ACTION PLAN OUTSTANDING PEKERJAAN PANEL PERIMETER TAHAP III (UTARA-SELATAN)

Kontraktor : CV PURNAMA

Lokasi : Podomoro Park, Bandung

ACTION PLAN PAGAR PERIMETER TAHAP III


DURATION
21 AGU - 27 AGU 28 AGU - 3 SEP 4 SEP - 11 SEP
No. URAIAN PEKERJAAN SAT VOLUME
S S R K J S M S S R K J S M S S R K J S M S
START DAY FINISH
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11
A. PEKERJAAN PANEL RW 10
1 DPT RW 10 STA 3+192.97 S/D STA 3+212.27 m 19.3 21-Aug-2023 3 24-Aug-2023
2 PAGAR PANEL STA 2+986.41 S/D STA 3+212.27 m 225.86 23-Aug-2023 6 29-Aug-2023

B. PEKERJAAN PANEL RW 16
1 DPT RW 16 STA 3+879 S/D STA 3+912 m 33.00 21-Aug-2023 4 25-Aug-2023
2 PANEL m 210.00 Masih Terkendala Warga

C. PEKERJAAN PANEL RW 11 (DPT,Saluran & Panel)


1 DPT RW 11 STA 2+849.32 S/D STA 3+063,08 m 213.76 22-Aug-2023 4 26-Aug-2023
2 SALURAN STA 2+849.32 S/D STA 3+063.08 m 213.76 28-Aug-2023 4 1-Sep-2023
3 PANELSTA 2+849.32 S/D STA 3+063.08 m 213.76 30-Aug-2023 4 3-Sep-2023

D. PEKERJAAN PANEL RW 07
1 JALAN AKSES WARGA RW 07 STA 2+380 S/D STA 2+2.280 m 100.00 30-Aug-2023 4 3-Sep-2023
2 PAGAR PANEL STA 2+380 S/D STA 2+280 m 100.00 4-Sep-2023 5 9-Sep-2023
3 DPT & PANEL rw 07 RT 05 STA 2+280 S/D STA 2+194 m 86.00 Masih Terkendala Warga

E. PEKERJAAN PANEL RW 08
1 TUTUP SALURAN 5+334.35 S/D 5+228.13 m 106.22 21-Aug-2023 4 25-Aug-2023
2 SALURAN STA 5+310 S/D STA 5+228.13 m 81.87 25-Aug-2023 4 29-Aug-2023
3 PANEL STA 5+464 S/D 5+595.65 m 131.65 28-Aug-2023 5 2-Sep-2023

F. PEKERJAAN PANEL RW 08 DEPAN JL. CIKONENG


1 DPT STA 2+641.87 S/D 2+682.51 m 185.87 21-Aug-2023 5 26-Aug-2023
2 PANEL STA 2+641.87 S/D 2+682.51 m 56.22 26-Aug-2023 5 31-Aug-2023