Purpose & Definition

In logistical processes it is often necessary to interchange parts. SAP provided interchange


material.

Parts interchangeability compromises the following function :


• Restricted or one-way interchangeable parts
• Material exchange functions
• Supersession

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 4


AGENDA

Purpose

FFF Class

Material Exchange

MRP-MPN Set

Supersession

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 5


FFF Class

Definition
Grouping fully interchangeable parts that have identical technical properties in terms of form, fit, and
function.

Use
FFF class is used as a “link” to group fully interchangeable, inventory-managed manufacturer parts.

Structure
• FFF class is represented in the system by a part with material type FFFC
• Part contains the “header data” of the FFF class
• FFF class is not inventory-managed and cannot be procured
• Material master record has only a Basic Data

FFF Class dengan model


• Fully Interchangeable ( A  B)
• One way restricted ( A  B)

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 6


Fully Interchangeability

Using FFF Class, we can exchange one


parts to another parts along same FFF
Matnr / FFF Class : 4710 Class.
Ex : In this FFFF 4710, Material 4710A,
4710B and 4710C can replaced each other
Fully interchangeable

Matnr 4710A Matnr 4710B Matnr 4710C

FFF Class : 4710 FFF Class : 4710 FFF Class : 4710


MPN Profile : IMPN MPN Profile : IMPN MPN Profile : IMPN

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 7


Fully Interchangeability

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 8


Restricted Interchangeability

Material : 4711

One-way
Restricted Interchangeability allowing us to exchange one
interchangeable
parts to another, but it can’t be reversible
or restricted

Ex : 4711 can be replaced by 4712, but 4712 can’t be


replaced by 4711
Material : 4712

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 9


Restricted Interchangeability

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 10


Supersession Chain

Material : 4711
Supersession Chain allow us to fully replace a discontinue
parts with a other parts starting from certain period.
Replaced By

Ex :
Material : 4712
• Material 4711 replaced by 4712 starting from 01 March
Valid From : 01 March 2020 2020, means 4711 can no longer be used in
transaction since the date.
Replaced By • Another replacement will be occurred from 25 July
2020 for 4713 replacing 4712. On this date, 4711 and
4712 can no longer be used.
Material : 4713
Valid From : 25 July 2020
© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 11
Supersession Chain

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 12


Pre-requisite of FFF Class
Material Master for FFF Group

FFF Class
• Define a material code for the FFF Group
• Material Type : FFFC
• Maintain Material View with Basic Data1
and Basic Data 2
• Mnf Part Profle : IMPN

Notes:
• Use a general code & description for this
FFF Group material since it will not be
used in any transaction (Only for grouping
the materials)
• Please use only FFFC material type as
standard material type for FFF Group
© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 13
Pre-requisite of FFF Class
FFF Group Maintenance

Once FFF Class material has been created,


we can continue to maintain its content in
tcode ‘PIC01’.

• Put FFF Class and click on button “Full


Interchangeability”
• List all material that can replace each
other

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 14


Pre-requisite of FFF Class
Setting for FFF material data checking

We can validate FFF Group material list by comparison of material data.


For example, FFF Group can only consist material with same Material
Group, or same Material Type, and so on.
Please remember, this setting can only be done in configuration level
We can find the setting in SPRO  Logistics General 
Interchangeability of Parts  Determine Common Fields of Parts

By default, no field taken as validation checking criteria. We can turn it on


by Set ‘X’ to the field we want to consider.

We can also add fields to be consider if it hasn’t listed yet in standard.

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 15


AGENDA

Purpose

FFF Class

Material Exchange

MRP-MPN Set

Supersession

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 16


FFF Class in transaction

Purchase Requisition Goods Receipt


• Parts can be exchanged / replaced • Interchange part can be done on Goods Receipt
part rather than changing the initial material of a
RFQ / Quotation purchase order. System will automatically
• Parts can be exchanged / replaced at the update the Purchase order
time of making a Quotation
Goods Issue
• Interchange part can be processed in Goods
Purchase Order
• Parts can be exchanged / replaced using Issue process through Availability Check
process where system will propose the
help on sub-items.
• New sub-items can be created to handle alternative material also.
partial delivery with different part Order (PM / PP Order)
• Good Receipt and Invoice Receipt are • Interchange part can be processed in Order
posted at the sub-item level Processing such as Maintenance Order &
• Sub-items’ price can be referenced from Production Order through Availability Check of
main item or individual info record Component where system will propose the
© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL
alternative material also. 17
Material Exchange
Procurement : RFQ and Quotation

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 18


Material Exchange
Procurement : RFQ and Quotation

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 19


Material Exchange
Procurement : RFQ and Quotation

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 20


Material Exchange
Procurement : RFQ and Quotation

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 21


Material Exchange
Procurement : Material Replacement Sample in Purchase Order

6.1111002A with qty 8 kg line


exchangeable with 6.1111002B
5 Kg, 6.1111002C 3 Kg

Notes: MPN Set Locked material will not be shown for exchange in Purchase Order

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 22


Material Exchange
Procurement : Purchase Order with sub item pricing
Two pricing method for Sub Item:
• ‘Blank’ : each sub item will use
individual info record means that
Each Material with Interchange Purchasing Info Record is required.
have different prices
• ‘A’ : price from main item will be
carried over to all sub items.

Each Material with Interchange


have same prices

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 23


Material Exchange
Procurement : Purchase Order with sub item pricing

The sub item pricing will be determined from vendor master.


First, the Schema Group Vendor in Vendor Purchasing Data
should be maintained under “09”, to enable Price
Determination from Special Pricing Procedure “VPUP01”
(Check in tcode M/08)
Next, maintain sub-item pricing in Interchangeability view

Notes: Once we activated Interchangeability, we better put ‘09’ in


Vendor Schema Group in all vendor. If any interchange parts
purchased from this vendor, system will check the sub-item
© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL
pricing, otherwise, nothing is happened. 24
Material Exchange
Inventory Management : Good Receipt (GR) Purchase Order (PO)

Material exchange tab


appear, if material have
assigned to
interchangeable

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 25


Material Exchange
Inventory Management : Purchase Order changes after Interchangeability

PO will automatically adjusted with new


item according to what receipt has
been done. The price will be
determined by Sub-item pricing

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 26


Material Exchange
Inventory Management : Good Issue (GI) with reservation

Click icon to shown


material exchange material

Material exchange in Goods Issue can be processed through Availability Check features (Next slide)

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 27


Material Exchange
Inventory Management : Good Issue (GI) with reservation

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 28


Material Exchange
Inventory Management : Service Order

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 29


Material Exchange
Inventory Management : Service Order

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 30


Material Exchange
Inventory Management : Stock Material

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 31


AGENDA

Purpose

FFF Class

Material Exchange

MRP-MPN Set

Supersession

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 32


MRP-MPN Set

Definition
• Material Requirement Planning Set (MPN-MRP set) are a subset of the inventory-managed
manufacturer parts in one FFF class and should be treated as fully interchangeable parts in MRP,
inventory management, and the availability check.

• MPN-MRP set has exactly one leading part that represents this MPN-MRP set from the MRP view

Working with MRP Areas


• MPN-MRP without MRP Areas
 Group all parts in FFF class into one MPN-MRP set for each plant

• MPN-MRP with MRP Areas


 Group all parts in FFF class into one MPN-MRP set for each plant and plant MRP area

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 33


MRP with MRP-MPN Set

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 34


MRP with MRP-MPN Set

Material 083.000.012-B
ROP 200
Material 083.000.012-A
Safety Stock : 50
ROP 300
Safety Stock : 100

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 35


MRP with MRP-MPN Set

Material 083.000.012-C
ROP 500
Safety Stock : 300

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 36


MRP with MRP-MPN Set

Material 083.000.012-C, ROP 300,


Safety Stock : 100 but because
material has been set with MRP-
MPN, safety stock : 300 followed
by Material 083.000.012-A with
safety stock : 300

MRP MPN icon,


It will show Safety Stock 083.000.01-C
own,
Planned order :
300 Safety Stock – 140 Stock = 160
© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 37
MRP with MRP-MPN Set

When create MRP for single


material, it only can be execute
with leading material
083.000.012-A

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 38


MRP with MRP-MPN Set
Goods Receipt Validation based on MPN Set

When a specific MPN is set for


plant, system will validate the
Goods Receipt only for listed
material in MPN instead of FFF

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 39


AGENDA

Purpose

FFF Class

Material Exchange

MRP-MPN Set

Supersession

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 40


Supersession

Definition
Supersesion material based validity date

Use
• Stock Shortage
The main material stock has run out while materials with similar characteristics are still available and
can be used as substitutes.

• Obsolete Part
Main material is damaged while there are other materials that can be used as substitutes

• Manufacture exchange
material changes from the vendor

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 41


Supersession
Master Data setting

Supersession, each
material has validity
date

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 42


Supersession in Transaction

Material Requirements Planning (MRP):


• Enhancements di MRP : Possible calculate MRP for all Inventory Management
supersession parts Enhancement di menu Stock Overview
• Calculate PIR (Planned Independent Requirement) Order Processing
supersession parts. Show Supersession Chain in Order Processing
• Enhancement on menu stock/requirements list:
Access the display of all parts in the supersession Purchasing:
chain. Modification of items in PR or PO can be done even
though GR and Invoice has occurred. Even so, parts
Forecasting replacement can only be used for quantity of items in PR
Consumption-based forecasting access to the display of or PO that are still outstanding.
all parts in the supersession chain.

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 43


Transaction Supersession
MRP

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 44


Transaction Supersession
Purchase Order

Material 6.1111002-SSB is
already expired, should be
use material with new
valid date 6.1111002-SSA

© 2020 Wilmar Consultancy Services company. All rights reserved. ǀ INTERNAL 45


PT. Wilmar Consultancy Services
Multivision Tower, 12th Floor
Jl. Kuningan Mulia Kav. 9B Jakarta Selatan - INDONESIA
Phone : +62 21 2938 0290
Fax : +62 21 2938 0289

Wilmar Consultancy Services Pte.Ltd


12 Kilang barat, #05-01, SINGAPORE 159354
Phone : +65 6631 0117

www.wcsglobal.id

You might also like