PROJECT PORTFOLIO
22 mn sqft under
construction
(32 projects)
32 mn sqft in PCP
(30 projects)
21 mn sqft in TDD
(16 projects)
With a launch every quarter, we are looking to add to the portfolio substantially
5
SCENARIO 2020 – UNDER CONSTRUCTION
FY20
• 55 mn sqft
FY19
• 39 mn sqft
FY18
• 24 mn sqft
Current
• 22 mn sft
CAGR – 39%
Assumption : Construction for projects in PCP shall start in FY19 and for those in TDD will start in FY20
6
OUR EXPERIENCE - HANDED OVER PROJECTS
Handover date as Delay
Project Phase PIL date
per agreement in months
Phase 1 Mar-14 Oct-14 7
Frontier
Phase 2 Mar-14 Mar-16 24
Phase 1 Dec-16 Jun-17 6
Summit
Phase 2 Mar-17 Jun-17 3
Phase 1 Jun-12 Dec-12 6
Prakriti Phase 2 (3 towers) Dec-13 Sep-15 21
Phase 2 (2 towers) Dec-13 Oct-15 22
Platinum – Kolkata Phase 1 Mar-16 Mar-16 0
Serenity Phase 1 Dec-16 Jan-17 1
Phase 1 Jun-15 Aug-15 2
Horizon Phase 2 Oct-15 Dec-15 2
Phase 3 A2 wing Dec-16 Apr-17 4
Anandam Phase 1 Mar-15 Sep-15 6
Phase 5A Jun-16 Oct-16 4
GGC
AHS 1 Sep-16 Feb-17 5
E-city Phase 2 Jul-16 Jan-17 6
Palm Grove Phase 1 Sep-15 Mar-16 6 7
TIME DELAY IN CURRENT PORTFOLIO
OC application date
Delay
Project
At time of award Currently projected (months)
9
TOP 10 REASONS FOR PROJECT DELAY
1 2 3 Deficient planning,
Difficulties in obtaining
Shortage of skilled activity, material, labour
licenses and permits
labourers and equipment
from authorities
management
4 5 Delays in preparation of
technical documentation
Low productivity by project designers
while construction is in
progress
Source – Mohmad Wahdan, Mostafa Abu Yousef, Ahmed Farid, “Study and Assessment of the Reasons for Project Delay or Stalled from Project Management View” 10
TOP 10 REASONS FOR PROJECT DELAY
6 7 8
Inadequate details and Frequent change orders Deficient coordination
inadequate design during construction among participants
Source – Mohmad Wahdan, Mostafa Abu Yousef, Ahmed Farid, “Study and Assessment of the Reasons for Project Delay or Stalled from Project Management View” 11
IMPACT OF DELAY
12
81 CR COST OF DELAY FOR ONGOING PROJECTS
OC application date Cost of delay
Delay COD
Project At time of Currently per day
(days) Rs Crs
award projected Rs crs / month
35.00 2.5% Central (Rehab) Apr-17 Dec-17 261 1.57 15.45
31.22
Prime (Rehab) Jan-19 Jul-19 185 1.76 10.88
30.00
2.0% 2.0% Sky Oct-21 Jul-22 284 0.52 4.90
14.00
Aria Oct-18 Oct-18 1.76
15.00 13.52
1.0%
101 Sep-19 Sep-19 1.15
10.00 0.7% GGC Ph 5 & AHS Mar-17 Aug-17 160 0.92 4.90
0.5% Prana Aug-18 May-19 262 1.02 8.93
5.00
1.950.2% 0.3% Infinity Jun-19 Sep-19 95 1.57 4.97
1.04
0.00 0.0%
Prakriti Varies Varies 270 1.56 14.00
Mumbai Vikhroli NCR West East South
Azure Ph 1 Mar-18 Apr-18 31 0.22 0.23
COD Percentage of development budget
Eternity Jan-19 Feb-19 30 0.81 0.81
Total COD for live projects 80.54
~1.09% of the development cost 13
PRANA
TIMELINES COST OF DELAY
OC application date Cost per
Expense head
Building At time of Currently month
Delay
award projected Preliminaries 0.01
Building A 15-Oct-17 19-Jun-18 247 PMC 0.08
Building B 4-Dec-17 24-Aug-18 263 Overheads 0.47
Building C 4-Dec-17 31-Aug-18 270 Interest 0.39
Building D 28-Mar-18 15-Nov-18 232 Housekeeping and maintenance 0.01
Building E 28-Mar-18 28-Nov-18 245 Escalation 0.06
Building F 22-Aug-18 16-May-19 267 Customer compensation 0.00
Building G 27-Aug-18 6-Oct-18 40
Net Delay (days) 262 Total cost per month (Rs Crs) 1.02
Cost of delay per day (Rs Crs) 0.03
14
PRIME (REHAB)
TIMELINES COST OF DELAY
OC application date Cost per
Expense head
Building At time of Currently month
Delay
award projected Preliminaries 0.01
T1
Sales 10-Jan-19
15-Apr-20 29-Jun-19
3-Oct-20 247
170 PMC 0.07
T2
Rehab 8-Nov-18
10-Apr-19 9-Jul-19
14-Aug-19 263
243 Overheads 0.17
T3
Net Delay (days) 12-Apr-18 6-Jul-19 450
262 Rent 0.93
T4 7-Oct-18 14-Jul-19 280 Housekeeping and maintenance 0.00
T5 28-Jul-18 15-May-19 291 Escalation 0.08
T6 8-Jul-18 8-May-19 304 LUC 0.50
T7 19-Jul-18 10-Jan-19 175
T8 20-Mar-18 17-Jan-19 303 Total cost per month (Rs Crs) 1.76
Net Delay (days) 185 Cost of delay per day (Rs Crs) 0.06
16
SECTOR 88A
TIMELINES COST OF DELAY
OC application date Cost per
Expense head
Building At time of Currently month
Delay
award projected Preliminaries 0.00
Tower 1, 3B, 3C Jul-18 Jul-18 0 PMC 0.17
Tower 2, 3A Jul-18 Aug-18 31 Overheads 0.09
Tower 6,7 Dec-18 Mar-19 90 Interest 0.90
Tower 8,9 Dec-18 Mar-19 90 Escalation 0.04
Tower 10 Mar-19 Sep-19 183 Customer compensation 0.01
Net Delay (days) 183
Total cost per month (Rs Crs) 1.21
Cost of delay per day (Rs Crs) 0.04
17
AZURE PHASE 1
TIMELINES COST OF DELAY
OC application date Cost per
Expense head
Building At time of Currently month
Delay
award projected Preliminaries 0.00
Jade Mar-18 Apr-18 30 PMC 0.07
Emerald Mar-18 Apr-18 30 Overheads 0.10
Pearl Mar-18 Apr-18 30 Interest 0.00
Net Delay (days) 30 Housekeeping and maintenance 0.00
Escalation 0.04
18
MANPOWER
19
CURRENT STATUS ACROSS ALL PROJECTS (FOR JUNE)
Available Labour Shortfall Shortfall
1400 100%
90% 90%
1200
80%
SHORTFALL
Shortfall Average
Cumulative Deficit in COC spends is 21%
54% 52%
47% 46%
41% 41% 43%
39%
33% 32% 32%
25% 26%
SHORTFALL
Shortfall Average Cumulative Deficit in COC spends is 19%
MA Y- 1 6 JUN-16 JUL-16 AUG-16 SEP-16 OCT-16 NOV-16 DEC-16 JAN-17 FEB-17 MA R - 1 7 APR-17 MA Y- 1 7 JUN-17
22
SUMMIT – PLANNED VS AVAILABLE
Available Shortfall
4500
4000
3500
3000 2006
2500 1244
2000
321 579 820 555
1500 482 341 372 619 676
1000 1933 127
1682 1860 1543
1406 1452 1434 1258 1282
500 1023 1068 1063
0
Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17
SHORTFALL
Cumulative Deficit in COC spends is 34%
Shortfall Average
51% 49%
43% 40%
38%
28% 32%
24% 26% 23%
18%
7% 7%
JUL -1 6 A UG -1 6 S E P -1 6 OCT-1 6 NOV-1 6 DE C-1 6 JA N-1 7 FE B -1 7 MA R-1 7 A P R-1 7 MAY-1 7 JUN-1 7
23
CUSTOMER CENTRICITY
24
SNAGGING / QUALITY ISSUES
• 88% of defects are related to Civil Work
88%
Undulations in walls and ceiling
26
LET’S HEAR THEM
DESIGN S&M CC
27
TECHNOLOGIES CURRENTLY AVAILABLE
28
LIST OF TECHNOLOGIES
30
TUNNEL FORMWORK