Kontraktor : CV PURNAMA
B. PEKERJAAN PANEL RW 16
1 DPT RW 16 STA 3+879 S/D STA 3+912 m 33.00 21-Aug-2023 4 25-Aug-2023
2 PANEL m 210.00 Masih Terkendala Warga
D. PEKERJAAN PANEL RW 07
1 JALAN AKSES WARGA RW 07 STA 2+380 S/D STA 2+2.280 m 100.00 30-Aug-2023 4 3-Sep-2023
2 PAGAR PANEL STA 2+380 S/D STA 2+280 m 100.00 4-Sep-2023 5 9-Sep-2023
3 DPT & PANEL rw 07 RT 05 STA 2+280 S/D STA 2+194 m 86.00 Masih Terkendala Warga
E. PEKERJAAN PANEL RW 08
1 TUTUP SALURAN 5+334.35 S/D 5+228.13 m 106.22 21-Aug-2023 4 25-Aug-2023
2 SALURAN STA 5+310 S/D STA 5+228.13 m 81.87 25-Aug-2023 4 29-Aug-2023
3 PANEL STA 5+464 S/D 5+595.65 m 131.65 28-Aug-2023 5 2-Sep-2023