Lifting Procedure Girder of Boiler (New)
Lifting Procedure Girder of Boiler (New)
1 of 17
- SDCC : Original
- CNEEC : Copy
- Originator: Copy
ISSUED EFFECTIVE
REV. NO BRIEF OF REVISION
DATE DATE
0 16-01- 2009 17 -01- 2009 ISSUED FOR APPROVAL
TABLE OF CONTENT
1 Title 1 of 17
2 Scope 3 of 17
3 Objective 3 of 17
4 Reference 3 of 17
5 Description Procedure 4 of 17
5.3 Execution 4 of 17
5.3.1 Preparation 4 of 17
6 Attachment
DOCUMENT NO. :
LIFTING PROCEDURE OF MAIN GIRDER STEEL P-T3109-RED-006
STRUCTURE ISSUED DATE :
16 JANUARY 2009
1. TITLE
2. SCOPE
This procedure describes the guidelines and operation step for lifting Main Girder
of Boiler #2 steel structure by using Crawler Crane Kobelco SL6000 Cap. 600
Tons. Transportation of the main girders from Tanjung periok port to erection
area conducted by other company.
Installation of the three main girders: will be directly placed on the support
structure at top of the right and left columns with the sequences as follow: K4
K3 K2. After installed, the main girders will be filled with connection
beam.
3. OBJECTIVE
As a guidance for engineers and supervisiors or related person for providing
and following erection method of main girder safely K2, K3 and K4.
DOCUMENT NO. :
LIFTING PROCEDURE OF MAIN GIRDER STEEL P-T3109-RED-006
STRUCTURE ISSUED DATE :
16 JANUARY 2009
4. REFERENCE
1. P - HSE – 001 – Management and implementation of HSEMS.
2. W – HSE – 001 – Project HSE Management System Plan.
3. W – SAF – 026 Crane & Lifting Procedure.
4. Handbook of Rigging by W.E Rossnagel, P.E (Third Edition).
5. General Catalog, The Crosby group, Inc. (2002 Catalog Browser ).
6. Drawing, No : CG13121-2-0 ( Steel Structure )
7. Drawing, No : G13123-0 (Main Girder)
5. DESCRIPTION PROCEDURE
1. Check ground condition for parking crane Kobelco SL6000 such as level and
compaction with minimum ground pressure 14 ton/m2.
2. Check crane condition before mobilize to lifting area.
3. Check rigging tools & accessories condition such as slings, shackles & etc.
4. No activity to be allowed in and around lifting area during lifting activity.
Install barricade tape to secure the lifting area.
DOCUMENT NO. :
LIFTING PROCEDURE OF MAIN GIRDER STEEL P-T3109-RED-006
STRUCTURE ISSUED DATE :
16 JANUARY 2009
5. Signalman, Operator & Supervisor should have proper radio/ visual contacts
at all time.
6. Workmen wear proper PPE ( Helmet, safety shoes, full body hardness/
Safety belt, etc) and lanyard hook of body harness always hooked up while
working at height (For detail, Please see Attachment for HSE Aspects
Identification, Risk Assessment and Risk Control ).
7. Perform house keeping after job completion.
5.3 EXECUTION
5.3.1 PREPARATION
1. Conduct load test before the crane used to ensure the crane condition
is good.
2. Check the crane crawler position to ensure they are in the same level.
3. Conduct good Backfill, compaction and leveling of area to ensure soil
bearing capacity as per requirement minimum 14 ton/m 2(Please, see
the attachment).
4. Barricade erections area to prevent unauthorized personnel entry to
the Lifting area.
5. Conduct final Rigging orientation by operator, riggers, and safety
personnel.
6. Crane positioning at lifting area and make sure the crane lifting radius
is conform with rigging calculation.
7. Check all rigging equipments such as shackles and wire sling ensure
is good .
8. Check the scaffold of Main girder erection for support the activity.
9. Check communication apparatus, to ensure good communication
during Lifting.
10. When lifting the girder, some specified persons must be located at
the area to monitor the girder position and ensure it will not hit the
other steel structure.
7. Use chain block to prevent the girder unstable, and release rigging
tools(sling and shackle)
8. After installed, the main girders will be filled with connection beam.
Note : Crane operator must follow orders from the authorized signalman
to avoid miscommunication.
6. ATTACHMENT