Professional Documents
Culture Documents
3258 GCL New
3258 GCL New
Node Information
Site ID 3258 End Site 2893
Site Config 2G900, 3G900, L1800, L2100, L800, L2300 Owner Information Open Site (Site Located inside Green Belt of Road)
36m Lightpole NA
Site Type SCECO Number
Cable ladder is to be horizontal on cross sections and vertical on rising sections. It is to be firmly
1.4 Cable ladder indoor Major OK NOK N/A
secured. Cable ladder elements must be electrically linked with Earthing straps which must be
properly terminated and short. There must be no ornamental loops in the links. MNS E&M
1.6 Clear up / rubble removal Minor OK NOK N/A Is site and surrounding area clear and clean? MNS Telecom
The site should be of a good appearance & show attention to detail. The equipment room is clean
2.1 Cleaning of Site and Surroundings Minor MNS Telecom/ E&M
& free of all rubbish. All unused materials are to be cleared from the site & properly disposed of.
Page 1 of 8
The access procedure must be submitted for sites in restricted area and give time to MNS to apply
4.5 Access procedure and permissions Major OK NOK N/A for long period permissions. Access permission for rental Generator team hould be ready and
avilable for two weeks before the need to renewal by Implementation Team or as per approved
condition and in case of sharing will follow owner condition. MNS Telecom/ E&M
5. AC Power installation
after SEC meter cables are selected & routed in a safe way & in accordance for site design
Mains Power Cables/Breakers(Permanent / Temporary) Major OK NOK N/A drawings & SCECO requirement. The supply cable & breaker must be of correct rating & type
5.1 referance to approved design. MNS E&M
Temporary Generator should be free from leakage; sound proofed with sound attenuated
5.2 Temporary (rented) generator Major OK NOK N/A
facilities ; it should operate with fixed voltage & frequency values; generator with its fuel tank & MNS E&M
cabling (male/female and right size of cable) should be properly/safely installed
in case of new Genset is tested and passed as per PAT document. Checked for correct make & type
OK NOK N/A
(according to specifications, & approved martial list & site generic drawings) & functional. Clear
7.1 Mobily (permanent) GenSet Major MNS E&M
from damages. The genet is free from fuel, oil & water leakage. Serial numbers are according to
commissioning document or as per dismantling sheet in relocated.
OK NOK N/A
ATS Major
7.3 ATS including its component to be functional (according to specifications). MNS E&M
To be tested and accepted as per PAT document and free from leakage & major Damages. Fuel
7.4 Fuel system installation Major OK NOK N/A
MNS E&M
level senior is connected and alarm can be reported to NOC.
The canopy shall be installed correctly, sound proof, corrosion free, sound level at 1 m away NGT
Canopy & Key Minor OK NOK N/A
Page 2 of 8
8. Earthing and Lightning Protection
All metallic equipments should be connected to grounding (like
8.1 Earthing of metal parts Major OK
NOK N/A
tower,mast;poles;fence;gate;shelter;Generator;ladders;railings;equipments;feeders;support MNS Telecom
frames, fuel tank, etc)
With proper installation, highest position, Lightning arresters are needed for four-legged tower in
8.5 Lightning arrester/rod Major OK NOK N/A
MNS E&M
heavy rain areas while lightning rods are for monopole.
9. Air Conditioning
OK NOK N/A
As per PAT document (The Ac system is of the correct brand & & type, positioned correctly & in a
9.1 ACU system installation Major OK
NOK N/A
location, safe from damage. The units & control panel are functional, fixed correctly, free of MNS E&M
corrosion, earthed & correctly wired. Drain pipe is properly fixed and unclogged)
The fire protection system is available, correct type (according to specifications), correctly
12.1 Fire Extinguishing System Major OK
NOK N/A
fastened & connected, nozzle is installed & the inspection sheet/tag available. Trigger of MNS E&M
automatic release mechanism is tested & found working properly.
12.2 Is of correct type (3 kg CO2) with inspection sheet / tag available & sealed. MNS E&M
in case of new The Battery back up should working properly. The Battery showing the correct
12.3 Battery Back up Unit Major OK NOK N/A
MNS E&M
value or as per dismantled check list for relocated site.
As per PAT document (Rectifier & Battery cabinet is in the position noted in the new site layout.
13.1 Mechanical Installation for Rectifier and Batteries Major OK
NOK N/A
the cabinet are secured to the floor in accordance with specification. No damages were found & MNS E&M
no leakage is seen on batteries. Batteries Temperature sensor cable is correctly)
The internal battery connection straps are positioned & connected correctly. The cables from the
Rectifier & Batteries Interconnection Major OK NOK N/A
Battery banks to the BFU are of the correct size / type , routed, & terminated properly. Battery
13.2 lugs are greased properly. MNS E&M
as per PAT document (The Fuse Unit is installed with correct rating, undamaged & labeled. All
13.3 DC Distribution Panel Major OK NOK N/A
MNS E&M
installed fuses are functional & its protection rating as per designated load requirement.) for
The Battery Load Test Results sheet is available on site & shows that the Load Test was correctly
Batteries Bank Testing Major OK NOK N/A
carried out & the result was satisfactory. Battery Serial Numbers comply with serial numbers on
13.4 Test Sheet. MNS E&M
13.5 DC System Operation Major OK NOK N/A
DC system has been commissioned & tested & found working properly without alarm MNS E&M
Manufacturer:…………………………… Product No………………………………No of Modules
Rectifier minor OK NOK N/A
Page 3 of 8
CB rating should be matching Equipment.this is for expansion and new addition of the equipment
Circuit Breaker Rating Major OK NOK N/A
in any exsting sites then power breaker ratings to be matched with Vendor equipment power
13.10 consumption. MNS Telecom
Labels must be applied correctly and in the specified positions.if CB cnnected to telecome then it
13.11 All breakers should be labeled Minor OK NOK N/A
MNS Telecom/ E&M
should labeled for specfic equipment
13.12 Battery Fuse unit (BFU) Major OK NOK N/A Must be properly seated and bolted into place MNS E&M
13.13 Batteries Installed Major OK NOK N/A
Physical Check MNS E&M
OK NOK N/A
The fence must be erected in accordance with the site drawings. Support post must be vertical.
14.1 Fence/ shelter door Major The chain link fence is 2.75 metres high. Any damage in the fence, which will lead to security MNS E&M
breach is not accepted, meanwhile small cuts in the fence will be considered as minor
OK NOK N/A
15.2 Radio Cabinet housing fastening bolts are completed & tightened properly. MNS Telecom
It should be in correct position in accordance with site layout,& clear from damages. Any changes
15.3 BTS & indoor MW Installation/Physical check Minor OK
NOK N/A
MNS Telecom
in the drawings to be updated and submitted to MNS
15.4 the BTS was tested & found functional with no alarms. all indicating leds are ok MNS Telecom
15.5 Sweep Test(VSWR-with & without TMA ) Major OK NOK N/A
VSWR are all NGT 1.4:1 for GF & RT sites. For Indoor & microcell sites the VSWR is not NGT 1.8:1 MNS Telecom
OK NOK N/A Antenna height, tilt, azimuth installed as per the RF & MW design. Antenna & Sector (Location &
15.7 Antenna Direction, Tilt & Height Major MNS Telecom
Orientation) its not blocking another antennas or sector coverage for another projects.
OK NOK N/A All cables should run properly , fixed with standardized clamps. Clamps are not loose & fixed
Feeders , Jumpers and Ethernet Cable Installation Major OK
NOK N/A
properly, distance between two clamps is 60cm for 1/2 S/F,80cm for 1/2 foam,120cm for 7/8" and
15.8 OK NOK N/A
140cm for 15/8".No mixed cables allowed. No feeders sharp bend (no sharp angle) allowed. MNS Telecom
NOK N/A
OK
The site is clear from all internal alarms(including not limited to VSWR, RX diversity, power limit
15.9 BTS/ Node B Remote Check Minor MNS Telecom
exceeded, ect..) The latest SW is installed & accepted by OMCR
If called up they must be of the specified type and installed in accordance with site drawings and
Wall brackets and or equipment spacers Major OK NOK N/A
15.11 Cable ladder, Trunking and Cables inside secure Minor OK NOK N/A
Firmly fixed and secured properly, with fixtures correctly Vertical or Horizontal. MNS E&M
15.12 Internal Optical cables connected Major OK NOK N/A Internal Optical cables connected. MNS Telecom
RBS should have proper ventilation and easy maintain.Ventilation should not be blocked due to
15.13 RBS Ventilation Major OK NOK N/A
MNS Telecom
any Hardware or cables.
Check RRU Power Connectivity and breaker ratings.Power should be connected on breakers in AC
RRU Power Connectivity Major OK NOK N/A
Page 4 of 8
15.16 Dummy panel covers. Major OK NOK N/A Must all be in place and correctly fixed. MNS Telecom
15.17 Feeder/Fiber Lengths. Minor OK NOK N/A
Lengths should be as per design and housed in box MNS Telecom
The Feeders must enter through the Roxtec in the correct positions. They must be set in the
Feeder/Cable/Fiber lead-in (Cable glands / Roxtec) Major OK NOK N/A
15.21 Flexible Pipes installation and cable tie Minor Check tie wraps and flexible pipe installation.properly closed from outdoor. MNS Telecom
Cable ties should be of a standard pattern throughout. They must be placed in a uniform manner,
e.g. the tongue must always point in the same direction (before trimming) and the locks should be
Clamps or cable ties installed Minor OK NOK N/A
level with each other. Colour should be uniform bearing in mind that white cable ties are not UV
protected, they should not appear on external elements. N.B. all cable ties must be trimmed after
tightening. The tongues must be cut off flush using a tie wrap tool or the flat side of a good pair of
15.22 side cutters. Clamps MNS Telecom
15.26 Check Bracket,Ventiliation,Temperature should be as per site lay out and accessible. MNS Telecom
OK NOK N/A
15.27 Pole popullated Minor
Check antenna installation(Mount and Antenna). MNS Telecom
TMA,Duplexer,Splitter installed (if specified in configuration data in IE
Major OK
OK NOK
NOK N/A
N/A
15.28 document) if applicable Must be installed in accordance with site drawing and functional. MNS Telecom
OK NOK N/A Check GPS for bloakage and other antenna as per standards (>10 m).Sealing,grounding and
15.29 GPS Installation Major MNS Telecom
brackets. If applicable
15.30 Synch Cable connections Minor OK NOK N/A Synch cables to be installed as per standards.
15.31 ASC and RET correctly installed as per design Minor OK NOK N/A
MNS Telecom
Access Point Installation, Direction and Height as per design and in reference to target coverage Access Points must be installed based on standard and design, Indoor antenna for indoor coverage
Major OK NOK N/A
15.32 (WIFI) and outdoor for outdoor coverage (unless justification provided by design) MNS Telecom
15.33 Power Injector for Access Points (WIFI) Major OK NOK N/A
Power Injector must be installed in safe location for MACRO Site and outdoor coverage MNS Telecom
15.34 Power Source and Adaptor Installation (WIFI) Major OK NOK N/A Cabling for the power adaptor and power source must be safe and protected MNS Telecom
15.35 AP Profiles and SSID Configuration (remote verification) (WIFI) Major OK NOK N/A
Proper AP Configuration for all AP's based on design with Correct folder and SSID MNS Telecom
Acceptable Latency is 50ms from end user, FTP Test must be same result with the configured BH
FTP Test for the backhaulLatency Test for Backhaul, Speedtest (WIFI) Major OK NOK N/A
Dummy cards/plates are not missing at empty slots/ unused plug in unit positions to provide dust
16.1 Dummy Covers Minor OK NOK N/A MNS Telecom
free and a proper cooling circulation through the electronic equipment.
16.2 the MW system to be tested & found functional with no alarms.all indicating leds are working MNS Telecom
OK NOK N/A The wave guide to be properly fixed by proper support, the two end of wave guides to be properly
16.3 IF Cable/ Wave Guide Fixing Major MNS Telecom
sealed, All connectors must be weatherproof (heatshrink/rubbertape)
Optical fiber cables are dressed sequentially or have no crosses. Optical fiber extra cables are
Optical Cables installation Major OK NOK N/A
16.4 properly mounted & placed. Optical fiber cable connections are secured. MNS Telecom
16.6 Sub-racks and Magazines are correctly fitted and grounded Major OK NOK N/A Check Fixation and grounding. MNS Telecom
16.7 Transmission node ventilation as per product standard Major OK NOK N/A
Check TXM ventilation. MNS Telecom
Page 5 of 8
OK NOK N/A
Power Connections to checked for redudency and Breaker Rating.Fuse Rating in MW Rack DCDB
Transmission Power Connections Major OK NOK N/A
and BLVD Connectivity to be checked.Power should be connected on separate breakers in
16.8 rectifiers based on approved EIR MNS Telecom
16.9 Transmission equipment and cables weather proofing Major OK NOK N/A All the cables and equipmen to be weather proofed.
Dishes must been on correct bearing. This will be indicated of acceptance of RSL. Dishes must be
Antennae (Dishes) Height and Diameteras per cevil design approval Major OK
NOK N/A
positioned so that we will not be blocked. Dishes on roof top sites must have at least 2.2 metres
height, measured from the bottom of the dish, above any adjacent walkway.
16.1 The locking bar(s) provided with larger dishes must be in place and securely fixed. MNS Telecom
All the outdoor cables should have proper clamping and in case Tie raps used then steel tie raps to
16.11 Outdoor Tie raps and clamps Minor OK NOK N/A
MNS Telecom
be used.
Protected, properly clamped and secure. No loops or unnecessary length.
Microwave Indoor/Outdoor cable is correctly installed. Major OK NOK N/A Connectors properly installed and in good condition.Labeling and Weather proofing to be checked
16.12 for connectors properly. MNS Telecom
16.13 Rack / Subrack installation Major OK NOK N/A
Rack / Subrack installation according to Civil layout and access design approval MNS Telecom
16.14 Rack Ground Connections for new installation Major OK NOK N/A Rack and Subrack ground connections MNS Telecom
16.15 Power supply protection circuit breakers values based on EIR Major OK NOK N/A
Check Power supply protection circuit breakers values should be as per standard and load. MNS Telecom
16.16 E1 Tributary and Ethernet labeling Minor OK NOK N/A Check E1 Tributary and Ethernet labeling MNS Telecom
16.18 Antenna(s) polarization Major OK NOK N/A Antenna(s) polarization according to plant doc. MNS Telecom
16.19 ODU(s) and pole / braket mounting as per design Major OK NOK N/A
ODU(s) and pole / braket mounting according to design doc. MNS Telecom
16.2 Warning labels Minor OK NOK N/A Antenna(s) EMF warning labeling presence. MNS Telecom
the outdoor units including RAU & Dish antenna support/assembly (bracket) for both 1.2 & 1.8
Antenna Fixture (1.2 & 1.8 Antenna Must be Supported By Struts) Major OK
NOK N/A
mtr are adjusted at correct azimuth & properly tightened (Antenna height and Polarization must
be as per design)
16.24 MNS Telecom
16.25 SYNC cable connections if applicable Major OK NOK N/A
Check for sync Cable connections properly. MNS Telecom
16.31 Channel Protection Switching test (N+1) – Physical test Major OK NOK N/A MNS Telecom
c.Link test and measurement (Back-end)
16.33 48 hrs link stability test Major OK NOK N/A MNS Telecom
16.34 Frequency checks (Sub band and spot frequency) Major OK NOK N/A
Frequency Pair should be as per Design MNS Telecom
Page 6 of 8
16.38 Link SW License Major OK NOK N/A
MNS Telecom
16.39 Planned link parameters vs Achieved link parameters (Tx pwr, Rx pwr etc). Major OK NOK N/A
Receive Signal Level if exceed (+/-3 db) and all other parameters to be as per design MNS Telecom
16.4 XPD Test to be done & mention the values NE & FE (=/>27) Major OK NOK N/A
MNS Telecom
16.41 Threshold shoud be not less than 30 dbm Major OK NOK N/A MNS Telecom
16.42 Provide BIR ( Backhauling Integration Report) with new site acceptance. Major OK NOK N/A
MNS Telecom
Since most sites are carrying over IP NW, so need to add KPIs of MW performance on IP domain
Major OK NOK N/A
New link should carrying live traffic prior to PAT and it will help to fast detection on vandalism
Major OK NOK N/A
16.59 All new configuration has beem implemented as per design , Removal of all old configuration Major OK
OK NOK
NOK N/A
N/A
MNS Telecom
f. Link Dismantling Exercise:
16.6 Removal of all configurations from link to be dismantled. Major OK NOK N/A MNS Telecom
All equipment and its related connection are removed from the site and no leftovers exist at the
16.61 Major OK NOK N/A
MNS Telecom
site
Disconnection SOR must be applied and implemented to remove all related connections of the
Major OK NOK N/A
Link dismantling exercise does not affect other traffic at the site. Major OK NOK N/A
MNS Telecom
16.64
16.65 Confirmation of dismantling completion. Major OK NOK N/A FATA to be shared with MNS
17. Router
17.1 Cables arrangement Minor OK NOK N/A
Check cable arrangement and cable connectivity with RBS and Transmission. MNS Telecom
17.2 Tie raps installation Minor OK NOK N/A check cable are properly routed and tie rap. MNS Telecom
17.4 Console Access Major OK NOK N/A check console access is working with login. MNS Telecom
Page 7 of 8
18. Safety Engineering
18.1 Steps and ladders Major OK NOK N/A
Monopole and tower ladder steps are missing/broken MNS E&M
Emergency phone numbers must be available at shelter door. Safety instruction plates are
SIGNAGE Minor OK NOK N/A
18.2 provided as per safety rules (Hazard, warning & Safety) MNS E&M
Name:
NRO Contractor (Telecom)
Signature
Name:
Mobily Project Representative(optional)
Signature
Name:
Manage Service Representative (E&M/Civil)
Signature
Signature
Page 8 of 8