Prueba de Descarga Baterias Dcbus - Sec-J - Att - J - 11 - App1
Prueba de Descarga Baterias Dcbus - Sec-J - Att - J - 11 - App1
11 DC BUS INSTALLATION
TEST
ok
10 Provide hard copy of Cell Corder data.
Disconnect battery string to be tested using installed disconnect device or ok
11 by disconnecting the negative cable connection and insulating.
12 Connect Load Bank to Battery Quick Disconnect ok
ok
16 Upon completion of Load Test, initiate off-line recharge of tested string.
17 Upon completion of charge, place string back on-line. ok
Record any battery problems in "Notes" section of Battery Load Test
ok
18 Data Sheet.
Page 3 of 4
8/27/07
APPENDIX 1, SHEET 1 TO SECTION J, ATTACHMENT J.11 DC BUS INSTALLATION
TEST
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
See Comments
Page 3 of 4
8/27/07
APPENDIX 1, SHEET 2 TO SECTION J, ATTACHMENT J.11 DC BUS INSTALLATION TEST
BATTERY ON DISCHARGE
AS CELL
RECEIVED VOLTAGE CELL CELL
CELL CELL CELL UNDER VOLTAGE TEMP.
NO. SERIAL VOLTAGE LOAD AFTER (NEG. POST
NUMBER (OPEN (START OF RECHARGE OF CELL)
CIRCUIT) TEST)
10 MIN. 20 MIN. 30 MIN. 1 HR 2 HR 3 HR 4 HR 5 HR 6 HR
Cell 1
Cell 2
Cell 3
Cell 4
Cell 5
Cell 6
Cell 7
Cell 8
Cell 9
Cell 10
Cell 11
Cell 12
Total Batt
Voltage
Amb. Temp
Test Amps
% Capacity
(Tested)
Page 4 of 4
8/27/07
APPENDIX 1, SHEET 2 TO SECTION J, ATTACHMENT J.11 DC BUS INSTALLATION TEST
NOTES:
Page 4 of 4
8/27/07