ADEC GATEWAY BUILDING

BAKU, AZERBAIJAN

PROJECT: RD 5088986

Contractor: Document Title:

METHOD STATEMENT FOR ERECTION OF


INDEPENDENT AND HANGING SCAFFOLD
Document No: Revision
00
BABIN – MS – 25
GATEWAY BUILDING BAKU,AZERBAIJAN

METHOD STATEMENT FOR ERECTION OF INDEPENDENT AND Page


HANGING SCAFFOLD 2 of 6
Date: 18.02.2014 Rev.00 No. BABIN-MS-25

REV. DESCRIPTION PREPARED BY CHECKED BY APPROVED BY DATE OF


APPROVAL

Issued for Review by


00 TY BG
Owner

Issued for Review by


01 TY BG
Owner

Issued for Review by


02 TY BG
Owner

BG : Bora GİRİTLİOĞLU(Project Manager)


EU: Erim UYSAL (Construction Manager)
TY: Tahir YILDIZ (Architect)
RA :RufatAliyev(QA/QC Engineer)

BABIN-FOR-01 REV.00 DATE:16.11.2011


GATEWAY BUILDING BAKU,AZERBAIJAN

METHOD STATEMENT FOR ERECTION OF INDEPENDENT AND Page


HANGING SCAFFOLD 3 of 6
Date: 18.02.2014 Rev.00 No. BABIN-MS-25

CONTENTS

1. SCOPE

2. PURPOSE

3. DEFINITIONS/ABBREVIATIONS

4. RESPONSIBILITIES

5. PROCEDURE

6. ATTACHMENTS

BABIN-FOR-01 REV.00 DATE:16.11.2011


GATEWAY BUILDING BAKU,AZERBAIJAN

METHOD STATEMENT FOR ERECTION OF INDEPENDENT AND Page


HANGING SCAFFOLD 4 of 6
Date: 18.02.2014 Rev.00 No. BABIN-MS-25

1. SCOPE

The purpose of this Method Statement is to define the specific tasks to be


performed by the SUBCONTRACTOR for erection of hanging scaffold in Gateway
Project.

2. PURPOSE

The scope of this Method Statement is to provide a detailed description for for
erection of hanging scaffold in Gateway Project and to ensure that the work is
performed in a safe, professional and controlled manner by competent trained staff.

3. DEFİNITIONS / ABBREVIATIONS

The following definitions/abbreviations are applicable:

 COMPANY ISTANBUL CARSI

 SUBCONTRACTOR NATIK AHADOV.

 TRA Task Risk Assessment.

 IFC Issued for Construction.

 HSE Health, Safety and Environment.

 PPE Personal Protection Equipment.

 PTW Permit to Work.

4. RESPONSIBILITIES

 Subcontractor’s Engineer is responsible for preparation of the method statement


and Subcontractor’s Superintendent to review/approve the method statement
and ensures the work is carried out in a safe manner.

BABIN-FOR-01 REV.00 DATE:16.11.2011


GATEWAY BUILDING BAKU,AZERBAIJAN

METHOD STATEMENT FOR ERECTION OF INDEPENDENT AND Page


HANGING SCAFFOLD 5 of 6
Date: 18.02.2014 Rev.00 No. BABIN-MS-25

 The Superintendent shall ensure that his Supervisor conducts daily toolbox talks
with his crew.

5. PROCEDURE

 Personnel involved in operation

Erection of hanging scaffold in Gateway Project will be carried out bypersonnel

Personnel

- Supervisor – 1
- Scaffolder – 5
- Helper – 1

 Procedure for erection of hanging scaffold in Gateway Project

Activity Procedure

3.1 Risk assessment, Permit to work to be in place and tool-box talk to be conducted
3.2 Working area to be secured and marked by safety tape for operation, sufficient
lighting to be made available if required
3.3 All non-relevant personnel to be restricted from entering working area. Area to be
carefully inspected
3.4 All equipments to be inspected and visually examined prior starting the work
3.5 Setting up work site
3.6 Crane to lift scaffold materials
3.7 Preparation for hooking up
3.8 Independent scaffold will be erected for access and strengthening
3.9 Erection of hanging scaffold – working at height
3.10 Scaffolding will be attached and fixed to the exiting stiffening beam
3.11 Housekeeping and removal of scrap materials will be progressive throughout the
job
BABIN-FOR-01 REV.00 DATE:16.11.2011
GATEWAY BUILDING BAKU,AZERBAIJAN

METHOD STATEMENT FOR ERECTION OF INDEPENDENT AND Page


HANGING SCAFFOLD 6 of 6
Date: 18.02.2014 Rev.00 No. BABIN-MS-25

 Precaution Notes

1. Contractor is to ensure full compliance with the HSE Procedures,

2. A full Risk Assessment for all works associated with erection of hanging scaffold
to be attached to this method statement.

3. Client and Contractor should ensure that the area around the work is clear of
unauthorized personnel.

6. ATTACHMENTS.

 TRA

BABIN-FOR-01 REV.00 DATE:16.11.2011