TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 2
3. DEFINITIONS ............................................................................................................... 2
4. PROCEDURE ............................................................................................................... 2
5. RESPONSIBILTIES ..................................................................................................... 4
6. REFERENCES ............................................................................................................. 5
7. ATTACHMENTS .......................................................................................................... 5
8. APPENDICES .............................................................................................................. 5
9. REVISION HISTORY.................................................................................................... 5
HSE-SAF-PRO-00-0013 Page 1 of 5
HSE-SAF-PRO-00-0013
SAFETY
Rev. 4
06-Sep-2015
SAFETY VARIANCE PROCEDURE
Page 2 of 5
1. INTRODUCTION
It is recognized that all situations cannot be addressed in any one procedure, program or
standard. Therefore, this procedure shall be used for situations where it is required to vary
from the established Q-Chem safe work practices.
The purpose of this procedure is not to circumvent established safe work procedures,
programs or standards but to address case-by-case situations where following the written
procedure is not possible or an equally safe alternative that make more sense for a task.
This procedure applies to all intended safety deviations in the Company to the written
requirements of the Q-Chem Safety department (it includes policies, programs, plans,
procedures, guidelines, manuals and standards).
3. DEFINITIONS
4. PROCEDURE
NOTE
Safety Section representative can be Safety Specialist, Safety &
Emergency Response Specialist, Process Safety & Compliance
Coordinator, Industrial Hygienist or FSC.
iii. The Hazard Analysis team shall conduct a hazards assessment using Hazard Analysis for
Safety Variance Permit (HSE-SAF-SFM-00-0120) and attach it to the Safety Variance
Permit.
iv. The team shall document the necessary safe guards and/or compensating measures on
the Safety Variance Permit.
HSE-SAF-PRO-00-0013 Page 2 of 5
HSE-SAF-PRO-00-0013
SAFETY
Rev. 4
06-Sep-2015
SAFETY VARIANCE PROCEDURE
Page 3 of 5
v. The Originator, seeking approval, shall prepare a completed variance package with all
applicable documents for review.
The package shall include the following documents as minimum:
a) Safety Variance Permit
b) Hazard Analysis for Safety Variance
vi. Based on the type of variance the following additional document(s) may be considered as
attachment. e.g.:
a) Job Safety Analysis
b) Marked Up P&ID
c) Rescue Plan
d) Pre Plan (for fire Prevention/Control)
e) Copy of previous Safety Variance Permit for the same task done in past
f) Operational Isolation/Action Plan
vii. The Originator shall present the Safety Variance Permit along with all applicable
documents to the Managers/Superintendents and obtain final approval from the following:
a) Originator Area Superintendent
b) Originator Department Manager
c) Affected Area Manager (if the variance is required for an area outside of Originator
Department Area other than Technical/Maintenance Manager/Superintendent
(RLOC)
d) Technical Manager/Superintendent (RLOC)
e) Maintenance Manager/Superintendent (RLOC)
f) Safety Manager/HSE Superintendent (RLOC)
g) Operations Manager/Plant Manager (RLOC)
viii. Extension of Safety Variance Permit: Plan the task in such a way to complete the task
during validity of Safety Variance Permit. In extreme case, Safety Variance Permit validity
may be extended. To extend the validity of the Safety Variance Permit, the Originator shall
obtain the original Safety Variance Permit from the HSE Administrative Assistant, fill the
date and time in Section H of the Safety Variance Permit and get the approval for
extension from following:
a) Originator Area/Department Manager/Superintendent (RLOC)
b) Safety Manager/HSE Superintendent (RLOC)
The Originator shall make copies of the extended approved Safety Variance Permit and
deliver the original documents to the HSE Administrative Assistant.
i. All parties involved in executing the work covered by the Safety Variance Permit shall be
briefed on the details of the variance and agreed safeguards, Hazard Analysis for Safety
Variance and other applicable documents.
HSE-SAF-PRO-00-0013 Page 3 of 5
HSE-SAF-PRO-00-0013
SAFETY
Rev. 4
06-Sep-2015
SAFETY VARIANCE PROCEDURE
Page 4 of 5
i. The Originator shall make copies of the approved Safety Variance Permit along with all
applicable documents and deliver the original documents to the HSE Administrative
Assistant.
ii. HSE Administrative Assistant shall provide the number to the Safety Variance Permit and
upload a scanned copy of Safety Variance Permit along with all applicable documents on
Safety Web Page.
iii. Approved Safety Variance Permits shall be maintained for the life of the Plant.
4.4. Follow up
5. RESPONSIBILTIES
i. Maintain all approved Safety Variance Permits for the life of the Plant.
ii. Provide number to all the Approved Safety Variance and upload onto Safety Web Page.
iii. If the Safety Variance Permit (Section G) prompts a change to the safety documents,
same to be added into Safety Manual Feedback for further follow up.
iv. Review/update this procedure as per the ‘Document Revision, Update and Tracking
procedure’ (QC-IMT-PRO-00-0001) or whenever a revision/change is recommended.
HSE-SAF-PRO-00-0013 Page 4 of 5
HSE-SAF-PRO-00-0013
SAFETY
Rev. 4
06-Sep-2015
SAFETY VARIANCE PROCEDURE
Page 5 of 5
6. REFERENCES
None
7. ATTACHMENTS
8. APPENDICES
None
9. REVISION HISTORY
HSE-SAF-PRO-00-0013 Page 5 of 5