Gantt Chart L
Gantt Chart L
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 CIVIL WORKS - -
1.1 CONCRETE BASE Sun 7/02/23 Fri 7/07/23 6 0% 5
1.2 STEEL FRAME Sat 7/08/23 Sun 7/09/23 2 0% 0
1.3 CORING Sun 7/02/23 Wed 7/12/23 11 0% 8
4 Duct works - -
4.1 Supply and Return Duct with all access. Thu 7/13/23 Wed 7/19/23 7 0% 5
4.2 Coring for grills Sun 7/16/23 Wed 7/19/23 4 0% 3
4.3 Fire Stop Sealant Sun 8/27/23 Thu 8/31/23 5 0% 4