Activity Hazard Analysis

Note: Workers must review the requirements of the AHA prior to starting work.
The AHA must be available at the job site during work activities.

Activity: Floor Installation


Project: Renovation Project – Building 102 Al Sayliyah Camp
HAZARDS
ACTIONS TO ELIMINATE OR MINIMIZE
JOB STEP HAZARDS
EACH HAZARD
Floor prep and layout Risk of exposure to asbestos from VCT/ mastic
Reference results of ACM survey.
under lament

Risk of exposure to silica based products


Respirators or dust masks may be required.

Respirator use in accordance with Respiratory Protection Program,


including medical evaluation and fit testing.

Follow the Hot Work Permit as required.


Install flooring Risk of fire from heat gun or open flamed tool
Fire watch is required (trained in fire extinguishers).

Employee shall have proper training on heat guns or open flamed


tools.
Employees are to be trained on the use of tools.

Risk of injuries/ cuts from improper tool use or Protect knifes or open blade with a holder or sheath to protect the blade
storage. while not in use.

Keep all used razor blades in a sharps container labeled as "SHARPS”


PPE
MINIMUM PPE REQUIRMENTS FOR ALL JOB STEPS SPECIAL PPE REQUIREMENTS
1) Hard Hats
2) Goggles NA
3) Safety Gloves
4) Safety Shoes
5) Respiratory Mask

Identify steps requiring special PPE: NA

EQUIPMENT
TOOLS AND EQUIPMENT INSPECTION CRITERIA
1) Tile Cutter Visual Inspection, Documentation, Cleanliness
2) Tile Saw Visual Inspection and Functionality, Cleanliness
3) Trowel Visual Inspection, functionality
4) Grout Float Visual Inspection, functionality
5) Spacer Visual Inspection, functionality
6) Rubber Mallet Visual Inspection, functionality
7) Notched Trowel Visual Inspection, functionality
8) Tile Nipper Visual Inspection, functionality
9) Tile Spacer Clips Visual Inspection, functionality
10) Level System Visual Inspection, functionality

OSHA-RELATED TRAINING APPLICABLE TO THIS ACTIVITY i


Fall Protection Material Handling
Ladder Safety Hazard Communication
Personal Protection Equipment Tools and Equipment Safety
Electrical Safety Emergency Procedures
Hand and Power tool Safety

Preparer
Name and signature of person who filled out this AHA: Anoop Anil Kumar Date:28/03/2024
By signing this AHA, the preparer is certifying that the information provided is true, and that any change in the conditions described in this AHA or inadequacies found for
protecting employees during the activity may require a revision to this AHA.

Acceptance by V2X personnelii


Name and signature of Project Administrator: Date:

Name and signature of EHS POC: Date:

i
Copies of training certificates must be included with this AHA, with Project-Specific Plans, and/or with the contractor’s APP.
ii