Subject: 2x660MW Jamshoro Supercritical Coal-Fired Power Plant, Contract dated March 29, 2018
Response against NCR Number 228
Reference: 1. Your letter CE/PIUM/CFPP/PIU/3394, dated 18th January 2023 for NCR 228
Dear Sir,
This is in the response to the above-referred letter. We would like to submit a response against
Non-Conformance Report (NCR) along with pictorial evidence.
NCR-228 relates to non-conformity of the Male Nurse and Ambulance. EPC wishes to inform that
the male nurse has been rehired to meet the legal requirement and the ambulance is now available
to response to emergencies.
We are looking forward to your cooperation.
Best Wishes,
Zhang Liming
Project Manager
Consortium of Siemens Aktiengesellschaft and
Harbin Electric International Company Limited.
(Siemens-HEI Consortium)
Attachment:
1. Response on NCR # 228 dated 3rd January 2024