Professional Documents
Culture Documents
SWP-01 Permit To Work System
SWP-01 Permit To Work System
SWP-01 Permit To Work System
2. SCOPE
2.1 This Operational Control Procedure is applicable to permit to work system for
activities such as work at height and lifting operation
3. RESPONSIBILITY
3.2 Supervisor shall ensure all activities required permit to work procedure is
complied when they performing activities like working at height, hot work and
other high risk activities on site.
3.3 The applicant who is the supervisor is responsible to apply the permit and
furnish all necessary information as specified in the permit.
3.4 The supervisor must ensure all workers performed the activities had
undergone appropriate training before deploying them to perform the
activities.
3.5 The supervisor shall ensure he reads and fully understands the statement stated
on the permit to work and supporting certificates and checklists.
3.6 The supervisor shall explain the risk assessment to all the workers during the
toolbox briefing. He shall be responsible for ensuring that all safety measures
are observed and procedures are followed.
3.7 The supervisor shall hold a copy of the permit to work and attachments at all
times. He shall ensure that they are available or displayed at the work area at
all times.
3.8 The following is the list of permit to work applicable to YORKOOL PTE LTD
• Working at Heights;
• Hot-Works;
• Lifting Operations;
• Other related works that require a PTW system implementation in the
workplace
Page 1 of 7
YORKOOL PTE LTD
SWP-01 PERMIT TO WORK SYSTEM
4. PROCEDURE
Stage 1: Application
• The supervisor (Applicant) shall apply for the permit by filling in all copies of
the permit for the high risk work job required.
• He must fill up the particulars correctly and legibly in the appropriate boxes
including the vessel's name, location, commencement and completion date and
time, type of high risk work and whether it is carried out in confined space.
• He must ensure supply of sufficient forced ventilation (seek safety officer
advice when necessary) and lightings and appropriate hot work tools used.
• A sketch of the location of the high risk work must be provided.
• The Safety Assessor, upon receipt of the application, evaluates the information
given by the Supervisor.
• The Safety Assessor must be familiar with the high risk work schedule.
• He shall inspect the area jointly with the supervisor and make assessment of
area and its surrounding.
• He shall also inspect to ensure all safety requirements have been compiled.
• If the work is perform inside confined space, he must ensure check and ensure
confined space is safe to perform the high risk work.
• If the ventilation is inadequate, he shall advise the Supervisor on the
appropriate safety measures
• If he is satisfied with the joint inspection result, he will then endorse the
application by signing at the Stage 2 of the application and hand the permit to
Project Manager for approval.
Page 2 of 7
YORKOOL PTE LTD
SWP-01 PERMIT TO WORK SYSTEM
Stage 3: Approval by Project Manager
• The Supervisor shall clearly post a copy of the permit-to-work and ensure the
copy is not removed until the date of expiry or date of revocation of the
permit-to-work on completion of high risk work.
Stage 5: Monitoring
Page 3 of 7
YORKOOL PTE LTD
SWP-01 PERMIT TO WORK SYSTEM
• If the job is not completed within the stipulated time, a fresh permit will have
to be raised and previous permit must be handed over to the Project Manager.
5. Validity of permit
5.1 The validity of the permit will base on the permit policy of the main
contractor/ owner of the project
5.2 The permit shall be valid base on the maximum allowable period stated on the
permit and is subject to daily review by Project manager.
5.3 If the job is not completed within the stipulated time, a fresh permit will have
to be raised.
5.4 The Project Manager must review and assess the need to continue high risk
work on a daily basis and may revoke the permit if he thinks fit to do so. For
the continued validity of the permit, the Project manager will sign on the
permit.
Page 4 of 7
YORKOOL PTE LTD
SWP-01 PERMIT TO WORK SYSTEM
5.5 If condition of the workplace changes, supervisor/ foreman of YORKOOL
PTE LTD must stop the job and notify the Project manager or safety assessor
of site immediately.
Page 5 of 7
YORKOOL PTE LTD
SWP-01 PERMIT TO WORK SYSTEM
6. ATTACHMENT
STAGE 1 (Application)
Application of permit by Supervisor (Responsible Person)
STAGE 5 (Monitoring)
Supervisor ensures safety measures are in place all the times
PM continually review progress of work
STAGE 6 (Completion)
Supervisor inform Project Manager of completion of Work
Page 6 of 7
YORKOOL PTE LTD
SWP-01 PERMIT TO WORK SYSTEM
Page 7 of 7