Professional Documents
Culture Documents
Day 1 Seminar, Part II Integrity
Day 1 Seminar, Part II Integrity
Testing Methods
Major pile defects cause
foundation failures
Anomaly Location (anomaly is not always a defect)
Percentage of Shafts with Anomalies
Calibration Sensors
Electronics Unit
Transmitter
Pressure Sensor Receiver
SHAPE
• Measure Wave Travelling
Speed (WS) from Downward
at 1 Ft Per
calibration sensors Second
• Measure time from
transmit time until
reflection pulse
from sidewall
received (t)
• Radius = WS * t
SHAPE Sensor Data – Good Slurry
SHAPE Output – Good Signals
Slurry within Spec
SHAPE Sensor Data – Too Much Sand in Slurry
Kenya Test
Kenya Test – Shaft within Verticality Spec
Kenya Test – Shaft Outside Verticality Spec
Waterfall Diagram on a Belled Shaft
Belled Shaft
SHAPE Adjustments for Diaphragm Walls
SHAPE
• Used to determine the shaft profile,
radius, volume, and verticality
Value
Cone Zero
LOG Scale
Cone Zero line
Field Examples
Bluefield, WV
Very soft, but muck bucket is empty – socket open for 5 days!
• Shale Bedrock
• Muck bucket used for
cleaning
• <0.5” over 75% of section
• <1.5” everywhere
Bluefield, WV
9/1/2000 10:56:12 AM
Hi 100.0 f t 63.0 Hz
2W 2.50 f t 2520 Hz
0.10
Pile Properties
D = 11.28 in.
0.00
L=40 ft.
WS = 12600
-0.10
L/D=43 (D=11.28 in)
V 0.174 in/s (0.186)
ft./sec.
40.00 f t (12600 f t/s)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 f t
(defect)
Pulse Echo Method Results
Shaft Properties
D = 60 in.
L= 69.5 ft.
WS = 13300 ft./sec
Bad
Pile
center
north
south
PIT indicated a defect at 13.5 ft. (4.1 m)
depth
Defect
Reaction pile OK
Franki pile MD :
LE:
5.25
26.08
(Brazil)
0.05 W S: 13123
LO : 6.56
H I: 328.08
due to -0 . 0 9
T1 To e
Vel
lateral soil 0 5 10 15 20 25 f t
F /Z
displaceme
nt from
later piles
Testing Foundations
In Service
0.04
0.00
-0.04
40.00 ft (12700 ft/s) V 0.076 in/s (0.080)
x1
Magn
0.75
29.4 ft 0.33
42.9 ft
1
Beta
0
0.97 0.85
12.1 ft 30.8 ft
0 5 10 15 20 25 30 35 40 45 50 55 60 diam
0 5 10 15 20 25 30 35 40 45 50 55 60 ft
Two velocity plot
Pile: bad - 3: # 2
12.5’
3.8m
concrete pile with 5
5
manufactured 20%
27’
8.2m reduction 10
10
15
40’ 15
20
20% 5’
max reduction. 25
reduction 1.5m
25
30
0.80
105.26 ft
30
35
35
40 35.4
ft diam
Conclusions - Pile Integrity Testing
• Fast, Inexpensive
• Mobile equipment, minimum site support
• Test many or even all piles on site
• No advance planning required
• Minimal pile surface preparation
• Finds major defects
• Cannot locate defect in cross section
• Can be difficult to locate defects in the upper
portion
• Potential length limitation (L/D > 30)
• Non-uniform pile difficult to interpret
• Cracks or joints block waves
Parallel Seismic Testing—PIT extension
• Used for unknown
foundation length
• Existing buildings
• Bridges
• Foundation reuse
• Instrumented hammer
• Hydrophone in PVC lined
borehole monitors wave
transmission
Parallel Seismic Test
Cross Hole Sonic Logging
ASTM D6760
Pull
Put probes in
Probes
From Cross Hole Test
bottom of Bottom
tubes. To Top Repeat test
Top view of pile with 4
for each access tubes
tube pair
Fill Tubes
with water Stress Waves, emitted
in one tube are received
in another one if concrete
quality is satisfactory
Transmit Receive
Cross Hole Sonic Logging
Velocity = distance/time
• Distance is spacing measured
between tubes
• Time is measured transit time
for pulse
Cross-hole Sonic Logging
Shaft
Reinforcement Cage
Shaft
CSL
60%
50%
40%
30%
20%
10%
0%
3 4 5 6 7 8 9 10
Shaft Diam. (ft)
GGL Shaft Tested GGL Cover Tested CSL Shaft Tested CSL Cover Tested 60
Potential issue with concrete flow
Upcoming problem with CSL
PDI Probes
All Probes both Transmit
and Receive
CSL Test Setup
How to find defects ?
Good
Defect
Reduced signal strength
Delayed arrival time
(slow wave speed)
65
Signal amplitude provides additional information
Signal
Defects
Arrival
First Arrival Time
“FAT” Defect
12dB
9dB
A B C
0
0 15% 30%
First Arrival Time Delay
Proposed guidance
Category B:
1. Rule out de-bonding (flood pile top)
2. Retest after longer wait time
3. Tomography
4. Consider depth location and # of affected profiles
Category C:
1. Rule out debonding (flood pile top)
2. Retest after longer wait time
3. Tomography
4. Consider depth location and # of affected profiles
5. excavation if near ground surface
6. core drilling if deep location (pressure grout, etc)
7. other test (low strain, high strain)
8. repair or replacement
PDI shaft – when to test?
ASTM D6760 suggests test after 3 days
(French norm requires test after 7 days)
Test after
Initial Test flooding top
and Test of shaft
Repeated 30
minutes later
after flooding
top of shaft
71
71
Tomography
• Used for evaluation of
“local defect”
• Defect in some scans
but not all scans.
• If defect in all scans it is a
full layer defect. No need to
pay for the Tomography
analysis
Tomography: “PDI-Tomo”
Runs on Windows 7 or higher
Requires minimal user input
Improved analysis techniques
Case Studies
Top Anomaly
Shaft was
rejected
Minimal or No Recovery
Cross-hole Sonic Logging
Advantages
• Not limited by L/D ratio
• Check concrete inside cage by depth & quadrant
• Installed tubes inspire better construction
• Tomography available
Limitations / Disadvantages
• Wait 3 to 7 days prior to test
• Access tubes required (steel preferred)
• Cannot see outside cage; limited x-section tested
• Small defect near tube can appear large
• Debonding, bleeding are issues
• leads to delays and unnecessary coring
Thermal Integrity Profiling
• ASTM D7949
Thermal Integrity Profiling
• Measures the elevated temperatures during the hydration process to
determine pile integrity
• Temperature during curing is directly related to concrete quality,
volume, and radius (cover)
• Reductions in temperature indicate necking, inclusions, or poor quality concrete
• Increases in temperature indicate bulges or increased concrete cover
• Variance in temperature between diametrically opposite wires
indicates cage alignment/cover issues
• Acquiring Volume data allows temperature to be converted to
radius
• Thermal Integrity Profiler evaluates concrete both inside and
outside the cage
• Assessing both cover and alignment
• 100% of cross section evaluated
• Evaluates shaft during curing (as early as 12 hrs. depending upon
mix design and pile diameter)
Thermal Profile from Uniform Shaft
Defect
avg avg
85 85
toe
toe
tanh
90 tanh
90
corrected
Depth (ft)
Depth (ft)
95 95
100 100
105 105
110 110
Toe Adjustment Example
TIP Testing Equipment
• Thermal Wire® cable
- Embedded in grout or concrete
- Digital sensors sample temperature
data
Quick Connect
TAG – Thermal AGgregator
Temperature drop is
approximately 42 °F between
average shaft temperature
and local temperature near
wires 7, 8, and 9
TIP Data at one half Peak Temperature
6
5 7
4 8
Coring Locations
3
9
2 10
1
Coring Results at approximately 90’ depth
• Coring result
close to wires 7
and 8, where
largest reduction
occurred
• Coring confirms
TIP test results
• Zone was hydro-
blasted and
pressure
grouting was
performed
Drilled Shaft with Soft Bottom
• Drilled Shaft
• Length: 24.55 ft.
• Shaft Diameter: 42 in (0-20.6 ft.)
• Socket Diameter: 38 in (20.6-24.55 ft.)
• Cage Diameter: 30 in
• Volume: 9.07 yd3 installed (107% of theoretical)
• Temporary casing installed to top of rock
Initial TIP results
Conversion to Radius
Coring results
Transmission Line Project
Late on a Friday we received a call from an Engineer stating “ We
pulled the forms off two foundations, and we think we have an
issue…”
Project Details
10
20
Depth in Feet
30
40
measure
d
50
60
70
TIP provided area versus depth to properly convert
embedded strain sensor data to force for a static load test
TIP on Micro Piles
• 10.75 inch
diameter
micropile
• 64 feet depth
PIT on Micro Piles
TIP and PIT on Micro Piles
Thermal Integrity Profiling
Advantages
Uses temperature vs. depth vs. quadrant
Test early after casting (speeds construction)
6 to 48 hours (depends on diameter)
Evaluates concrete quality, cover & alignment
Evaluates shape (look at peak temperature time)
Finds significant defects (look at “half peak time”)
Inspires quality construction
Avoids CSL issues of debonding, bleeding
Limitations / Disadvantages
Relies on fairly accurate volume measurements
Preplan thermal wire cables
Can test only during early curing
Thank You!!
Questions???