SUPPLY AND INSTALLATION OF 01 NEW HEAVY FUEL OIL TANK AT Classic Schedule Layout 17-Jan-24 14:40

TOBRUK REFINERY

Activity ID Activity Name Original Start Finish Remaining Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025
Duration Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
420 HEAVY
01-Mar-24 FUEL
09-Oct-25 09-Oct-25, Q-43 PROJECT SUPPLY A
Q-43 PROJECT SUPPLY AND INSTALLATION OF 01 NEW OIL TANK 420
AT TOBRUK REFINERY
Q-43 PROJECT.2 PROJECT MILESTONES 420 01-Mar-24 09-Oct-25 420 09-Oct-25, Q-43 PROJECT.2 PROJEC

Project Start 0 01-Mar-24 0 Project Start, 01-Mar-24


Project Finish 0 09-Oct-25 0 Project Finish,
150 01-Mar-24
Q-43 PROJECT.1 PROJECT MANAGEMENT, HSSE , PROCUREMENT, 26-Sep-24
ENGINEERING 150 26-Sep-24, Q-43 PROJECT.1 PROJECT MANAGEMENT, HSSE , PROCUREMENT, ENGINEERING

Site Visit/Site Survey/Collect data 25 01-Mar-24 04-Apr-24 25 Site Visit/Site Survey/Collect data
Project Execution Plan and Project Management 30 12-Mar-24 22-Apr-24 30 Project Execution Plan and Project Management
Project Communication Plan 30 15-Mar-24 25-Apr-24 30 Project Communication Plan
Project HSSE Plan & Case Studies 30 12-Mar-24 22-Apr-24 30 Project HSSE Plan & Case Studies
Project Method Statement Report 30 01-Mar-24 11-Apr-24 30 Project Method Statement Report
Detailed Engineering 97 01-Mar-24 15-Jul-24 97 Detailed Engineering
Procurement 150 01-Mar-24 26-Sep-24 150 Procurement

Q-43 PROJECT.3 150.000 BBL 398(Fabrication


TANK FABRICATION WORK 02-Apr-24 09-Oct-25
in workshop 398
) 09-Oct-25, Q-43 PROJECT.3 150.000

Q-43 PROJECT.3.1 FOUNDATION WORKS 65 02-Apr-24 01-Jul-24 65 01-Jul-24, Q-43 PROJECT.3.1 FOUNDATION WORKS
Excavation Works 10 02-Apr-24 15-Apr-24 10 Excavation Works
Filling and compaction 20 16-Apr-24 13-May-24 20 Filling and compaction
Tank foundation works 35 14-May-24 01-Jul-24 35 Tank foundation works
Q-43 PROJECT.3.2 ERECTION OF 150.000 BBL TANK 180 02-Jul-24 10-Mar-25 180 10-Mar-25, Q-43 PROJECT.3.2 ERECTION OF 150.000 BBL TANK
Construction works 180 02-Jul-24 10-Mar-25 180 Construction works
Q-43 PROJECT.3.3 TANK HYDROTEST 20 11-Mar-25 07-Apr-25 20 07-Apr-25, Q-43 PROJECT.3.3 TANK HYDROTEST
Hydrotest works 20 11-Mar-25 07-Apr-25 20 Hydrotest works
Q-43 PROJECT.3.4 TANK COATING 30 08-Apr-25 19-May-25 30 19-May-25, Q-43 PROJECT.3.4 TANK COATING

Coating works 30 08-Apr-25 19-May-25 30 Coating works


Q-43 PROJECT.3.5 MECHANICAL/PIPING TIE-INS 30 20-May-25 30-Jun-25 30 30-Jun-25, Q-43 PROJECT.3.5 MECHANICAL/PIPING TIE-INS
Installation of Pipe supports/valves/Tie-ins , Sand blasting works 30 20-May-25 30-Jun-25 30 Installation of Pipe supports/valves/Tie-ins , Sand blasting works
Q-43 PROJECT.3.6 FIRE FIGHTING SYSTEM OF THE TANKS 53 01-Jul-25 11-Sep-25 53 11-Sep-25, Q-43 PROJECT.3.6 FIRE FIGHTING SY
Firefighting works/Foam system/Cooling system etc. 53 01-Jul-25 11-Sep-25 53 Firefighting works/Foam system/Cooling system etc.
30 20-May-25
Q-43 PROJECT.3.7 ELECTRICAL & INSTRUMENTATION FOR BOTH TANKS 30-Jun-25 30 30-Jun-25, Q-43 PROJECT.3.7 ELECTRICAL & INSTRUMENTATION FOR BOTH TAN
Installation of Cable tray, Hook-up etc. 30 20-May-25 30-Jun-25 30 Installation of Cable tray, Hook-up etc.
Q-43 PROJECT.3.8 COMISSIONING & START-UP 20 11-Sep-25 09-Oct-25 20 09-Oct-25, Q-43 PROJECT.3.8 COMIS
Comissioning 10 11-Sep-25 25-Sep-25 10 Comissioning
Start-up 10 25-Sep-25 09-Oct-25 10 Start-up

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 1
17/01/2024 00 I.E
Actual Work Critical Remaining Work