FIDIC CLAIM SERIES #01

FIDIC YELLOW
BOOK 2017:
CONTRACTOR
CLAIM EVENT
SCENARIOS

parithi
Ilam
01 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 1.9: ERROR IN


EMPLOYER’S SPECIFICATION

Cause of Claim: Error in Employer’s


specification not discovered before
Contract Award.
Contractor Entitlement:
Extension of Time (EOT): YES
Cost: YES
Profit: YES

parithi
Ilam
02 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 1.13: DELAY IN


WORK PERMIT

Cause of Claim: Delay in Work


permit by Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
03 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 2.1: DELAY IN


ACCESS TO SITE

Cause of Claim: Delay in Access to site


by Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
04 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 4.6:
UNFORESEEABLE
ADDITIONAL COOPERATION

Cause of Claim: Instruction for


unforeseeable additional cooperation
with other agencies of Employer or
Government.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
05 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 4.7: ERROR IN


SETTING-OUT DATA

Cause of Claim: Error in setting-out data.


Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
06 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 4.12:
UNFORESEEABLE PHYSICAL
CONDITIONS

Cause of Claim: Unforeseeable physical


conditions at Site.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO

parithi
Ilam
07 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 4.15: CHANGES TO


ACCESS ROUTE

Cause of Claim: Changes to an access


route.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO

parithi
Ilam
08 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 4.23: DISCOVERY OF


FOSSILS ETC.

Cause of Claim: Discovery of fossils etc.


Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO

parithi
Ilam
09 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 7.4: DELAY IN


TESTS/INSPECTION

Cause of Claim: Delay in tests/inspection


due to Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
10 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 7.6: REMEDIAL


WORK PRIOR TO TAKING-
OVER

Cause of Claim: Remedial work prior to


Taking-Over due to Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
11 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 8.5: EXCEPTIONAL


CLIMATIC
CONDITIONS/FORCE
MAJEURE

Cause of Claim: Exceptional climatic


conditions/Force Majeure.
Contractor Entitlement:
EOT: YES
Cost: NO
Profit: NO

parithi
Ilam
12 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS

CLAUSE 8.10: SUSPENSION


BY EMPLOYER

Cause of Claim: Suspension by Employer


unless Contractor default.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
13

CLAUSE 10.2: DELAY IN


EMPLOYER TAKING-OVER A
PART

Cause of Claim: Delay in Employer


Taking-Over a Part.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
14

CLAUSE 10.3: DELAY OR


DISRUPTION WITH TESTS
ON COMPLETION

Cause of Claim: Delay or Disruption with


Tests on Completion.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
15

CLAUSE 11.7: DELAYED


ACCESS AFTER TAKING-
OVER

Cause of Claim: Delayed access after


Taking-Over.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
16

CLAUSE 11.8: SEARCH FOR


DEFECTS NOT ITS FAULT

Cause of Claim: Search for defects not its


fault.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: YES

parithi
Ilam
17

CLAUSE 13.3.2:
CONTRACTOR REQUIRED TO
SUBMIT VARIATION

Cause of Claim: Contractor required to


submit proposal for Variation which is
not accepted.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: NO

parithi
Ilam
18

CLAUSE 13.6: CHANGE IN


LAWS/PERMITS AFTER
CONTRACT AWARD

Cause of Claim: Change in Laws/Permits


after Contract Award.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO

parithi
Ilam
19

CLAUSE 16.1: SUSPENSION


DUE TO PAYMENT DEFAULT

Cause of Claim: Suspension due to


Payment Default by employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
20

CLAUSE 16.1: SUSPENSION


DUE TO PAYMENT DEFAULT

Cause of Claim: Suspension due to


Payment Default by employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
21

CLAUSE 16.2.2: RIGHT TO


TERMINATE BY EMPLOYER

Cause of Claim: Right to Terminate by


Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
22

CLAUSE 16.3: WORK


INSTRUCTED AFTER
TERMINATION

Cause of Claim: Work instructed after


termination.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: YES

parithi
Ilam
23

CLAUSE 16.4: TERMINATION


ON EMPLOYER DEFAULT

Cause of Claim: Termination on


Employer default.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: YES

parithi
Ilam
24

CLAUSE 17.2:
RECTIFICATION
LOSS/DAMAGE DUE TO
FORCE MAJEURE

Cause of Claim: Rectification


loss/damage to executed works due to
Force Majeure, the Employer, or other
contractors.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES

parithi
Ilam
25

CLAUSE 18.4: EXCEPTIONAL


EVENT

Cause of Claim: Exceptional Event.


Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO

parithi
Ilam
Was this Tip
helpful to you?
Like | Comment | Share | Follow

FOLLOW ME FOR MORE

Ilamparithi BoologaSundaraVijayan

Disclaimer: The information provided in this presentation serves as educational content and does not constitute legal

hi
advice. While efforts have been made to ensure accuracy, no warranty is provided regarding reliability or

rit
applicability. Viewers are advised to seek independent legal counsel for specific situations. The presenter and

pa
platform bear no liability for decisions made based on this information. Contractual terms may vary, and users should

lam
refer directly to their contracts for guidance. By accessing this presentation, viewers acknowledge these terms.