25-Babin-Ms-0025 Erection of Hanging Scaffold On Gateway
25-Babin-Ms-0025 Erection of Hanging Scaffold On Gateway
BAKU, AZERBAIJAN
PROJECT: RD 5088986
CONTENTS
1. SCOPE
2. PURPOSE
3. DEFINITIONS/ABBREVIATIONS
4. RESPONSIBILITIES
5. PROCEDURE
6. ATTACHMENTS
1. SCOPE
2. PURPOSE
The scope of this Method Statement is to provide a detailed description for for
erection of hanging scaffold in Gateway Project and to ensure that the work is
performed in a safe, professional and controlled manner by competent trained staff.
3. DEFİNITIONS / ABBREVIATIONS
4. RESPONSIBILITIES
The Superintendent shall ensure that his Supervisor conducts daily toolbox talks
with his crew.
5. PROCEDURE
Personnel
- Supervisor – 1
- Scaffolder – 5
- Helper – 1
Activity Procedure
3.1 Risk assessment, Permit to work to be in place and tool-box talk to be conducted
3.2 Working area to be secured and marked by safety tape for operation, sufficient
lighting to be made available if required
3.3 All non-relevant personnel to be restricted from entering working area. Area to be
carefully inspected
3.4 All equipments to be inspected and visually examined prior starting the work
3.5 Setting up work site
3.6 Crane to lift scaffold materials
3.7 Preparation for hooking up
3.8 Independent scaffold will be erected for access and strengthening
3.9 Erection of hanging scaffold – working at height
3.10 Scaffolding will be attached and fixed to the exiting stiffening beam
3.11 Housekeeping and removal of scrap materials will be progressive throughout the
job
BABIN-FOR-01 REV.00 DATE:16.11.2011
GATEWAY BUILDING BAKU,AZERBAIJAN
Precaution Notes
2. A full Risk Assessment for all works associated with erection of hanging scaffold
to be attached to this method statement.
3. Client and Contractor should ensure that the area around the work is clear of
unauthorized personnel.
6. ATTACHMENTS.
TRA