Extension of Time (EOT) Terms and Definitions PDF
Extension of Time (EOT) Terms and Definitions PDF
Extension of Time (EOT) Terms and Definitions PDF
1. Act of God
A natural occurrence caused directly and exclusively by natural forces without any
human interference, which could not have been reasonably foreseen or prevented
by the contractor or any other party to the contract.
2. Adjusted As-Built
A traditional schedule impact analysis technique that uses a one-time, after-the-fact
insertion of the owner and excusable delays into the as-built schedule to quantify
the global impact.
3. Adjusted As-Planned
A traditional schedule impact analysis technique in which delays are included in the
original CPM without regard to actual progress or historical work activity data, to
quantify global impact.
4. As-Built Schedule
An accurate historical representation of the actual sequence of construction and
how it was completed.
5. Baseline (As-Planned) Schedule
The target construction schedule is based on the contractor’s original understanding
of the project and used as the standard by which progress is measured.
6. Cardinal Change
A change (either directed or constructive) to the contract that, because of the size or
the nature of the changed work, is clearly beyond the general scope of the contract.
7. Change
When a contractor takes on any type of work that deviates from the original
contract, or from the scope of work or plan of action reasonably anticipated under
the contract.
8. Collapsed As-Built (But-for)
A schedule impact analysis technique that assigns responsibility for each party by
removing all sources of each delay (owner, excusable, contractor) to quantify the
global impact.
9. Concurrent Delays
Independent sources of delay that occur at the same time and/or on separate
parallel paths of a CPM network.
10. Constructive Change
A change that is not acknowledged by the owner as such when it occurs, but which
nonetheless is a change.
This is our EOT Course that will strengthen your knowledge of the EOT Claim and definitions.
You may also check the 4 Successful Steps for Getting your EOT Claim article.
Article Link: https://planningengineer.net/extension-of-time-eot-terms-and-definitions/
---------------
Useful links:
Join our email Newsletter, we send useful free content regularly:
https://planningengineer.net/newsletter/
Our Services https://planningengineer.net/our-services/
Our Courses: https://planningengineer.net/lp-courses/
Support Forums: https://planningengineer.net/forums/
Free Arabic Basic Course Playlist:
https://youtube.com/playlist?list=PL7qHhNmknL6F5IOHAsNnPVMt1X-fvYe3J
---------------
Keep in Touch:
WhatsApp: +201277767728
Email: Info@PlanningEngineer.Net
English YouTube Channel: https://www.youtube.com/c/PlanningengineerNet/videos
Arabic YouTube Channel: https://www.youtube.com/@planningengineer3906
Linked in: https://www.linkedin.com/company/planning-engineer-est/
Facebook Page: https://www.facebook.com/PlanningEngineerDotNet
Facebook Group: https://www.facebook.com/groups/1138400132963230
Twitter: https://twitter.com/PlanningEEst
Instagram: https://www.instagram.com/planningengineerest/
TikTok: https://www.tiktok.com/@planningengineerest
---------------