Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Notes:
i) BUSM12 on the 400 dia. fresh water pipe at the junction of Wai Ping Close and Wai Wo Street has not been installed due
to the permissions from relevant authorities had not received in the reporting period.
ii) Vibration monitoring points (VCP1 to VCP5) were relocated to the NSRson 7/4/2021 and renamed as VCP1a to VCP5a
for monitoring vibration during the piling period continuously in real time.
iii) The monitoring device at VCP2/2a was out of order and the monitoring device at VCP3/3a was relocated to the location
VCP2/2a.
iv) Tilting marker TM1 & Building settlement marker no. BUSM7 (Plastic tape markers) located at street Lamp post of Pak
Wo Street were reported damaged on 29/10/2021. New tilting marker TM1A & Building settlement markers BUSM7A
were installed on the same street lamp post and new position of the markers surveyed on 29/10/2021.
2.5 Ground Floor Beam & Slab construction (at level +9.4mpd)
100% Beam & slab concreting completed.
Page 3 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
2.14 Retaining Wall Construction (located at western site boundary adjacent to Pak Wo Road)
a) 100% (10 out of 10 Bays) base slab of retaining wall concreting completed.
b) 100% (10 out of 10 Bays) wall stem of retaining wall concreting completed.
c) 100 % (28 out of 28 nos.) short cantilever beams (RWCB for supporting surface channel) concreting
completed.
d) 100% (27 out of 27 nos.) cantilever beams (RWCB for supporting the 2.5m high fence wall) concreting
completed. During the reporting period, cantilever beam no. RWCB32 to RWCB35, RWCB41 and
associated concrete tie beams no. RWB5 to RWB8, RWB14, and RWB15 completed the concreting.
2.15.2 Western steel sheet pile wall (wall adjacent to Pak Wo Road)
a) 100% (168 out of 168 numbers) of steel sheet piles were driven to their design toe level.
b) 100% layer 1, layer 2 steel waling& steel struts (8 numbers) installation completed.
(Located at gridline 1A to 1E)
c) 100% of steel waling (1 layer) & corner struts (4 numbers) installation completed.
(Located at gridline 1E to 1G)
Page 4 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
2.15.3 Southern steel sheet pile wall (wall adjacent to Wai Ping Close)
a) 100%of steel sheet piles were driven to their design toe level.
b) Gridline 1G to 2G
100% steel waling (1 layer) & corner struts (4 numbers) installation completed.
e) Gridline 2H to 4H
100% steel waling (1 layer) & corner struts (4 numbers) installation completed.
f) Gridline 4H to 7H
100% steel waling (1 layer) & corner struts (7 numbers) installation completed.
2.15.4 Eastern steel sheet pile wall (wall adjacent to Wai Wo Street)
a) 100%of steel sheet piles were driven to their design toe level.
b) Gridline 7F to 7H
100% steel waling (1 layer) & corner struts (7 numbers) installation completed.
Page 5 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
satisfactory.
5.4 Steel fabric (B503) for carriageway road widening works – test samples of the steel mesh were tested at
HOKLAS laboratory and the results of the steel mesh rebar test were found to be satisfactory.
5.5 Steel reinforcing bar (Batch 2) for precast concrete element construction was delivered to YLW site (located in
mainland China) on September, 2021. Test samples of the steel rebar were tested at HOKLAS laboratory &
Public Works Laboratories, the test results of the steel rebar were found to be satisfactory.
5.6 Steel reinforcing bar (Batch 3) for pile cap construction delivered to site on December, 2021. Steel rebar samples
send to Public Works Laboratories for testing, the test results of the steel rebar were found to be satisfactory.
5.7 Steel reinforcing bar (Batch 4) for pile cap construction delivered to site on late December, 2021. Test samples of
the steel rebar were tested at HOKLAS laboratory & Public Works Laboratories.
5.8 Steel reinforcing bar (Batch 5) for pile cap construction delivered to site on January, 2022.Test samples of the steel
rebar were sent to Public Works Laboratories for testing.
5.9 Steel fabric B503 and A193 for on grade concrete slab were tested at HOKLAS laboratory and the test results of
the steel mesh rebar were found to be satisfactory.
5.10 Steel fabric C503 & A193 (Batch 2) for external Driveway & Car parking area were tested at HOKLAS
laboratory and the test results of the steel mesh rebar were found to be satisfactory.
5.11 Steel reinforcing bar (Batch 1) for superstructure construction delivered to off-site storage yard on May 2022.Test
samples of the steel rebar were sent to Public Works Laboratories for testing and the test result was found to be
satisfactory.
5.12 Steel fabric C503 & A193 (Batch 3) for ground floor on grade concrete slab delivered to site on May, 2022.
Test sample of the steel fabric was sent to Public Works Laboratories for testing, the test result was found to be
satisfactory.
5.13 Hot rolled Steel H-beam (254x254x73kg) for lagging UC of excavation and lateral support works delivered to site
on May,2022. Test sample of the steel H-beam was sent to Public Works Laboratories for testing, the test results of
the steel H-beam were found to be satisfactory.
5.14 Steel reinforcing bar (Batch 2) for superstructure construction was delivered to off-site storage yard on June
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bar was found to be satisfactory.
5.15 Steel reinforcing bar (Batch 3) for superstructure construction was delivered to off-site storage yard on July
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bars (diameter of 12mm, 16mm, 20mm, 25mm, 40mm ) was found to be satisfactory. Steel bar samples of 10mm
diameter do not meet the permissible deviation requirement as specified in CS2:2012, Table 3 - Permissible
deviation from nominal mass. Additional or new batch of 10mm diameter steel bar need to be sent to Public
Works laboratory for testing.
5.16 Steel plates (grade S275J0 – 16mm, 20mm thick) were sent to Public Works Laboratories for testing, the test
result of the steel plates (customer test request no. SP-7) was found to be satisfactory.
Page 6 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
5.17 Steel reinforcing bar (Batch 4) for superstructure construction was delivered to off-site storage yard on July
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bars (diameter of 10mm, 16mm, and 40mm) was found to be satisfactory. However, steel bar samples of 12mm
diameter do not meet the permissible deviation requirement as specified in CS2:2012, Table 3 - Permissible
deviation from nominal mass. Additional steel bar (12mm diameter) was re-tested and re-test result of the steel bar
(mass per meter length) was found to be satisfactory.
5.18 Steel plates (grade S275J0 – 5mm, 12mm, 16mm, 25mm thick & grade S355J0 – 20mm thick) were sent to
Public Works Laboratories for testing in August 2022, the test result of the steel plates (customer test request no.
SP-8, SP-9) was found to be satisfactory.
5.19 Steel reinforcing bar (Batch 5 & 6) for superstructure construction was delivered to off-site storage yard on
August 2022.Steel bar sample was sent to PWL for testing and the test result was found to be satisfactory.
5.20 Soil samples of imported soil for backfilling proposed by the Contractor were tested in August, 2022 by Public
Work Laboratories. The preliminary results are as follows: Particle size distribution of soil and chemical analysis
(total Sulphate content) of soil comply with ASD specification. However, the liquid limit of the soil does not
comply with ASD specification. Additional soil samples were sent to PWL for retesting on September, 2022. The
result of retesting the soil sample (liquid limit of soil) is found to be satisfactory.
5.21 Steel reinforcing bar (Batch 7) for superstructure construction was delivered to off-site storage yard on October
2022.Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the steel
bar is found to be satisfactory.
5.22 Steel reinforcing bar (Batch 8) for superstructure construction was delivered to off-site storage yard on November
2022. Test samples of the steel rebar were sent to Public Works Laboratories for testing. The preliminary test results
of the steel rebar (bar diameter of 12mm, 16mm, 25mm) were found to be satisfactory. For 10mm diameter bar, test
sample does not comply with the tensile strength & total elongation at maximum force requirements specified in
CS2:2021, hence the test result is not satisfactory.
5.23 Steel angles of sizes 50x50x5mm, 30x30x5mm(grade S275J0) and 125x75x8mm(grade S355J0) for Aluminum
blade, Louvre, Aluminum Cladding (Batch 1) were delivered to off-site storage yard on November,2022. Test
samples of the steel angles were sent to Public Works Laboratories for testing. The preliminary test results of the
50x50x5mm, 30x30x5mm & 125x75x8mm were found to be satisfactory. For 75x50x5mm thick steel angle, the
tensile strength of the test sample is found to be lower than minimum tensile strength requirement specified in BS EN
10025-2:2004, hence the test result is not satisfactory.
5.24 Steel plate of the following thickness (10mm, 12mm, 16mm, 2mm, 3mm, 4mm, 5mm, 6mm, 8mm, 20mm – grade
S275J0) & 12mm thick (grade S355J0) were delivered to site on December,2022. Test samples of the steel plates
were sent to Public Works Laboratories for testing. The preliminary test results of the steel plates were found to be
satisfactory.
5.25 Steel reinforcing bar (Batch 9 & 10) for superstructure construction was delivered to off-site storage yard on
December 2022 & January,2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing,
Page 7 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
the test result of the steel bar (bar diameter of 12mm, 16mm, 25mm, 32mm, 40mm) is found to be satisfactory.
5.26 Steel reinforcing bar (Batch 11) for superstructure construction was delivered to off-site storage yard on January,
2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing and the test result of the
steel bar is found to be satisfactory.
5.27 Steel reinforcing bar (Batch 12) for superstructure construction was delivered to off-site storage yard on January,
2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing, the test result of the
steel bar (10mm diameter) is found to be satisfactory.
5.28 Steel reinforcing bar (Batch 13) for superstructure construction was delivered to off-site storage yard on February,
2023. Test samples of the steel rebar (12mm & 16mm diameter) were sent to Public Works Laboratories for testing
and the test result of the steel bar is found to be satisfactory.
5.29 A steel angle of sizes 75x50x5mm (grade S275J0) was delivered to off-site storage yard on January, 2023. Test
samples of the steel angles were sent to Public Works Laboratories for testing, the test results of the steel angle was
found to be satisfactory.
5.30 Steel channel of sizes 200x90x 30.3kg/m (grade S355J0) was delivered to off-site storage yard on January, 2023.
Test samples of the steel channel were sent to Public Works Laboratories for testing, the preliminary test results of
the steel angle was found to be satisfactory.
5.31 Steel reinforcing bar (Batch 14) for superstructure construction was delivered to off-site storage yard on February
2023. Test samples of the steel rebar were sent to Public Works Laboratories for testing. The preliminary test results
of the steel rebar (bar diameter of 12mm, 40mm) were found to be satisfactory. For 32mm diameter bar, test sample
does not comply with the tensile/yield strength ratio requirements specified in CS2:2021, hence the test result is not
satisfactory. The 32 diameter steel bar sample was retest on early March, 2023 and the tensile test result was found to
be satisfactory.
5.32 Steel reinforcing bar (Batch 15) (bar diameter of 12mm, 16mm, 25mm,32mm &40mm) for superstructure
construction was delivered to off-site storage yard on March, 2023. Test samples of the steel rebar were sent
to Public Works Laboratories for testing and the tensile test result was found to be satisfactory.
5.33 Hot rolled Steel H-beam (305x305x97kg/m & 152x152x30kg/m – file no. HB-5) for structural steelworks
was delivered to site on March, 2023. Test sample of the steel H-beam was sent to Public Works Laboratories
for testing, the test results of the steel H-beam were found to be satisfactory.
5.34 Steel angle of sizes 50x50x6mm, 75x50x5mm, 100x100x8mm - file no.SA-5 (grade S275J0) was delivered
to off-site storage yard on March, 2023. Test samples of the steel angles were sent to Public Works
Laboratories for testing, the test results of the steel angle was found to be satisfactory.
5.35 Steel channel of size 150x75x 17.9kg/m - file no. SCC-4 (grade S275J0) was delivered to off-site storage
yard on March, 2023. Test samples of the steel angles were sent to Public Works Laboratories for testing, the
test results of the steel angle was found to be satisfactory.
5.36 Steel plate of thickness 5mm, 6mm, 8mm, 10mm &12mm – file no. SP-12 (grade S275J0) was delivered to
site on March, 2023. Test samples of the steel plates were sent to Public Works Laboratories for testing and
Page 8 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Material
Release Agent for Steel Formwork YL/MS/S/005 23/10/2020 29/10/2020
Page 9 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Page 10 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Page 11 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
FSP III 0.4m x 12m Hot Rolled U-Sheet YL/MS/S/098 14/12/2021 03/01/2022
Pile Grade 355GP (Batch 4)
M30 Nuts for steel bracket YL/MS/S/099 14/12/2021 18/12/2021
Page 12 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
PVC water stop for Retaining wall stem YL/MS/S/0126 06/06/2022 14/06/2022
- expansion &contraction joint
construction
Zinc rich Primer YL/MS/S/0127 06/06/2022 14/06/2022
Page 13 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Page 15 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Page 16 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Page 17 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Page 18 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
Submission Date
RMA-YL-0011 0018 To specify the steel grade of steel 16/03/2021 22/03/2021 26/03/2021
splice plate for sheet piles.
RMA-YL-0018 0043 Increase depth of pile cap PC21 08/10/2021 11/10/2021 15/10/2021
Page 20 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
RMA-AECOM -0004 0024 1) Change Façade Type 1a span 08/09/2021 09/09/2021 09/09/2021
to 0026 length
2) 2)Revise Upper & Lower
Beam Main bar size from
T16 to T12
Page 21 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
RMA-AECOM -0008 0053 Revised the trimming details 23/11/2021 23/11/2021 21/12/2021
of the manhole when
opening greater than 500mm
RMA-AECOM -0009 - Provide RC checking of Pile 08/12/2021 08/12/2021 10/12/2021
cap for the linear
displacement of the piles.
Additional reinforcement is
not necessary.
RMA-AECOM -0010 0071 Revise the typo of links 13/12/2021 13/12/2021 14/12/2021
details of SB4
Delete side bar details of
SB14
Reduce the thickness of
SB14
Page 22 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
Page 23 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
RMA-AECOM -0024 070b, 0144-0149 1) Proposed 500mm thick 27/04/2022 28/04/2022 12/05/2022
bearing wall carried by
strap beam SB52 added.
Ground Beams setting
out &slab top level
updated.
RMA-AECOM -0026 0143a, 0051c Revised design toe level of steel 12/07/2022 13/07/2022 18/07/2022
sheet piles due to the underground
obstruction encountered on site.
RMA-AECOM -0027 0149a, 0161-0167 Propose additional slab opening, 03/08/2022 04/09/2022 18/08/2022
hanger wall, bearing wall detail
and screen wall detail.
RMA-AECOM -0028 1)150mm diameter sub-soil drain 16/08/2022 16/08/2022 26/08/2022
is proposed as UPVC perforated
pipe in leakage collection system
2)Addition protection details for
the weephole is proposed.
RMA-AECOM -0029 SK-0172, SK-0173, Revise column C7 (1/F, 2/F), C8 02/09/2022 02/09/2022 13/09/2022
SK-0174, SK-0175 & (1/F, 2/F), C13 (2/F), C14 (1/F,
SK-0177, SK-0178, 2/F), C19 (2/F) Details
SK-0179
RMA-AECOM -0030 Checking the structural adequacy 29/08/2022 30/08/2022 11/10/2022
- pile cap steel bar due to out of
tolerance steel H pile verticality
RMA-AECOM -0031 0177a Revised the excavated level for 06/09/2022 06/09/2022 06/09/2022
steel wailing and strut (CS4C,
CS4D, CS4E, CS4F)
RMA-AECOM -0032 0187,0188 Amend the 2/F Framing Plan 15/09/2022 15/09/2022 31/10/2022
RMA-AECOM -0033 0166a,0189, 0190 Amend the Wall R.C. Detail 16/09/2022 16/09/2022 26/09/2022
GF-3F
RMA-AECOM -0034 0164a, 0192 Revised the beam size of 1B58 27/09/2022 27/09/2022 29/09/2022
Page 24 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
RMA-AECOM -0044 0050b, 0216 Amend the Hoarding Layout and 21/11/2022 21/11/2022 28/11/2022
Detail
RMA-AECOM -0045 0050c Amend the Hoarding Layout and 08/12/2022 08/12/2022 withdrawn
Detail
RMA-AECOM -0046 0180d Propose the Sunken Slab Detail 30/12/2022 03/01/2023 21/02/2023
RMA-AECOM -0047 0220 Revise façade typical details. 04/01/2023 06//01/2023 21/03/2023
RMA-AECOM -0048 0162a Corbel typical details added 16/01/2023 18/01/2023 20/02/2023
Updated hanger wall RC details
RMA-AECOM-0052 '0248-0251, 0222a 1. Update Details for Slab 27/02/2023 27/02/2023 10/03/2023
Openings (5/F)
RMA-AECOM-0053 '0286-0289, 0308, 1. RMA for 6/F slab 02/03/2023 02/03/2023 08/03/2023
0225a
RMA-AECOM-0054 '0290-0294, 0296 1. RMA for 7/F slab 03/03/2023 03/03/2023 09/03/2023
RMA-AECOM-0055 SK-0221a, SK-0318 1. Revise the 4/F slab R.C. details 06/03/2023 06/03/2023 10/03/2023
to SK-0324 according to the revised CBWD
opening
RMA-AECOM-0056 'SK-0225b 1. 6/F sunken slab 10/03/2023 10/03/2023 10/03/2023
RMA-AECOM-0057 'SK-0217a, SK-0325 - 1. Revise the 3/F slab R.C. details 13/03/2023 13/03/2023 04/04/2023
SK-0332 according to the revised CBWD
opening
RMA-AECOM-0058 'SK-0218 & 0219, 1. Revise the 2/F slab R.C. details 18/03/2023 18/03/2023 31/3/2023
SK-0333 to 0336 according to the revised CBWD
opening
RMA-AECOM-0059 'SK-0225c, SK0297a, 1. Revise the RC detail of 6F & 17/03/2023 17/03/2023 24/3/2023
SK302a-305a, 7F Beam due to the discrepancy
SK-311a of framing plan and the RC detail.
SK-313a-317a
RMA-AECOM-0060 'SK-0164c, 1. Revise the 1/F slab R.C. details 15/03/2023 15/03/2023 Comment on
SK-0165b, SK-0337, according to the revised CBWD
SK-0205a, SK-0206a, opening 20/3/23
SK-0340,
RMA-AECOM-0061 'SK-0338 & SK-0339 Propose the External Wall RC 17/03/2023 17/03/2023 31/3/2023
Detail
RMA-AECOM-0062 'SK-0341, SK0343, Amend the thickness of 1LS27 & 17/03/2023 17/03/2023 31/3/2023
SK-0344 1LS27
Page 25 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
RMA-AECOM-0068 '0280a, 0281a 1. Revise 8F Beam Column Joint 11/05/2023 11/05/2023 16/05/2023
design of C21, C25, C26, C38,
C39, C42, C43 due to
modification of connecting beam
level
RMA-AECOM-0069 'SK-0444 to 0448, 1. Revise 8F Beam and Slab R.C 12/05/2023 12/05/2023 16/05/2023
SK-0452 to 0459 Detail and Framing Plan.
RMA-YL-0029 056a 1) Change the rebar size of 22/12/2021 22/12/2021 15/05/2023
0058 PC08, PC12, and
0068a SB17&SB10.
0071 2) Delete drg. of PC11 from
0081 SK-56
3) Revise shear links of
SB5,SB15& SB14.
RMA-YL-0030 0083 - 0098 1) Change steel links of 01/06/2021 01/07/2021 12/01/2022
column from type E to type
N.
2) Add note no. 3
RMA-YL-0031 0082a 1) Amended the side bars from 13/01/2021 14/01/2021 12/01/2022
20 no. to 18 no.
RMA-YL-0032 0080a 1) Details for filling the gap 13/01/2021 14/01/2021 15/01/2021
between
Steel waling & steel sheet
pile wall added.
RMA-YL-0034 0074d, Revised the connection 10/03/2022 10/03/2022 14/04/2022
0100a details of the main &
secondary steel struts.
RMA-YL-0035 Steel bar details of 100mm 11/03/2022 11/03/2022 13/03/2022
- thick partition wall revised.
RMA-YL-0036 1) Revised the cut off level & 30/03/2022 30/03/2022 31/03/2022
0044a tentative pile length of steel
piles for Pile cap no. PC28
RMA-YL-0037 0104 1) Delete the anchor bar from 07/04/2022 07/04/2022 12/04/2022
precast wall type PF115
RMA-YL-0038 SK-0150 Types of hose reel added to 18/05/2022 19/05/2022 20/05/2022
SK-0151 MIC detail drawing.
Page 26 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
RMA-YL-0046 SK-102Bb, 170, 171 Proposed dividing Stage 7 24/08/2022 24/08/2022 26/08/2022
ELS working area into
Area A & Area B
RMA-YL-0047 SK-0082a,SK-0145a, Add lap length for 24/08/2022 24/08/2022 25/08/2022
construction joint of SB57,
SK-0176 SB62 & SB63
Page 27 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
RMA-YL-0061 SK-0231 - SK0240 Beam R.C details revised: 26 no. 02/02/2023 02/02/2023 08/03/2023
Beam of 5F
RMA-YL-0062 SK-0181 Beam R.C details revised: 10 no. 02/02/2023 02/02/2023 withdrawn
Beam of 5F
RMA-YL-0063 SK-0226 Revise the RC detail of max. span 10/02/2023 10/02/2023 22/02/2023
of RWCB from 1500 to 1750
Page 28 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
Page 29 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Submission Date
CHC/SM/004 16/03/2021 Approval to the Use of Steel Sheet Pile (Batch 1)& NA
12mm Steel Plate (Batch 1)
CHC/SM/005 19/03/2021 Approval to the Use of Steel H-Piles (Batch 4) NA
Page 30 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
CHC/SM/016 03/01/2022 Approval to the Use of Steel Reinforcing Bar for Pile NA
Cap (Batch 3)
CHC/SM/017 13/01/2022 Approval to the Use of FSPIII Steel Sheet Piles NA
CHC/SM/018 18/01/2022 Approval to the Use of Hot Rolled Steel Plate (50mm NA
thick)(Batch 2)
CHC/SM/019 18/01/2022 Approval to the Use of Steel Reinforcing Bar for NA
Precast Concrete Units manufactured by YLW Concrete
Precast Products Company Ltd. in mainland China.
CHC/SM/020 28/01/2022 Approval to the Use of steel fabric (C503 & A193) for NA
on grade concrete slab construction.
CHC/SM/021 28/01/2022 Approval to the Use of Structural Steel Sections -150 x NA
75 steel channel
CHC/SM/022 29/04/2022 Approval to the Use of steel fabric (A193& C503) for NA
on grade concrete slab construction.
CHC/SM/023 02/06/2022 Approval to the Use of steel fabric (A193) for on grade NA
concrete slab construction.
CHC/SM/024 08/06/ 2022 Pile No.C30 – Concreting in Rainy day under Red NA
Rainstorm Warning
CHC/SM/025 16/06/2022 Approval to the Use of Structural Steel Sections NA
CHC/SM/028 26/07/2022 Approval to the Use of Steel Reinforcing Bar for Pile NA
Cap (Batch 4)
CHC/SM/029 26/07/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 1)
CHC/SM/030 26/07/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 2)
CHC/SM/031 26/07/2022 Approval to the Use of Hot Rolled Steel Plate (16mm, NA
20mm thick) SP-7
CHC/SM/032 24/08/2022 Precautionary Measures for severe Tropical Storm NA
Ma-On
CHC/SM/033 12/10/2022 Approval to the Use of Structural Steel Plates (SP-8, NA
SP-9)
CHC/SM/034 17/10/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 3)
CHC/SM/035 17/10/2022 Approval to the Use of Steel Reinforcing Bar for NA
Superstructure (Batch 4)
Page 31 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Pull out test report of threaded rod & nut (Batch 5 & 6)
CHC/SM/046 16/12/2022 Bolting assemblies proposed for steel work of this building
N/A
project.
Test Report of Structural Steel Sections (Customer Request
CHC/SM/047 03/01/2023 No. SA-2)
N/A
Approval to the Use of Steel Reinforcing Bar for
CHC/SM/048 04/01/2023 Superstructure construction (Batch 7)
N/A
Test Report of Steel Reinforcing Bar for Superstructure
CHC/SM/049 04/01/2023 construction (Batch 8)
N/A
CHC/SM/057 11 02 2023 4/F – Anchor bolt details for steel channels supporting YL replied on 13/02/2023
steel scaffold at shaft opening
CHC/SM/058 11/02/2023 5/F – Steel fixing of Façade Type PF519 , PF520 & YL replied on 16/02/2023
Concrete Post
CHC/SM/059 13/02/2023 5/F – Steel fixing of Partition wall (100mm thick) YL replied on 14/02/2023
CHC/SM/060 13/02/2023 Reminder for 5/F, steel fixing of Façade wall no. PF520 YL replied on 14/02/2023
CHC/SM/061 14/02/2023 Reminder for Steel Fixing Works – Substandard Steel YL replied on 14/02/2023
link is not allowed to be used for construction
CHC/SM/062 13/02/2023 5/F – Steel fixing of Façade Type PF516 to PF518 & YL replied on 14/02/2023
Concrete Posts
CHC/SM/063 13/02/2023 5/F – Steel fixing of Bearing wall (200mm thick) YL replied on 14/02/2023
CHC/SM/064 14/02/2023 Reminder for 5/F, steel fixing of Façade wall no. PF513 YL replied on 14/02/2023
Page 32 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
CHC/SM/067 15/02/2023 5/F – Steel fixing of Bearing wall at staircase ST-5 YL replied on 24/02/2023
(200mm thick)
CHC/SM/068 15/02/2023 5/F – Steel fixing of Façade Type PF529 , PF530 & YL replied on 16/02/2023
Concrete Posts
CHC/SM/069 15/02/2023 5/F – Steel fixing of Façade Type PF529 , PF530 & YL replied on 16/02/2023
Concrete Posts
CHC/SM/070 15/02/2023 G/F - Concrete Defect of External Wall YL replied on 01/03/2023
CHC/SM/074 17/02/2023 2/F - Concrete Defects of internal Wall (Honeycomb) YL replied on 24/02/2023
are covered up without carrying out an agreed repair
work inspection procedures
CHC/SM/075 20/02/2023 G/F - Concrete Defect of Internal Wall ( Clinical waste YL replied on 24/02/2023
storage room)
CHC/SM/076 20/02/2023 G/F - Concrete Defect of Internal Wall ( Chemical YL replied on 24/02/2023
waste store room)
CHC/SM/077 21/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 9)
CHC/SM/078 22/02/2023 1/F - Concrete Defect of Internal Wall (Lift shaft P1 to YL replied on 29/03/2023
P6)
CHC/SM/079 24/02/2023 G/F - Concrete Defect of Internal Wall (Van Car Park) YL replied on 04/03/2023
CHC/SM/080 24/02/2023 2/F – 3/F Formation of an opening in the Staircase YL not yet replied
(ST-5) Landing Slab
CHC/SM/081 27/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 10)
CHC/SM/082 27/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 11)
CHC/SM/083 27/02/2023 Approval to the Use of Steel Reinforcing Bar for N/A
Superstructure construction (Batch 12)
CHC/SM/084 28/02/2023 G/F - Concrete Defect of Internal Wall (Cable Duct YL replied on 04/03/2023
chamber)
CHC/SM/085 02/03/2023 G/F – Concrete Defect of Sprinkler Water Tank YL replied on 17/03/2023
CHC/SM/086 03/03/2023 G/F – Concrete Defect of BUM Store Room YL replied on 10/03/2023
CHC/SM/087 03/03/2023 2/F – Concrete Defect of Lift shaft no. P1 to P6 YL replied on 13/04/2023
CHC/SM/088 03/03/2023 2/F – Concrete Defect of Column No. C40 & C44 YL replied on 13/04/2023
CHC/SM/089 07/03/2023 1/F – Concrete Defect of Column No. C44 YL replied on 13/04/2023
CHC/SM/090 07/03/2023 1/F – Concrete Defect of Column No. C45 YL replied on 12/04/2023
CHC/SM/091 07/03/2023 1/F – Concrete Defect of Column No. C41 YL replied on 12/04/2023
CHC/SM/092 10/03/2023 1/F – Concrete Defect of Irrigation & Cleansing YL replied on 12/04/2023
Transfer Tank
CHC/SM/093 13/03/2023 G/F to 1/F - Concrete Defect of Staircase No.ST-2 YL replied on 06/04/2023
CHC/SM/094 13/03/2023 G/F to 1/F - Concrete Defect of Staircase No.ST-1 YL replied on 12/04/2023
(+9.35mpd to +12.9)
CHC/SM/095 13/03/2023 G/F to 1/F - Concrete Defect of Staircase No.ST-1 YL replied on 06/04/2023
(+12.9 to +14.0)
Page 33 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
CHC/SM/096 22/03/2023 G/F to 2/F – Post installed Rebar failed at the Pull Out YL replied on 23/03/2023
Test
CHC/SM/097 22/03/2023 1/F to 2/F– Concrete Defect of Staircase No. ST-2 YL replied on 06/04/2023
CHC/SM/098 23/03/2023 1/F to 2/F– Concrete Defect of Staircase No. ST-4 YL replied on 14/04/2023
1/F to 2/F– Concrete Defect of Staircase No. ST-1
CHC/SM/099 23/03/2023 (+15.95mpd to +17.325mpd)
YL replied on 06/04/2023
1/F to 2/F– Concrete Defect of Staircase No. ST-1
CHC/SM/100 23/03/2023 (+17.025mpd to +19.125mpd)
YL replied on 12/04/2023
G/F – Post installed Rebar failed at the Pull Out Test
CHC/SM/101 30/03/2023 (30/03/2023)
YL replied on 31/03/2023
Test Report of Structural Steel Sections (Customer Request
CHC/SM/102 31/03/2023 No. SA-5)
N/A
CHC/SM/103 31/03/2023 Test Report of Structural Steel Sections (Customer Request N/A
No. HB-5 & SCC-4)
Approval to the Use of Structural Steel Plates (SP- 10, SP-12)
CHC/SM/104 31/03/2023 N/A
3/F to 4/F – Concrete Defect of Column No. C13, C14, C19,
CHC/SM/105 13/04/2023 C20
YL replied on 09/05/2023
4/F to 5/F - Concrete Defect of Staircase No.ST-5 (+29.4 to
CHC/SM/106 13/04/2023 +33.9)
YL not yet replied
2/F to 3/F - Concrete Defect of Staircase No.ST-2 (+29.04 to
CHC/SM/107 13/04/2023 +24.9)
YL replied on 09/05/2023
3/F - Concrete Defect of Concrete Wall (Gridline 1 to 2, A to
CHC/SM/108 13/04/2023 E)
YL replied on 09/05/2023
Approval to the Use of Steel Reinforcing Bar for
CHC/SM/109 18/04/2023 Superstructure construction (Batch 13)
N/A
Approval to the Use of Steel Reinforcing Bar for
CHC/SM/110 18/04/2023 Superstructure construction (Batch 15)
N/A
CHC/SM/111 18/04/2023 3/F Concrete defect of Column no. C30, C32 to C35, C38, YL replied on 17/05/2023
Page 34 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
10 A.O.B
Nil.
SW
_________________
Sarick Wong
Resident Engineer
Date: 21th May, 2023
Page 35 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
Appendix A
Record Photos
Page 36 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
A -1.1 General view of the site (1/F – 8/F) – External view of the A -1.2 General view of the site (1/F to 8/F) – External view of the
building, a view from Pak Wo Road (Western site boundary) building, a view from Wai Ping Close (South eastern site boundary)
A -1.3 7/F floor level - Steel fixing of 7/F beam & slab. (Gridline 4 to A-1.4 7/F floor level – Concreting of 7/F beam & slab. (gridline 4 to 7, E
7, E to H) to H)
A -1.5 G/F floor level – Installation of building services is in progress. A -1.6 Construction of cantilever beam & associated tie beam at top of
retaining wall completed. (gridline 1, A to H)
Page 37 of 38
Project Title: Design & Construction of A Community Health Centre Cum
Social Welfare Facilities at Pak Wo Road,North District
Contract No: SS H501
Contractor: Yau Lee Construction Co., Ltd (YL)
RE Report No. 33 Reporting Period: 17 April, 2023 to 21 May, 2023
APPENDIXCN1
TEST REPORTS
Page 38 of 38