Note: Workers must review the requirements of the AHA prior to starting work.
The AHA must be available at the job site during work activities.
2. Human error 2. Mark or flag equipment and breakers that will be part of
outage.
2. Barricade energized electrical 1. Unauthorized entrants to within the arc
1a. Use red danger tape and stanchions (or similar) to
work area at electrical equipment flash and/or limited approach boundary
encircle the panel at the limited approach boundary.
1b. Position a worker outside of the physical barrier to
also stand guard.
1c. Allow no one inside of the physical barrier who is not
on the electrical team and who is not wearing the required
shock PPE that is identified for the task per the electrical
risk assessment.
1a. Wear shock PPE that is identified for the task per the
electrical risk assessment.
3. Open electrical equipment 1. Electric shock 1b. Remove any conductive material from the top and sides of
the electrical panel before opening the electrical panel.
1c. Use insulated tools to remove bolts and screws from panel
cover.
EQUIPMENT
TOOLS AND EQUIPMENT INSPECTION CRITERIA
1) Insulated Ladder Visual Inspection, Documentation
2) Screw drivers Visual Inspection and Functionality, Cleanliness
3) Wire Strippers Compatibility, Documentation, Visual Inspection
4) Voltage Tester Compatibility, Documentation, Visual Inspection
5) Drill and Bits Compatibility, Documentation, Visual Inspection
6) Circuit Tester Compatibility, Documentation, Visual Inspection
Preparer
Name and signature of person who filled out this AHA: Anoop Anil Kumar Date:28/3/2024
By signing this AHA, the preparer is certifying that the information provided is true, and that any change in the conditions described in this AHA or inadequacies found for
protecting employees during the activity may require a revision to this AHA.
Acceptance by V2X personnelii
Name and signature of Project Administrator: Date:
i
Copies of training certificates must be included with this AHA, with Project-Specific Plans, and/or with the contractor’s APP.
ii
This AHA and other applicable safety documents must be accepted by V2X prior to commencing project work.