CONSTRAINTS

‐ We click on the status tab in the activity details at the bottom of the screen.

CONSTRAINTS TYPES
 Start On imposes the specific start date you choose. The Start On
constraint can delay an activity's early start or move forward an
activity's late start to satisfy the constraint date.

 Start On or before defines the latest date an activity can start. This
constraint only affects late dates and may decrease total float. When
calculating a schedule, P6 Web Access imposes the start on or before
constraint in the backward pass only if the calculated late start date
will be later than the imposed date.

 Start On or after defines the earliest date an activity can begin.


This constraint affects only early dates. When calculating a schedule,
P6 Web Access imposes the start on or after constraint in the forward
pass only if the calculated early start date will be earlier than the
imposed date.
48 | P a g e
Eng. Hussien Mostafa Ahmed