Professional Documents
Culture Documents
L 4 Civil Engineering Drawing III Lecture 4
L 4 Civil Engineering Drawing III Lecture 4
68
Accurate detailing has an important role in the procurement and durability of
reinforced concrete structures. The preparation of final reinforcement
drawings and schedules is generally squeezed into a period between completion
of final design and the start of construction on site.
Once the reinforcement drawings and schedules gain the status of construction
drawings they are distributed to the relevant parties. In traditional contracts,
the reinforcement drawings and schedules will be issued to the Contract
Administrator and to the main contractor, client’s Quantity Surveyor, etc.
The reinforcement is placed and fixed by steel fixers then checked in-situ.
They also provide the detailer with the layout and sectional information
required to specify the length, shape and number of each type of reinforcing
bar.
69
3.3.2.2 Reinforcement Drawings
Reinforcement drawings describe and locate the reinforcement in relation to
the outline of the concrete work and to relevant holes and fixings.
Separate drawings or plans for top and bottom layers of reinforcement should
be used only for fabric and in exceptional cases, e.g. voided bridge decks and
box girders with four layers of reinforcement.
Reinforcement drawings are primarily for the use of the steel fixers. It is
preferable that general arrangement and reinforcement drawings be kept
separate, but for simple structures a combined drawing may be appropriate.
3.3.2.3 Standard Details
Standard details are those details that are used on a repetitive basis. Details
used in this way must be carefully worked out, fully detailed and totally
applicable to each location where they are to be specified. Standard details
may apply to concrete profiles or reinforcement arrangements, and they
should be drawn to a large scale
3.3.2.4 Diagrams
Diagrams may be used as a means of communicating design ideas during both
pre-contract work and the post-contract period. Diagrams may be formally
presented or sketched freehand providing they convey information clearly,
neatly and in detail.
3.3.2.5 Record Drawings
When the reinforced concrete structure has been constructed, the original
drawings used for the construction process should be amended to indicate any
changes in detail that were made during the construction process.
3.3.3 Abbreviations
Standard abbreviations are recommended but, if there is any risk of confusion
or ambiguity with their use in any particular circumstances, then the words
should be written in full. No other abbreviations should be used unless clearly
defined on all the drawings on which they appear.
70
3.3.4 Title and Information Panels
Key information relating to the job and drawings should be placed in the
bottom right-hand corner of the drawing sheet.
project title
drawing title
office of origin
scales
drawn by (name)
checked by (name)
date of drawing.
71
Cross-sections of reinforcement should be drawn approximately to scale.
3.3.6 Lettering
Distinct and uniform letters and figures ensure the production of good, legible
prints; the style should be simple. Capital letters should be used for all titles
and sub-titles and should preferably be mechanically produced. Lower-case
letters may be used in notes.
3.3.7 Dimensions
The general arrangement drawing should show all setting-out dimensions and
sizes of members. The reinforcement drawings should contain only those
dimensions that are necessary for the correct location of the reinforcement.
Dimensions should be written in such a way that they may be read when
viewed from the bottom or the right-hand side of the drawing. They should,
where possible, be kept clear of structural detail and placed near to and above
the line, not through the line.
For site layouts and levels, the recommended unit is the metre. For detailing
reinforcement and the specification of small sections, the recommended unit is
the millimetre. It is not necessary to write mm.
72
Dimensions should normally be to the nearest 5 millimetre. Thus:
3.3.8 Levels
3.3.8.1 Datum
On civil engineering and major building works it is usually necessary to relate
the job datum (a temporary benchmark, TBM, or transferred OS benchmark)
to the Ordnance Survey datum. On other works, a suitable fixed point should
be taken as job datum such that all other levels are positive. This datum
should be clearly indicated or described on the drawings, and all levels and
vertical dimensions should be related to it.
3.3.9 Scales
The following scales are recommended as a suitable for concrete work:
73
3.3.10 Gridlines
A grid system provides a convenient datum for locating and referencing
structural members, as shown in Figure 3.5.
Grid notation should be agreed with the architect and would normally be
numbered 1, 2, 3, etc, in one direction, and lettered A, B, C, … X, Y, Z,
AA, AB, etc. (omitting I and O) in the other direction. These sequences
should start at the lower left corner of the grid system. Supplementary
grids, if required, can be incorporated within the system and identified as
follows. Aa, Ab, Ac, Ba, 2.5, 4.2, etc.
74
assumes a horizontal section drawn immediately above the surface of the
structural arrangement or component. Dimension lines should be kept clear of
the structural details and information.
75
76
77
78
Example of general arrangement drawing for concrete structures
79
3.4.2 Layout of Foundations
The position of each foundation should be given relative to the grid lines. The
width, length and depth should be given and the level of the bottom of the
foundation should be given relative to a given datum.
80
3.4.3 Layout of stairs
The stair structural layout or general-arrangement drawing should indicate all
the dimensions required to set out the concrete profile as shown in Figure
3.6.
81
The architect will normally locate the stair between floors using the top of
the finishes as the vertical datum. The height of risers will be equal but the
thickness of finish may vary, particularly at floors and landings. It follows
that structural risers may vary in height. Treads may require sloping risers to
provide a nosing, and fillets may be needed to maintain a constant waist
thickness (see Figure 3.7).
It is often arranged that the finishes to nosings of adjacent flights will line
through across the stair. Sometimes the junctions of all soffits are made to
line through.
82
3.4.4 Project introduction
Brief:
Draw and detail structural drawings for a simple residential house for which
you have completed architectural drawings
83
Step 1: General arrangement drawings
Develop slab and beam layout drawings for the upper floor slab of your house.
Submission:
84