Professional Documents
Culture Documents
MST Compressed Air Piping
MST Compressed Air Piping
MST Compressed Air Piping
Package 2 – Line 3
M-ANM-3A1DPW-CM00-MST-000001-Rev A
06 April 2017
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page ii
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page iii
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page iv
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
CONTENTS
1. PURPOSE......................................................................................................................... 1
2. SCOPE OF WORK............................................................................................................ 2
3. REFERENCES................................................................................................................... 3
3.1.GENERAL REFERENCES........................................................................................... 3
3.2 SPECIFICATION AND DESIGN..................................................................................4
3.3 MATERIALS / SPECIFICATION...............................................................................4-5
4. DEFINITIONS.................................................................................................................... 6
5. RESPONSIBILITIES.......................................................................................................... 7
5.1 PROJECT ENGINEER................................................................................................. 7
5.2 QA/QC MANAGER...................................................................................................... 7
5.3 QA/QC ENGINEER...................................................................................................... 8
5.4 SITE ENGINEER......................................................................................................... 8
5.5 SAFETY OFFICER...................................................................................................... 8
5.6 STORE KEEPER......................................................................................................... 8
6. CONTRACTUALOBLIGATIONS........................................................................................8
7. MANPOWER & PLANT.................................................................................................... 11
7.1 MATERIALS REQUIRED........................................................................................... 11
7.2 TOOLS AND EQUIPMENT REQUIRED....................................................................12
7.3 PERSONNEL............................................................................................................. 14
8. QUALITY MANAGEMENT............................................................................................... 16
8.1 GENERAL.................................................................................................................. 16
8.2 REFERENCES........................................................................................................... 16
9. HEALTH, SAFETY & ENVIRONNMENTAL SUSTAINABILITY........................................17
9.1 WORK OPERATIONS................................................................................................ 20
9.2 FIRST AID & EMERGENCY SERVICES...................................................................20
9.3 RISK MANAGEMENT................................................................................................ 21
9.4 EMERGENCY CONTACT LIST.................................................................................21
9.5 ORGANIZATIONAL CHART......................................................................................21
Page v M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page vi M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
1. PURPOSE
The purpose of this method statement is to describe systematically the installation of
the Compressed Air piping system and associated activities within the West Depot.
Moreover this document will define the methods to be adopted to ensure that the
works conducted at site are in compliance with the relevant design documents and
materials. The materials will be installed in accordance with the relevant design
drawings and using recognized installation practices that are safe and compliant with
the Project Safety Plan, associated safety procedures and as per the manufacturer
recommendations. The inspection and testing of the works will be as per the Project
Quality Plan, its associated Quality Procedures and relevant Inspection and Test
plan.
Page 1 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
2. SCOPE OF WORKS
The works covered by this method statement sets out the procedures for the delivery,
installation, inspection and testing of the Compressed Air piping system in West
Depot.
All necessary materials/equipment will be delivered to site as per plan and will be
stored and handled as per the manufacturer’s recommendations. The pipe sizes,
distances and routing will be checked and installed as per the relevant shop
drawings. The cutting and prefabrication of the pipes will be carried out as per the
details shown in the relevant drawings.
Once the installation of pipes and fittings are completed, the system will be tested and
inspected as per the relevant standards. This report included but is not limited to the
following issues:
Inspection on arrival at site for the quantity, quality and compliance of material to
material submittal.
Descriptions of the methods and equipment to be used for each operation and
sequence of operation. Safety precautions to ensure safety of workers, members of
Public and users of adjacent facilities.
Page 2 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
3. REFERENCES
Page 3 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
The materials used at site shall conform to the requirement of approved material submittal.
The materials used at site shall conform to the requirement of approved site environmental
plan.
Page 4 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Building P
Pipework Sections
Page 5 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
4. DEFINITIONS
o ANM
: ArRiyadh New Mobility Consortium (CWG / EWG).
o Contractor
:The Contractor is CWG (Civil Working Group Joint Venture) (ANM).
o Engineer/Architect
: The Engineer/Architect is RMTC (Riyadh Metro Transit Consultants).
o EWG
: Electromechanical Working Group Joint
o TCSE JV
: Termigas–Cem Estero– Sitie Gulf –Electro Mechanical Works - Joint
Venture – MEP works subcontractor
o Owner
: ADA (ArRiyadh Development Authority).
o ITP
: Inspection & Test Plan
o IRE
:Inspection Request
o MAR
:Material Approval Request
o QA/QC
: Quality Assurance / Quality Control
o HSE
: Health & Safety Environment
o PPE
:Personal Protective Equipment
Page 6 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 7 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
5. RESPONSIBILITIES
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified
at relevant steps in the procedure:
Ensure all materials used and work performed are as per contract
specifications.
Liasioning with consultant/client and general work force involve in the project.
Page 8 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Ensure IRs are being raised for activities in timely manner and inspected by
the Company.
He will follow and carried out all the relevant tests as per project
specifications.
Daily reports of the works are achieved and coordinated for the future
planning with the Site Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the
same to the Site Engineer immediately.
Page 9 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Ensure all concerned personals shall use PPE and all other items as
required.
Ensure high risk elevated areas are provided are barricade, tape, safety nets
and provided with ladders.
Page 10 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
6. CONTRACTUAL OBLIGATIONS
The contractor shall, with due care and diligence, design to the next provided by the
contract, execute and complete the works and remedy any defects therein in accordance
with the provisions of the contract. The contractor shall provide all superintendence,
labours, materials, plant, equipment and all other things, whether of a temporary or
permanent nature, required in such design, execution and completion and remedying of
any defects, so far as the necessity for providing the same is specified in or is reasonably
to be inferred from the contract.
Page 11 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
The following materials will be used for the execution of the works:
Description Quantity
1 Pipe TBA
2 Fittings TBA
3 Pipe Support TBA
Page 12 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
The following equipment / tools will be used during the execution of works:
No Description Quantity
Page 13 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Figure D : W Level
The Ruler Water level used to insure straightness of the erected pipe
Page 14 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 15 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
7.3 PERSONNEL
7.3.1 SUBCONTRACTOR
o TCSE JV
Description Quantity
1 Project Manager 1
2 Construction Manager 1
3 QA/QC Manager / Team TBD
4 Health and Safety Manager / Team TBD
5 QA/QC Team TBD
6 Site Engineer / Supervisor TBD
7 Skilled Labors TBD
Page 16 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
8. QUALITY MANAGEMENT
8.1 Quality Assurance
8.1.1 General
For the execution activities of the construction phases related to the Installation of
Compressed Air Piping System a set of specific quality procedures shall be
implemented to guarantee the fulfilment of Employer’s requirements. Total control
processing shall be implemented through documentation system for submission,
approval, transmittal and recording, coordinated with all concerned parties for
systematic and harmonious accomplishment of the works. The activities shall be
carried out by specialized, qualified and experienced personnel.
Generally, QAP and QCP procedures are focused on assessing the quality of
inspection procedures, practices and results to improve consistency and accuracy of
the inspection outcomes
Refer to the Quality Assurance Plan: M-ANM-300000-GQQA-MPL-000001 Rev B
All procedures described in the QAP and QCP shall be followed. Procedures
mentioned there shall also be applicable to all works described in this method
statement. Quality measures for Installation of Compressed Air Piping System shall
be controlled through approved Inspection Requests (IRs), including all tasks
inspection points as per quality control records for Installation of Compressed Air
Piping System. QC Engineer shall maintain a master set of all relevant documents
checklists, standards, drawings, inspection reports and data in the master file with an
updated register.
Page 17 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 18 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
All site works relevant to this activity and other works are planned and executed in a
manner that the risk of danger to the public, Employer’s personnel, site personnel
and all people directly and indirectly associated with the works will be avoided,
mitigated or controlled especially during works on live traffic. The area should be
maintained free from undue obstructions and hazards at all times. Perimeter fence
shall be provided with gates manned by Security Personnel to prevent unauthorized
access. Appropriate access must be provided including pedestrian lanes and road
crossing as far as reasonably practicable.
All operatives must receive Site Specific Safety Induction and provided with the
mandatory PPE before deploying them on the work site. Briefing on the relevant
method statement, risk assessments and safe work procedures including emergency
procedures shall be conducted before the activity starts. Regular toolbox talks must
be done to ensure operatives are aware of the hazards and the control measures
related to their works. Permit to Work System must be implemented for all critical
works related to this activity.
Mobile plant equipment including stationary equipment and accessories that will be
used on site must adhere to the guidelines set forth in the Plant and Equipment
Procedure (M-ANM-300000-GH00-PRO-000018-0) and other applicable ANM
procedures. Prior to operating the equipment for the first time during a shift, the
operator shall inspect the equipment in accordance with the manufacturer's
guidelines. If at any time, a Mobile Plant Equipment is found to be in need of repair,
defective, or in any way unsafe, the equipment shall he taken out of service until it
has been restored to safe operating condition.
A safe work briefing which should be conducted prior to the start of this activity using
the attached form (M-ANM-300000-GH00-FOR-000003 Rev 0 -Safe Work Method
Page 19 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Statement). All operatives involved must sign in this form and a copy should be kept
for verification.
The Sub-contractor in charge for this activity is required to provide a competent and
experienced Safety Staff that will be responsible for implementing and maintaining
the appropriate HSE requirements.
Lifting operation shall be under the direct supervision of a qualified lifting supervisor.
The crane must have valid third party test certificate and shall be operated by a
competent operator with a valid third party training certificate and KSA driving
license. Competent rigger/s with valid third party training certificate must be assigned
to assist the crane operator. All lifting gears must have valid third party test certificate
and must be inspected before and throughout the duration of the lifting operation.
Under no circumstances, that a defective lifting equipment and accessories, will be
used during the normal course of this activity. Basic and standard lifting operation
shall use the standard lifting plan (M-ANM-300000-GH00-FOR-000164 Rev 0-Crane
Lift Plan) and should be attached in the Permit to Work while critical/complex lift shall
follow the requirements of M-ANM-300000-GC00-PRO-000002-Rev-0 -Lifting
Operation Procedure.
Temporary supports, steel cage preparation and shuttering works including removal
after completion of works must be in accordance with the approved technical
specifications. Any modifications must be approved by the technical department.
Site specific emergency plan must be developed with due consideration to this
activity and all other simultaneous activities in the area. Safe access shall be
provided to the working area/ work platform.
Use, storage and handling of chemicals must be in accordance with the Material
Safety Data Sheets and waste contaminated waste will be disposed in line with PME
Standard.
Page 20 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
All emergency provisions should be available including but not limited to First Aiders,
First Aid Boxes, Fire Extinguishers as well as rescue equipment for possible water
flooding in the area.
2. First aid box shall be provided at all stations. The first aid box will be supervised by
on site first aider/supervisors.
3. First aid shall be readily available during the all the hours where work is carried out
on site. All training shall be to MOL approved standards and such training shall
include Cardio Pulmonary Resuscitation (CPR) and other emergency techniques. All
first aiders shall be suitably identified with a “Red-Crescent” sticker pasted on the left
side of the safety helmet. It shall be worn at all times when on the site.
5. Sub-contractors shall provide trained first aiders for a minimum ratio of 1 to 50.
Page 21 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
The risk management enhances the traceability of the major construction hazards
identified from the beginning until completion of the project. The Risk Management
Strategy for the RMP Project includes the following items:
Page 22 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 23 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
3. Shelters shall be designed and set up with strong materials and shall be for large
groups of personnel to take shelter in high temperatures or when the work has been
stopped due to the ambient temperature being at or above 54 ˚C.
4. The following equipment will be provided inside the Heat Stress Shelters.
b. Bench seats.
e. Trash bins
Page 24 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
The first criterion is to assess the situation and contact the relevant emergency
services.
During the emergency service call, Arabic speaking person must be available for the
effective communication with the emergency service.
Once the emergency service has been summoned, place a contact person that is
speaking Arabic at an appropriate and visible location in order to direct the
emergency crew to the specific location of the casualty on arrival
Page 25 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
1. Prior Activities.
Prior to installation of Compressed Air Pipes & Fittings, it is essential that following
activities are completed or in progress:
All personnel must complete a Safety and Environmental induction with relevant
training (if required).
Installation of safety signs relate to Health and Safety precautions according to the
Specifications, M-ANM-300000-GH00-MPL-000001.
Drawing for laying of Compressed Air Pipes & Fittings installation locations shall be
provided
Survey must be carried out before start of operation as well as during all the
installation process.
All the materials to be used for the relevant works shall be already identified,
approved as per the ITP and available at the work place.
Site Engineer should ensure that the construction drawings are the latest issue.
Page 26 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
All the delivered materials to site will be inspected by site/QC engineer for any
damages/defects ensured that materials are as per approved material submittal and stored
adequately as per manufacturer recommendations. The damaged/defective materials will be
rejected and sent back to the supplier.
During the unloading and handling, utmost care shall be taken that the material is not dropped
on to the ground. If mechanical lifting equipment is used, ensure no metallic slings, hooks or
chains will be used in direct contact with the pipe. Deliver Pipes to Project site should be in
the proper storage.
Transportation: When loading and transporting Compressed Air pipes not still in its original
packing, take care that the pipes are supported along their entire length to avoid their being
bent. Arrange the pipes such that they lie with their end collars offset. Avoid subjecting the
pipes to impact stress, particularly when temperatures are low.
Page 27 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Short-term pipe deformation can occur where pipe stacks are unevenly exposed to the effects
of the sun (or other forms of heat). Pipes should not therefore be stored in direct sunlight.
No materials will be permitted to enter the works location without being inspected on arrival to
the site.
11.1.3 Installation of Compressed Air Pipes, Valves, Fittings and Accessories, Pipe
Hanger
Page 28 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
The installation of pipe hangers will be carried out in the following manner:
Identify the actual location of the hangers based on the approved drawings. Mark the
position for installing the drop-in anchor.
Check the hanger size to confirm the depth of the hole to be drilled based on the
relevant drawings and manufacturer’s specifications. Adjust the depth gauges and
flush the anchors with the base material surface.
Check the hanger size as per approved design to select the right drill bit and then drill
the hole according to the manufacturer’s specification on the marked location.
Hammer down the conical plug inside the anchor with setting punch.
Threading of pipes, if required, will be done in the workshop area. The works will be
carried out by trained and competent personnel.
The pipe will be cut to the desired length if not received as per the requirement. Place
the pipe in between the machine and cut it by using cutter.
Turn carriage hand wheel to bring dies against end of pipe. Continue applying
pressure to hand wheel to start dies.
When desired length of thread has been reached, depress release handle to
discharge latch. Die head will open automatically.
Release foot switch and then turn carriage hand wheel clockwise to back die head off.
Page 29 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
After threading provide jute for the assembling of elbow and pipe.
11.1.1.4 Installations
Valves Installation
Confirm the valve size and location based on the relevant shop drawings. Ensure that
the selected valve is as per manufacturer.
Place the valve between the pipes and make sure that the threads are free of dust.
Guide one of the pipe ends onto the valve's thread, slowly run pipe in clockwise
direction.
Hold the valve firmly by a spanner on the flat nearest joint and then rotate the pipe
with a plumbing wrench. Rotate the pipe until the end of the spindle operating joint.
Repeat the above steps for the other pipe.
Confirm the valve size and location based on the relevant shop drawings.
Ensure that the selected valve is flanged type or as per approved.
Place the valve between the pipe flanges. Make sure that the flange and the
adjacent pipe work are clean of dirt.
Select the gasket size according to the valve and associated pipe size based
on the approved shop drawings so that it can match the pipe work flange.
Connect the valve with the pipe flange. The pipe flange shall be square with
the associated pipeline.
Page 30 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
When the valve is in proper position, install the bolts into the holes. Tighten
the nuts one by one evenly using the torque wrench. Repeat the above steps
for the other joint.
Erection of Pipes
Mark the routing of the piping as per the approved and coordinated drawings.
Join all the fabricated pipes and prepare it for pressure testing.
Provide Pipe sleeves as per the specification for all pipes passing through the wall or
slab.
Metal sleeves to be provided for each pipe passing through wall or slab. Also the fire
sealant to be provided for the fire rated wall/slab.
Fittings
Threads should be free from mechanical damage, dirt, chips and excess cutting oil.
Use a thread sealant or as per material approval (Teflon tape, pipe dope etc.)
FOR WELDING:
Page 31 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Welding preparation:
Where ever welding is specified for connections, necessary welding procedures shall
be followed. Only qualified welders shall be used for welding. Only tack weld shall be
done prior to full weld to see that the member is properly oriented in the correct
location as per drawing.
For welded joints the requirements related to welds size and weld type shall be in
compliance with project drawings and welding specific procedure applicable.
All welds shall be carried out in accordance with approved welding procedure
specification and qualification. Welders and welding operator shall be qualified and
approved by Client accordance with the applicable welding code.
Welding process
Welding shall not be performed when the surfaces of the parts to be welded are wet
or during periods of high winds. Under rainy or windy conditions the welder/welding
operator and work shall be properly shielded.
Prior to fit-up and aiding, the grove and adjacent surfaces shall be cleaned to remove
all grease, oil, rust, dirt, paint by filling, brushing, grinding or by the use of approved
solvents.
The weld joint surfaces shall be visually inspected for the presence of moisture before
welding, In case of presence of moisture, the joint surface shall be dried by use of a
flame torch or by other approved methods.
Each weld layer or pass shall be visually free of slag, inclusions, cracks porosity and
lack of penetration.
Page 32 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Welded attachments
Clamps, welded clips, tack welds, or other appropriate means shall be used to
properly align the joint for welding
Welded attachments used for fit-up shall be compatible with the base materials.
All areas from which temporary attachments have been removed shall be visually
examined for any defects.
Tack Welding
Tack welds shall have the same quality requirements as the final welds.
Qualified welders using qualified welding procedure specification shall make tack
weld.
When tack welds are to become part of the finished weld, they shall be visually
examined and defective welds removed.
Material shall be cut to shape and size by mechanical means such as machining,
shearing, grinding, or by gas cutting. The cut surface shall be ground to bright metal.
The cut shall be smooth and true, and slag and contamination should be cleaned
from the cut surfaces.
Cleaning; all cleaning and rust removing shall be done by use of grinding wheels or
discs, wire brushes, abrasive paper or other suitable methods. The interior and
exterior surfaces of materials shall be cleaned to the required acceptance levels using
procedures meeting the requirements of specification.
Page 33 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Alignment
All pipes and fittings shall be inspected and tested after the completion of installation.
Before starting any test the system shall be visually inspected to ensure that the
recommendations for the correct installation procedure have been complied with, and
the pipe line together with appliances, valves and fittings are laid as per the above
given procedure.
Piping Leak Tests for Metal Compressed-Air Piping: Test new and modified parts of
existing piping. Cap and fill general-service compressed-air piping with oil-free dry air
or gaseous nitrogen to pressure of 50 psig (345 kPa) above system operating
pressure, but not less than 150 psig (1035 kPa). Isolate test source and let stand for
four hours to equalize Temperature. Refill system, if required, to test pressure; hold
for two hours with no drop in pressure.
Page 34 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 35 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
13. APPENDIX
Annexure 1
– Risk assessment
Annexure 2
– Emergency Flowchart Communications & Contacts
Annexure 3
– Safe Work Method Statement
Page 36 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Annexure 1
RISK ASSESSMENT
Page 37 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Risk Assessment
Project: Riyadh Metro Project - Line 3
Location: Stations ( WEST DEPOT)
Activity: Installation of Compressed air Piping RISK = LIKELIHOOD x SEVERITY
Ref No: M-ANM-3A1DPW-CM00-MST-000001-REV A
ng and preliminary activities Ensure safe access into working area and appropriate lighting.
Installation of safety signs and Health and Safety precautions according to the Specifications.
Prior to any construction activities related to substructures, pre-construction evaluations should be completed to
Public Safety.
determine existing conditions that could affect the construction.
Inadequate training.
1 3 3 9 Medium Based on the evaluation studies, wherever applicable (traffic management, utilities relocation, street closures etc.,) 1 3 3 Low
the pre-construction activities shall be taken up and completed before starting the construction of structure.
Presence of other
activities.
Following are the major pre-construction activities after obtaining the necessary work permits,
No Welfare.
In places where needed proper working platform must be provided.
Site Engineer should ensure that the construction drawings are the latest issue.
All the materials to be used for the relevant works shall be already identified, approved and available at the work
place.
Page 38 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Access roads connecting to the project site and various infrastructure facilities areas.
Public Safety. Construction of offices, workman restroom, mosque, dining hall, workshops, stores, and other related facilities. The
porta cabin / covered area for prayer shall be provided at locations, when there is no mosque / prayer room within
Inadequate training. 500 meters of working site.
2 3 3 9 Medium 1 3 3 Low
Presence of other Construction of facilities for water supply system, electric power system and distribution arrangements, drainage
activities. and waste disposal etc.
No Welfare. Toilets for the Staff and workers shall be provided along with sewage collection tank.
Lack
3 of HSE information conveyed to the workers All personnel prior to commencing work on site are to attend the site induction. 2 3 6 Low
Page 39 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Allow for appropriate lighting facility when natural light is not available.
Working in partial or full absence of light. Provide adequate site water and isotonic drinks supplies and carry out regular health checks on site personnel etc.
Study route and site features before mobilization to assess potential hazards.
Workers to wear appropriate PPE including safety glasses, high visibility jacket, helmet and safety shoes at all
times.
Page 40 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Blockages, breakdown and/or damages of equipment and plant. Maintenance to be ensured on a regular basis.
Workers to wear appropriate PPE (Gloves and steel toed safety boots) at all times.
Page 41 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Safe Working Load of lifting gears to be checked against the weight of the load to be lifted.
Failure of lifting gears or crane and/or tilting.
Crane safe working load and maximum working radius shall never be exceeded.
Overloading of the crane.
Lifting plan will be studied and prepared prior to starting the lifting activities.
Crane overturning.
Ensure 3rd party certified operator/riggers for lifting works.
Tilting of suspended
Use competent lift supervisor and one assistant for feedback.
loads.
Use tag lines to control the load to be lifted.
Spin of load / load
colliding with existing
7 Ensure continuous communication and visibility between signalman, supervisor and crane. 2 5 10 Medium
structure.
Use examined / tested / inspected lifting equipment.
Moving crane hitting
personnel during
Ensure all loose items are removed or securely fixed to the material to be lifted.
loading/unloading.
Area at risk should be cleared and cordoned off prior to lift.
Fall of material causing
injury/death of personnel.
Do not allow personnel to stand / walk under suspended loads.
Instability of lifting
Workers to wear appropriate PPE at all times.
equipment
Ensure a proper base is provided underneath the crane outriggers prior to lifting.
Scaffolding should be fully boarded, provided with handrail, mid rail, toe guard and proper out rigger and anchoring.
Slipping, tripping, fall from height leading to body injuries, cuts or Leaning or climbing over scaffold guardrails should be avoided.
death.
Scaffold platform should be clean and tidy to avoid any tripping hazard.
Unsafe use of ladder
8 causing injury/death. Full body harness system will be utilized as a last option to work at height. 1 4 4 Low
Objects / material fall from Ladders shall be at the correct angle and be secured or footed whilst in use.
height.
All objects / material to be kept away from the edge.
Page 42 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 43 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Inform nearby plant operator as to your presence, do not stand on haul roads and must wear high visibility clothing, safety helmet and safety boots.
Page 44 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Diversions to be implemented prior to any work commencing outside the site boundary’sAll traffic diversions are to be in accordance with the Traffic
Management and Diversion section within the method statement.All local authority permits to be in place prior to
deploying the traffic management and diversion.Working only permitted as per the times described on the
permit.Priority and thought to be given to members of the public, barriers, warning signs, good temporary footpath
access.Every precaution must be taken with regards to the placing of Concrete Jersey barriers.Times for delivery
Collision of vehicles with the workforce
11 will be depicted on the authorized permit and must be adhered to.Cones shall be used as a temporary diversion for 1 4 0 Low
the delivery vehicle.Workers to be made aware and kept reminded of the hazards with vehicles.Flagmen to be
deployed in strategic locations in order to slow the oncoming vehicles.Supervisor to conduct toolbox talk before
start of work. If the load is beyond the capacity of single person to lift, provide additional team member to lift. In
case of heavy loads to be lifted ensure appropriate equipment is used.Workers to wear appropriate PPE (Gloves
and steel toed safety boots) at all times.
Fire All flammable/ combustible materials should be protected if it cannot be removed and appropriate fire extinguisher
should be available.
Injury / Accident / Near miss due to unsafe act or condition in area Adequate fixed and temporary lighting (tower lights) must be provided to ensure proper illumination of the site to ensure workers, excavations and
of low or no illumination equipment can be clearly seen.
(general).
All heavy equipment must be provided with beacon lights, front and rear lights and audible alarms to ensure easy
Unidentifiable equipment identification by all workers in the area.
in the working area
(struck by). Personnel will wear high visibility jackets to ensure easy identification on the site at all times.
13 1 3 0 Low
Slips, Trips and falls due Adequate fixed and temporary lighting must be provided to ensure proper illumination of the site.
to poor site / work area
illumination. At least one supervisor must be available at all times to monitor and assist workers in case of emergency
Ensure adequate sleeping environment provided to staff during day shift.
Injury resulting from using
tools and equipment Ensure adequate time is allowed to share Information between shifts.
without sufficient task /
site lighting. Shift supervisors should be trained to recognize risk factors leading to fatigue and be able to identify fatigued
Page 45 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Inadequate supervision.
Sharp objects. Where work is particularly demanding, consider shortening the length of the shift.
Foreign Objects
Dust
Slip, trip & fall Special Toolbox meeting to be conducted by the HSE officer to all personnel to stay to away from Slip, trip & fall.
14 1 3 0 Low
Foreign Objects Ensure all access is free from obstructions.
Equipment shall be fitted with noise suppressors, properly and efficiently working at all times.
Disturbance of residents by noise and vibrations caused by Coordinate the activities for periods in the day when the disturbance to the public will be minimized.
n / Demobilization of plant
2 and equipment to/from site 1 3 0 Low
vehicles/equipment.
Regular maintenance of plant by lubrication, tightening loose parts, replacing worn-out components shall be
conducted to avoid increase in noise.
of Plant/vehicles around
3 the site Activities that potentially generate high dust levels shall be curtailed, suspended or postponed in situations where 1 3 0 Low
the wind direction and speed is causing adverse impacts on nearby sensitive receptors.
Care shall be taken to prevent mud/dust being transported onto the public roads by vehicle wheels (provide wash
bay).
Disturbance of residents by noise and vibrations caused by Equipment shall be fitted with noise suppressors, properly and efficiently working at all times. Regular maintenance of plant by lubrication, tightening loose
4 vehicles/equipment. parts, replacing worn-out components shall be conducted to avoid increase in noise. 1 3 0 Low
Page 46 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Before leaving warehouse all equipment shall be completely checked and sent to site only if all parts are regularly
working.
Fuel hydrocarbons and any other hazardous materials shall be stored at specifically designated, taped of areas
inside a spillage tray.
5 Spillage trays shall be located under the crank-cases of engines, pumps and machinery. 1 3 0 Low
Extinguishers shall be of sufficient number, size and required type to handle any potential fire hazard.
Any hoses shall be fitted with protective closer to avoid any leakages.
All the concrete/shotcrete waste and water contaminated with concrete to be discharged to this location.
6 1 3 0 Low
Solid hazardous and non-hazardous waste shall be immediately stored in temporary storage
Page 47 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Annexure 2
EMERGENCY FLOWCHART
Page 48 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 49 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Annexure 3
Page 50 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 51 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 52 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 53 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 54 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 55 M-ANM-3A1DPW-CM00-MST-000001-Rev A
METHOD STATEMENT FOR INSTALLATION OF COMPRESSED AIR PIPING
Page 56 M-ANM-3A1DPW-CM00-MST-000001-Rev A