Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

1

TANGEDCO
CHENNAI NORTH EDC PWLC SEHEDULE OF RATE - 2020

SL. Approved
DESCRIPTION OF WORKS UNITS
NO Rate

I ERECTION OF DOUBLE POLE STRUCTURE WITH DISTRIBUTION TRANSFORMER.


1 Excavation of Structure Pole Pit 2' x 3' x 1/6 th of height of pole per pole 550
2 Erection of 9.14 M RCC/9.0 Mtr PSC /RSJ pole per pole 600
3 Transporting of 9.14 m poles from Road side to pole pit per pole 300
Structure pole mass Concreting and coping 0.6x0.6x1.65 mtr for DP
4 per pole 2600
structure Including cost of materials and cement.
Erection of structure materials complete such as top channel, seating
5 channel, belting angle, cross bracing. DPDC channel, T.I. Fitting etc., in Per Set 2200
complete.
6 Excavation of stay pit 0.95x0.60x1.5m Per Set 300
7 Erection of Stay Set Complete Per Set 300
8 Sleeve concrete for stay set including all materials & cement 1 Loc 700
9 Erection of HG fuse set with transport 1 set 450
10 Erection of 11 KV AB switch complete set with transport 1 set 1500
Transformer structure grounding and earthing of structure complete
11 including excavtion of earth pit and erection of earth pipe with salt, coal and 3 earth pits 2300
earth refiling etc., complete with trough / w.o. trough
Erection of Aluminium bus bar pipe complete for H.T. Bus bar
12
arrangements for DP Structure
a) For Double Pole Structure 1 set 750
b) For Triple Pole Structure 1 set 1300
c) For Four Pole Structure 1 set 1500
Erection of L.T. Open type fuse unit including cable jumpering upto the
13 1 unit 500
line.
Providing LT bus bar arrangements in DT structure including fixing of cross
14 1 set 500
arm and insulator.
15 Erection of H.T. jumpering in DP structure complete (150 * 3) 1 set 450
16 Erection of H.T. LAS (3 Nos) 1 set 300
17 Erection of L.T. LAS (4 Nos) 1 set 180
18 Erection of DT excluing loading and unloading using Crane
a) 63 KVA / 100 KVA 1 No 1500
b) Above 100 KVA 1 No 1700
Painting of two coats of Aluminium paint for DP structure and iron materials
19 including cost of paint and distemper etc. Without 1 set 1000 / 2200
Material / With Material

20 Painting of Structure pole with Distemper including cost of material Each 300
Loading and unloading of Distribution Transformer at site and store. (All
21 1 No 1000
Rating)
Dismantling of failed DT from the structure including removing HT & LT
22
connection and all other incidental works. (excluding loading and unloading)
a) Upto 100 KVA 1 No 750
b) Above 100 KVA 1 No 850
2

II LAYING OF HT CABLE
Excavation of cable trench 0.6 meters width and 1.2 meters depth including
1 cost of providing sign boards, danger lights, indication arrangements lead,
lift, labour and tools and plants etc.,
a) Normal Road (earth) R.M 150
b) Tar Road R.M 200
c) Concrete Road R.M 350
Transporting of 11 KV HT cable from departmental stores to work spot by
2 engaging private vehicle including recoiling ,coiling and loading and
unloading at both sites.
a) Loading and unloading of HT Cable Perdrum 500
b) Transporting of HT Cable Per 5 Km 1500
c) Transporting of HT Cable above 5 Km Per Km 50
3 LAYING OF HT CABLE
a) Laying of 11KV 3 X 300 sq mm XLPE cable R.M 24
b) Laying of 11KV 3 X 120 sq mm XLPE cable R.M 21
Covering HT cable by cement "V" trough after covering the cable with good
4 loose earth including loading, unloading and transport from stores to site 1 No 20
and letter painting of feeding details & Cable size on the trough

Refilling with excavated earth layers well consolidated as per std


5 R.M 15
specification including all materials, lead, lift etc., complete.

Transport back any balance cable, empty drums and other materials if any
by engaging private vehicle including recoiling, coiling and loading and 1 Trip
6a 1200
unloading at both sides from workspot to departmental stores (minimum 2 upto 5 Km
drums)

6b above 5 Km per km 50
III LAYING OF LT CABLE
Tansport of LT cable by engaging private vehicle including recoiling, coiling,
1
loading & unloading at both sites.
a) Loading and unloading of LT Cable Perdrum 500
b) Transporting of LT Cable Per 5 Km 1500
c) Transporting of HT Cable above 5 Km Per Km 50
Excavation of cable trench size 0.45m x0.75 m including cost of providing
2 sign boards, danger lights, indication arrangements, lead, lift, labour and
T&P etc.
a) Normal Road (earth) R.M 100
b) Tar Road R.M 150
c) Concrete Road R.M 240
3 LAYING OF LT CABLE
a) Laying of 240 sq.mm cable R.M 16
b) Laying of 120 sq.mm cable R.M 13
c) Laying of 25 sq.mm cable R.M 11
d) Laying of 16 sq.mm cable R.M 9
Refilling with excavated earth layers as per std specification including all
4 R.M 10
materials, lead, lift etc., complete.
3

IV ERECTION OF PILLAR BOX

Erection of pillar box including excavation of foundation pits as per standard


1 specification 2 Nos pillar concrete walls, coping and earthing including cost
of all materials, el. works, transportation, lead, lift etc.,

a) 4 / 6 Way Pillar Box - 3 Feet Height using Concrete only Per Loc 4500
b) Mini Pillar Box - 3 Feet Height using Concrete only Per Loc 3000
Cleaning&painting with Aluminium paint 2 coats & numbering with fdr
2
details with materials /with out materials
a) 8 way pillar box per box 900 / 600
b) 6 way pillar box per box 800 / 500
c) 4 way pillar box per box 600 / 400
d) Mini way pillar box per box 500 / 200
V DISMANTLING OF PILLAR BOX

Dismantling of old pillar box including associated accessories, loading on the


1
vehicle, transporting, unloading at stores and stacking.

a) 4/6/8 way pillar box per box 500


b) Mini pillar box per box 200

VI MISCELLANEOUS
Erection of RCC/RSJ/PSC pole and other poles including excavation of pole
1
pit (pit size 2'x3'x1/6th of the length of poles)
a) Excavation of pole pit for 7.5/8 metres per each 500
b) Erection of pole pit for7.5/8 metres per each 550
c) Excavaion of pole pit for 9.14 metres per each 550
d) Erection of pole pit for 9.14 metres per each 600
e) Trasportation of pole of all sizes from Road side to work spot per each 300
f) Trasportation of pole of all sizes from Stores to Road side upto 2KM per each 300
Above 2 Km - Per Km Per Km 75
2 Base concerting 30 cm thick for one pole including of all materials per each 450
Transporting of DTs/Metering sets/Line Materials through private vehicle
3 Per Trip 1500
from store to work spot / vice versa upto 10 Km
above 10Km / Km Per Km 50
4 Erection of V cross arm 3 1/2' size per each 150
5 Erection of V cross arm 4 1/2' size per each 200
6 Erection of Tapping channel 5 ' size / V Cross Arm 5' size per each 200
7 Excavation of stay pit per loc 300
8 Erection of stay set complete per set 300
9 Fixing of 11 KV TI fitting per each 60
10 Fixing of 33 KV TI fitting per each 60
11 Fixing of LT 3 phase cross arm per each 100
12 Fixing of LT TI fitting per each 60
13 Fixing of single phase cross arm per each 70
14 LT pin insulator with pin per each 40
15 LT shackle with strap sets per each 50
16 11 KV pin insulator with GI pin per each 50
17 33 KV pin insulator with GI pin per each 60
18 11 KV strain disc with metal parts per each 70
19 33 KV strain disc with metal parts per each 100
20 Fixing of Aluminium knob per each 20
4

21 Fixing of caution / Danger Board per each 75


22 Providing of fly stay (excluding pole erection and earth excavation) per loc 250
Concreting of poles with 1:3:6 mix, 1.1/2 broken metal jelly and M sand
23 including coping (M sand, jelly and cement, will be supplied by the
contractor) (size 2x3x1/6th of pole height)
a) 7.5 metres/8 metres pole per each 1500
9.14 metres pole (with coping of 1' dia upto height of 1.1/2' above ground
b) per each 2500
level)
24 Earthing of poles per each 100
Paving out conductor, stringing and sagging of line of all sizes of ACSR /
25 AAAC conductors of HT/LT lines including pin binding of supports and
terminating at shackle points using aluminium roller, including jumpering.
a) 7/2.59 mm ACSR/7/2.50 AAAC RM 3
b) 7/3.35 mm ACSR/7/3.15 AAAC RM 4
c) Raccoon 7/4.09 mm RM 6
d) Dog conductor 7/4.72 mm RM 7
26 Numbering of location/each including cost of paint and labour Per loc 50
27 Providing of guarding per span excluding of stay set erection
a) 2 wire flat guarding(Split neutral grounding) per span 400
b) 4 wire flat guarding per span 800
c) Craddle guarding including earthing and earth pit excavation per span 1500
Erection of street light fittings 2 feet/4 feet (All materials supplied by the
28 per each 180
Board) Labour alone.
29 Erection of cross bracing set 10' / 15' Structure
a) DP structure per each 400
b) TP structure per each 600
30 Erection of Top Channels 10' / 15' Structure
a) DP struture per each 250
b) TP structure per each 300
31 Erection of 33 KV centre rotating AB switch complete set per set 3000
32 Erection of 11 KV centre rotating AB switch complete set per set 2000
33 Erection of spacers & jumpers
a) Single phase spacer per each 40
b) Three phase spacer per each 50
c) jumper per phase for LT per each 40
d) Jumper per phase for HT per each 50
e) Provision of 'PA' jumpers per each 30
34 Metering set loading & unloading
a) Loading per set 500
b) Un loading per set 500
35 Erection of metering sets
a) Up to 11KV metering set per set 1000
b) Above 11KV metering set per set 1200
36 Loading of poles
a) 7.5/8 metres pole (RCC/PSC)/Each per pole 200
b) 9.14 metres pole RCC /9.0 mtr PSC/9.14 RSJ /Each per pole 300
37 Un Loading of poles
a) 7.5/8 metres pole (RCC/PSC)/Each per pole 200
b) 9.14 metres pole RCC /9.0 mtr PSC/9.14 RSJ /Each per pole 300
38 Loading of conductor
a) Conductor drum of all sizes with conductor per drum 400
b) Conductor drum of all sizes without conductor per drum 100
5

39 Un loading of conductor
a) Conductor drum of all sizes with conductor per drum 400
b) Conductor drum of all sizes without conductor per drum 100
Manufacturing of MS clamps at works spot as per requirement , including
40
alteration by using (with material)
a) 50x8 mm flat per clamp 150
b) 65x10 mm flat per clamp 170
41 Cutting of channels/Flats/Angle
a) Channel/Flat/Angle per cutting 50
b) RSJ pole cutting per cutting 150
c) Tubular pole cutting per cutting 100
d) Rail pole cutting per cutting 150
e) Drilling of 5/8", 3/8", 1/" Holes in Channels / Angles
i) Slot Holes Per hole 100
ii) Round Holes Per hole 50
VII MAINTENANCE WORK
1 Maintenance of DT structure for various capacity (pole mounted structure)
a DP/TP Structure maintenance Per Structure 1200
b DT maintenance Per DT 350
c Structure earthing wire redoing Per loc 350
d Replacement of Structure earthing in complete without material per set 1500
e DT structure Yard cleaning Per loc 150
f Watering to earth pits Per loc 50
g Numbering of location including cost of paint and labour Per loc 50
Maintenance of pillars works such as replacement of damaged insulators
2
worn out stembolts, lugs, termination of cables and dressing.
a) 8 way pillar box Per Box 800
b) 6 way pillar box Per Box 600
c) 4 way pillar box Per Box 400
d) Mini pillar box Per Box 300
e) Numbering of Pillar with feeder details including cost of paint and labour Per Box 150
Maintenance of 11 KV ABS only. (Checking of alignment and replacement
3 of wornout fixed and moving contacts PT insulator, changing earthing and
Lubricating).
a 11 KV AB switch at structure per set 750
b 11 KV AB switch at SS per set 900
Maintenance of 33 KV ABS only. (Checking of alignment and replacement
4 of wornout fixed and moving contacts PT insulator, changing earthing and
Lubricating).
a) 33 KV AB switch at structure per set 1000
b) 33 KV AB switch at SS per set 1600
5 Tree cutting (Tree clearance)
a) Cutting of big tree fouling on the line. per tree 250
b) Cutting of tree branches fouling on the line. per tree 100
c) Clearing of heavy bushes per sq.mtr 25
d) Jungle/bushes/velikathan clearence per sq.mtr 10
6 Set righting leaned HT/LT Poles
a) Pin Point location per loc 300
b) Cut Point Location per loc 500
6

7 Resagging of HT/LT lines for all conductor sizes


a) Re-sagging (HT) 7/4.72 mm RM 5
b) Re-sagging (HT/LT) 7/4.09 mm RM 4
c) Re-sagging (HT/LT) 7/3.35 mm RM 3
d) Re-sagging (HT/LT) 7/2.59 mm RM 2
8 DC & RC of service wire in LT line
a) DC of Single phase service Per Sc 25
b) DC of Three phase service Per Sc 40
c) RC of Single phase service Per Sc 25
d) RC of Three phase service Per Sc 40
VIII DISMANTLING WORKS
1 Dismantling of 7.5m/8.0m Poles per pole 275
2 Dismantling of 9.14 Mtr. Poles/RSJ/Tubular Poles per pole 300
3 Dismantling of Stay set complete per pole 150
Dismantling of conductors including Coiling and Transporting from workspot
4
to road side
a) upto 7/3.35 mm without transport RM 1.25
b) above 7/3.35 mm without transport RM 2.50
5 Releasing of LT S ph "X" Arm/TI Fitting per each 35
6 Releaasing of LT 3 ph "X" Arm per each 50
7 Releasing of 3' - 6" "V" Cross Arm/Tapping channal/Guarding "X" Arm per each 100
8 Releasing of 4' - 6" and "V" Cross Arm per each 100
9 Releasing of 5' "V" Cross Arm per each 100
10 Releasing of Distn.Tr. Only at field per DT 850
11 Dismantling of Transformer Structure materials
a) upto 100 KVA per set 1100
b) Above 100 KVA per set 1100
12 Dismantling of AB Switch at Structure
a) 11 KV AB switch per set 375
b) 33 KV AB switch per set 500
13 Dismantling of H.G. fuse set per set 225
14 Dismantling of HT LAS at DT Structure per set 150
15 Dismantling of LT LAS at DT Structure per set 90
16 Dismantling of Earth Pipe and Structure earthing complete per set 1150
Dismantling of 2 Sets Open type fuse unit with all wiring complete(including
17 per set 250
bus bar arrangement)
18 Dismantling of cross bracing set per set 300
19 Dismantling of Top Channel per each 150
20 Dismantling of Guarding including Dismantling of cross arm per span per span 300

21 Dismantling of Single ph service wire & re-effecting service including meter per Sc 100

22 Dismantling of three ph service wire & re-effecting service including meter per Sc 140
Breaking of RCC Damaged Poles after dismantling,releasing the grill
23 per pole 200
including transporting to Road side
24 Stacking materials/Scrap per tonne 500
IX Substation Maintenance
a Cleaning of 110 KV Breakers including CTs and allied maintenance work per set 250
b Cleaning of 110 KV LAS per set 180
c Cleaning of 110 KV AB switch and applying petroleum jelly per set 250
Cleaning of 110 KV Power transformer insulators and assisiting for all other
d per Pr.Trf 450
maintenance works
7

e Cleaning of 33 KV/11 KV Breakers and CTS and allied maintenance works per set 250
f Cleaning and checking of 110 KV Bus insulators per stack 100
Cleaning and checking of 33 KV/11 KV AB switches including tightening of
g per set 200
bolt and nut and applying Petroleum jelly
h Releasing and refixing of clamp in 110 KV/33 KV/11KV buses per clamp 200
Maintenance of 110 KV ABS only. (Checking of alignment and replacement
i per set 1500
of wornout fixed and moving contacts, and Lubricating).
j Removing weeds in Substation/Office premises (Jungle Clearance) per sq.mtr 12
k Hot oil circulation of Tr.oil in Pr.Tr. With filter machine & loading. per Ltr. 1.8
l Releasing of Tr. Oil from Pr.Tr. per Ltr. 0.5
m Transporting of filter machine unit (to&fro) per trip 6500
n Loading of Tr.oil drum with oil per drum 50
o Un loading of Tr.oil drum with oil per drum 35
p loading /unloading of empty drum per drum 10 / 10
IXA Fixing of Missing doors in Pillars
i). MS Mini pillar door per each 650
ii). MS 4 way pillar door per each 1100
iii). MS 6 way pillar door per each 1800
iv). MS 8 way pillar door per each 2500
v). FRP 4 way pillar door per each 900
vi) Provision of 2 Nos Hinges Per Box 200
X UG CABLE FAULT RECTIFICATION WORK
A ATTENDING TO FAULTS IN 11KV & 33KV CABLES BY DOING IT MANUALLY
Earth work Excavation to the required depth, width(cable route) is 1.2m x
1 0.6m respectively (As per prevailing PWLC Rates)
HT Cable
a) Normal RM 150
b) Tar RM 200
c) Concrete RM 350
LT Cable
a) Normal RM 100
b) Tar RM 150
c) Concrete RM 240
Installation of joint by private jointer in the absence of company jointer
2 (intimation to be given to company through mail/ company phone Nos and
record to be maintained)
a) 11 KV LS 1200
b) 33 KV LS 2500
Refilling with M- sand over the cable and joints (cost of M.sand as per PWD
3
schedule of rates @ Rs.1590/- per cub.M
a) 11 KV (10mx0.6mx0.15m)=0.9 cub.mx1590 per loc 1430
b) 33 KV (15mx0.6mx0.15m)=1.35 cub.mx1590 per loc 2150
4 Refilling labour charges /mtr
a) LT Cable RM 10
b) HT Cable RM 15
Transporting of cables and joint kits from stores to site (SL.NO.7 or 8 ,
5
whichever is applicable)
a) 11 KV LS 1000
b) 33 KV LS 1000
Transporting of cables and joint kits from office to site (SL.NO.7 or 8 ,
6
whichever is applicable)
a) 11 KV LS 500
8

b) 33 KV LS 500
9

RATES FOR LABOUR & TOOLS & PLANT USED FOR ATTENDING TO
B
33KV & 11KV CABLE FAULTS
1 Hire Charges
a) Hire charges for engaging JCB per Hour 750
b) Hire charges for engaging Crane per Hour 750
Installation of joint by private jointer in the absence of company jointer (intimation
2 to be given to company through mail/ company phone Nos and record to be
maintained)
6000
a) 11 kv fault LS (Max 8
7500 Hrs)
b) 33 kv fault LS (Max 10
Hrs)
Engaging Hydraulic compressor (Tractor) for Breaking concrete/Tar Roads
2 per Hour 500
(Wherever Necessary)
Rental for de-watering pump as per PWD schedule of Rate (Wherever
3 Per day 1850
necessary)
Engaging Labour for Manual excavation and cleaning the trench, joint pit
4
excavation and identify the cable in addition to engaging JCB.
1880
a) 11 KV (Semi skilled Labour @ Rs.470/head) Per day
( 4 Person)
2820
b) 33 KV (Semi skilled Labour @ Rs.470/head) Per day
( 6 Person)
Concreting after rectification of fault by using PCC 1:3:6 ( If applicable, with
5 necessary justification & certification by concern Executive Engineer For
reqd length,width and depth as per site condition)
11/33 KV per cum 4900
LAYING OF UG CABLE USING TRENCHLESS METHOD FOR FAULT
XI
RECTIFICATION / NEW WORK
a) Laying of HT UG Cable using Trenchless Technology without pipes Per mtr 1900
b) Laying of HT UG Cable using Trenchless Technology with pipes Per mtr 2900
XII Single Pole Structure Work
1 Loading and Unloading of 9.0m Square Pole Per Each 600
2 Excavation of Pole Pit Per Each 600
3 Erection of 9.0m Square Pole Per Each 550
4 Transporting of Square Pole from Road Side to Pole Pit per pole 300
5 Excavation of stay pit 0.95x0.60x1.5m per loc 300
6 Erection of Stay Set Complete per set 300
7 Fixing of Single Pole Structure Material in complete shape per set 3000
8 Erection of 16 / 25 / 40 KVA Distribution Transformer per each 1300
Transformer structure grounding and earthing of structure complete
9 including excavtion of earth pit and erection of earth pipe with salt, coal and Set 2300
earth refiling etc., complete with trough / w.o. trough
Structure pole mass Concreting and coping 0.6x0.6x1.65 mtr for DP
10 per pole 2600
structure Including cost of materials and cement.
11 Sleeve concrete for stay set including all materials per loc 700
12 Erection of HT LAS (3 Nos) per set 300
13 Erection of LT LAS (4 Nos) per set 180
14 Erection of LT Wiring Kit (Double Open Type Circuit) per set 750
Painting of single pole structure including iron materials double coat with
15 Per Structure 500 / 1100
materials / without materials
16 Painting of Structure pole with Distemper including cost of material per pole 300
10

SUPERINTENDING ENGINEER
CEDC/NORTH

You might also like