 06/04/2023
1/F to 2/F– Concrete Defect of Staircase No. ST-1
CHC/SM/100 23/03/2023 (+17.025mpd to +19.125mpd)
YL replied on 12/04/2023
G/F – Post installed Rebar failed at the Pull Out Test
CHC/SM/101 30/03/2023 (30/03/2023)
YL replied on 31/03/2023
Test Report of Structural Steel Sections (Customer Request
CHC/SM/102 31/03/2023 No. SA-5)
N/A

CHC/SM/103 31/03/2023 Test Report of Structural Steel Sections (Customer Request N/A
No. HB-5 & SCC-4)
Approval to the Use of Structural Steel Plates (SP- 10, SP-12)
CHC/SM/104 31/03/2023 N/A
3/F to 4/F – Concrete Defect of Column No. C13, C14, C19,
CHC/SM/105 13/04/2023 C20
YL replied on 09/05/2023
4/F to 5/F - Concrete Defect of Staircase No.ST-5 (+29.4 to
CHC/SM/106 13/04/2023 +33.9)
YL not yet replied
2/F to 3/F - Concrete Defect of Staircase No.ST-2 (+29.04 to
CHC/SM/107 13/04/2023 +24.9)
YL replied on 09/05/2023
3/F - Concrete Defect of Concrete Wall (Gridline 1 to 2, A to
CHC/SM/108 13/04/2023 E)
YL replied on 09/05/2023
Approval to the Use of Steel Reinforcing Bar for
CHC/SM/109 18/04/2023 Superstructure construction (Batch 13)
N/A
Approval to the Use of Steel Reinforcing Bar for
CHC/SM/110 18/04/2023 Superstructure construction (Batch 15)
N/A

CHC/SM/111 18/04/2023 3/F Concrete defect of Column no. C30, C32 to C35, C38, YL replied on 17/05/2023

C40, C41, C42, C44 & C45


3/F - Concrete Defect of Wall, Concrete Post for façade wall
CHC/SM/112 18/04/2023 (1 to 5, F to H)
YL replied on 17/05/2023
3/F - Concrete Defect of Wall (Gridline 4 to 7, F to H)
CHC/SM/113 18/04/2023 YL replied on 17/05/2023
Approval to the Use of Steel Reinforcing Bar for
CHC/SM/114 18/04/2023 Superstructure construction (Batch 14)
N/A
G/F (Zone C) - Concrete Defect of Column & Wall
CHC/SM/115 26/04/2023 YL not yet replied
G/F (Zone D) - Concrete Defect of Column
CHC/SM/116 26/04/2023 YL not yet replied
Test Report of Structural Steel Sections (Customer Request
CHC/SM/117 27/04/2023 No. SA-6)
N/A
Test Report of Structural Steel Sections (Customer Request
CHC/SM/118 05/05/2023 No. SA-7)
N/A
Test Report of Structural Steel Sections (Customer Request
CHC/SM/119 05/05/2023 No. SCC-5)
N/A
4/F (Zone A) - Concrete Defect of Column & Wall
CHC/SM/120 09/05/2023 YL not yet replied
4/F (Zone D) - Concrete Defect of Column & Wall
CHC/SM/121 09/05/2023 YL not yet replied

Page 34 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

9 Critical & Outstanding Submission from the Contractor


Nil.

10 A.O.B
Nil.

SW
_________________
Sarick Wong
Resident Engineer
Date: 21th May, 2023

Page 35 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

Appendix A

Record Photos

Page 36 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

A-1Record Photos of the Site

A -1.1 General view of the site (1/F – 8/F) – External view of the A -1.2 General view of the site (1/F to 8/F) – External view of the
building, a view from Pak Wo Road (Western site boundary) building, a view from Wai Ping Close (South eastern site boundary)

A -1.3 7/F floor level - Steel fixing of 7/F beam & slab. (Gridline 4 to A-1.4 7/F floor level – Concreting of 7/F beam & slab. (gridline 4 to 7, E
7, E to H) to H)

A -1.5 G/F floor level – Installation of building services is in progress. A -1.6 Construction of cantilever beam & associated tie beam at top of
retaining wall completed. (gridline 1, A to H)

Page 37 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023

APPENDIXCN1

CONCRETE CUBE COMPRESSIVE STRENGTH

TEST REPORTS

Page 38 of 38

You might also like