印尼苏拉威西 2×50MW 2#机组大修验收方案 清单

First Inspection Procedure list

Turbine 汽轮机
已验收
T001 Steam turbin 汽轮机
(Approved)
已验收
T002 Generator mechanical parts 发电机机械部分
(Approved)
已验收
T003 Oil system 油系统
(Approved)
已验收
T004 Control and protection system 控制和保护系统
(Approved)
缺备件(Not yet
T005 Condenser and auxilliary machine 凝结器和阀门
done)
已验收
T006 Deaerator and accessory valve 除氧器
(Approved)
已验收
T007 Condensate pump 凝结水泵
(Approved)
已验收
T008 Vacuum pump 真空泵
(Approved)
已验收
T009 Boiler feed pump 电动给水泵
(Approved)
已验收
T010 HPH No.1&2 and gsh air exhaust fan 高压加热器
(Approved)
已验收
T011 Main steam system 主蒸汽
(Approved)
已验收
T012 Cooling water system 冷却水系统
(Approved)
已验收
T013 OHT 过热器
(Approved)
已验收
T014 Low pressure heater 低加清洁度
(Approved)
已验收
T015 Insulation valve for steam connection 辅助蒸汽
(Approved)
已验收
T016 Flash vessels 定排
(Approved)