Professional Documents
Culture Documents
33117-Iqc-0005 Rev. B
33117-Iqc-0005 Rev. B
1
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 2 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
1. GENERAL REQUIREMENTS:
API 560 5th Edition (2016) “FIRED HEATERS FOR GENERAL REFINERY SERVICE”.
API 530 7th Edition (2015) “CALCULATION OF HEATER TUBE THICKNESS IN
PETROLEUM REFINERIES” (Applicable to Radiant Coils Charge Heater MR‐H‐01, Nº 1
Interheater HTR MR‐H‐02, Nº 2 Interheater HTR MR‐H‐03, Nº 3 Interheater HTR MR‐
H‐04 and Hot Oil Convection Coil).
ASME I 2017 Edition “RULES OF CONSTRUCTION OF POWER BOILERS” (Applicable to
Steam Superheater Convection Coil, Steam Generation Convection Coil and BFW
Economizer Convection Coil).
INDIAN BOILER REGULATIONS IBR (Applicable to Steam Superheater Convection
Coil, Steam Generation Convection Coil, BFW Economizer Convection Coil).
ASME II 2017 Edition (Part A, C, D).
ASME V 2017 Edition “NONDESTRUCTIVE EXAMINATION”.
ASME VIII Div. 1 2017 Edition “RULES FOR CONSTRUCTION OF PRESSSURE VESSELS”.
ASME B31.3 2016 Edition “PROCESS PIPING” (Applicable to Radiant Coils Charge
Heater MR‐H‐01, Nº 1 Interheater HTR MR‐H‐02, Nº 2 Interheater HTR MR‐H‐03, Nº
3 Interheater HTR MR‐H‐04 and Hot Oil Convection Coil).
ASME IX 2017 Edition “QUALIFICATION STANDARD FOR WELDING, BRAZING AND
FUSING PROCEDURES; WELDERS; BRAZERS; AND WELDING, BRAZING AND FUSING
OPERATORS”.
EN 10204 2004 Edition “METALLIC PRODUCTS‐TYPES OF INSPECTION DOCUMENTS”.
B034‐0MN‐80‐45‐SP‐0002 Rev. 0 “JOB SPECIFICATION FOR FIRED HEATER
PACKAGE”.
2‐12‐7 (19 March 2015) “FIRED HEATER” – UOP Specification.
B034‐0MN‐80‐45‐SP‐0003 Rev.0 “SPECIFICATION FOR PROCUREMENT OF PRESSURE
PARTS”.
2
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 3 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
3
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 4 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
‐ No production welding shall be performed until the welding dossier (weld map with all
weld joints clearly marked, WPS and PQR) has been reviewed and returned to Vendor
either with minor comments or without comments.
‐ Welder performance qualifications as per clause 3.3 of 6‐17‐0003 Rev. 4. All Welders
and welding operators shall be qualified in accordance with ASME IX with the procedure,
materials and wall thickness range which are used for coils and in accordance with IBR
where applicable. Inspector shall witness the test and certify the qualification of each
welder. Only welders approved by the Inspector shall be employed.
‐ All PQR’s must be qualified in accordance with the requirements of ASME B31.3 2016
Edition (for Charge Heater MR‐H‐01, Nº 1 Interheater HTR MR‐H‐02, Nº 2 Interheater
HTR MR‐H‐03, Nº 3 Interheater HTR MR‐H‐04 and hot oil convection coil), ASME I 2017
Edition & IBR (for Steam Superheater Convection Coil, Steam Generation Convection
Coil and BFW Economizer Convection Coil), ASME IX 2017 Edition, API 560 5th Edition
and applicable Project Specifications 6‐17‐0003 Rev. 4, 2‐12‐7 and B034‐000‐80‐45‐4404
Rev. 0
‐ Welding consumables shall be selected in accordance with Appendix I & II of Project
Specification 6‐17‐0003 Rev. 4, Note 16 Section B of B034‐000‐80‐45‐4404 Rev. 0 and
Section 11.m of UOP Project Specification 2‐12‐7:
Material certificates (welding consumables) shall be certified as indicated in
section 3.4.3 of 6‐17‐0003:
4
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 5 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
a) For carbon steel material (P1) welding consumable shall be delivered with
material certificate EN 10204 3.1 in chemical and EN 10204 3.1 in
mechanical properties in accordance with the corresponding SFA of ASME II
Part C 2017 Edition.
b) For alloy material (grades P11, P9 and P22) welding consumable shall be
delivered with material certificate EN 10204 3.1 in chemical and EN 10204
3.1 in mechanical properties according to the corresponding SFA of ASME II
Part C 2017 Edition).
Brand of welding consumables shall be is subjected to the approval of EIC, as
required in Section 3.7.7 of Project Specification 6‐17‐0003 Rev. 4.
In case of dissimilar metals to be welded together the composition of welding
consumables shall be at least similar to that of higher alloyed material, as per
Note 16 Section B of B034‐000‐80‐45‐4404 Rev. 0 and section 11.m of UOP
Project Specification 2‐12‐7.
For alloy material use of low hydrogen welding consumables is highly
recommended (supplemental diffusible‐hydrogen designator of H4 or lower).
As per section 12.3.g. (2) of 2‐12‐7, product analysis content of tin and
phosphorous for welding consumables P11 material, when used, shall be less
than 0.015% and 0.012% respectively. The percentage limits are weight percent.
Weld metal for P22 base metals shall have a carbon content > 0,05% (as per
ASME II Part D requirements). It is highly recommended the use of only one
welding consumable heat number in order to reduce the number of PQR
qualifications.
Additionally, welding consumables of P22 material shall comply with the
following requirements of section 12.4.c.(3) of 2‐12‐7:
Mn and Si levels shall be maintained at the lowest possible levels
consistent with good weldability.
5
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 6 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
‐ Permitted welding processes as per API 560 5th Edition (2016), applicable Code (ASME
B31.3 for Charge Heater MR‐H‐01, Nº 1 Interheater HTR MR‐H‐02, Nº 2 Interheater HTR
MR‐H‐03, Nº 3 Interheater HTR MR‐H‐04 and hot oil convection coil and ASME I/IBR
Steam Superheater Convection Coil, Steam Generation Convection Coil and BFW
Economizer Convection Coil) and Section 3.7 of Project Specification 6‐17‐0003 Rev. 4.
GTAW process shall be used for root passes and SMAW process for fill and cap passes.
As required in section 3.7.2 of 6‐17‐0003 Rev. 4, purging inside the tubes for GTAW
welding shall be done with Argon 99.98% purity. Shielding gas shall be Argon 99.99%
purity.
‐ Backing strips or consumable inserts shall not be used (section 3.7.4 of 6‐17‐0003 Rev.
4 and section 11.n of UOP Project Specification 2‐12‐7).
‐ Installation and welds of thermocouples on furnace tubes shall be carried out in
accordance with Appendix V of Project Specification 6‐17‐0003 Rev. 4 and also in
accordance with the applicable Codes.
‐ Preheating shall be as per section 3.8 and Appendix III of 6‐17‐0003 Rev. 4, Section 330
of ASME B31.3 2016 Edition (for Charge Heater MR‐H‐01, Nº 1 Interheater HTR MR‐H‐
02, Nº 2 Interheater HTR MR‐H‐03, Nº 3 Interheater HTR MR‐H‐04 and hot oil convection
coil), Section PW‐38 & A‐100 of ASME I 2017 Edition & IBR (Steam Superheater
Convection Coil, Steam Generation Convection Coil and BFW Economizer Convection
Coil).
6
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 7 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
The preheat zone shall be at or above the specified minimum temperature in all
directions from the point of welding for a distance of the larger or 75 mm or 1.5 times
the greater nominal thickness.
Preheating shall be made using electrical resistances as required in section 7.4.5 of
B034‐0MN‐80‐45‐SP‐0002 Rev. 0.
Preheat temperature shall be maintained without interruption until any required PWHT,
except when all of the following conditions are satisfied: sections 3.8.3 & 3.8.4 of 7‐17‐
003 and section 330.2 of ASME B31.3 2016 Edition, the most stringent.
For welding in the case of dissimilar alloy combinations, the preheat temperature shall
be according to the alloy requiring the higher temperature.
Temperature measurement for preheating may be by thermocouple or temperature
sensitive crayons.
Minimum preheat temperature shall be in accordance with the requirements of the
specific Codes and applicable Project Specifications, the most stringent:
Welds between P9‐P9 material (ASME Number P5B): 205ºC.
Welds between P9‐P11 material (ASME Number P5B‐P4): 205ºC.
Welds between P11‐P22 material (ASME Number P4‐ P5A): 205ºC.
Welds between P22‐P22 material (ASME Number P5A‐P5A): 205ºC.
Welds between CS‐CS material (ASME Number P1‐P1): 10ºC.
‐ Maximum interpass temperature shall be monitored by means of thermosticks or
thermocouples.
Maximum interpass temperature shall be in accordance with the requirements of the
specific Codes and applicable Project Specifications, the most stringent:
Welds between P9‐P9 material (ASME Number P5B): 315ºC maximum.
Welds between P9‐P11 material (ASME Number P5B‐P4): 315ºC maximum.
Welds between P11‐P22 material (ASME Number P4‐ P5A): 315ºC maximum.
Welds between P22‐P22 material (ASME Number P5A‐P5A): 315ºC maximum.
Welds between CS‐CS material (ASME Number P1‐P1): 315ºC maximum.
7
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 8 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
8
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 9 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
9
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 10 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
b) Impact test of each Step cool test sample shall be performed and
transition curves developed per the requirements of point 1 of this
section.
c) Acceptance criteria shall be in accordance with the following:
PQR’s for joints between P22 material (2 ¼ Cr‐1Mo & 2 ¼ Cr‐1Mo) supporting
WPS’s for welding of Steam Superheater Convection Coil, shall be qualified in
accordance with the requirements of ASME IX 2017 Edition, 6‐17‐0003 Rev. 4,
B034‐000‐80‐45‐4404 Rev. 0, UOP 2‐12‐7, ASME I 2017 Edition and IBR, as
follows: welds shall be cooled slowly under the cover of mineral wool from the
recommended preheat temperature to room temperature; PQR’s shall be
qualified with 3 cycles of PWHT at 730 ± 10ºC during 2 hours/per cycle (above
315ºC heating rate shall be 150ºC/h and cooling rate to 315ºC shall be 60ºC/h)‐
10
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 11 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
mechanical test and hardness test shall be reported after one cycle of PWHT
and after 3 cycles of PWHT; chemical analysis; macrography; hardness test
(maximum acceptance value shall be 241 HB or the equivalent value in HV10);
‐ No welding repairs shall be carried out without the approval of Client and Owner
inspector.
11
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 12 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
12
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 13 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
‐ Required documentation:
Inspection and test plan in accordance with ITP 5011 Rev. 0 included in Project
Specification 6‐82‐5000 Rev. 0 and considering the requirements indicated in
these fabrication requirements. At least, 4 columns shall be included in each ITP:
MANUFACTURER, TECNICAS REUNIDAS, TPIA & EIL.
Welding dossier (Weld map marking clearly all weld joints, WPS, PQR) in
accordance with the specific Codes, Project Specifications and requirements of
section 1.2 of this document. Fabrication shall not commence until all the
involved documents have been reviewed and returned to Vendor either with
minor comments or without comments.
Welders Qualifications in accordance in accordance with the specific Codes,
Project Specifications and requirements of section 1.2 of this document.
Weld control sheets. Information there included shall be, at least, the following:
Heater number, Coil reference, Weld number/identification, Base Material
Specifications and base material heat number, WPS reference, Welding
Consumable specification and heat number, Welding date, Welder
identification, NDTs report number and date of test, PMI report number and
date of test, PWHT report number and date, Hardness report number and
date…. See an example in Annex I of this document.
Welding Repair Procedure (in accordance with the requirements of ASME B31.3
2016 Edition and Sections 3.6.7 & 5 of 6‐17‐0003 Rev. 4). Only two repairs per
13
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 14 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
joint are permitted. No welding repairs shall be carried out without the approval
of Client and TR inspector.
Material Certificates of welding consumables in accordance with EN 10204 3.1
(for chemical and mechanical properties).
Procedure for material inspection at reception and material traceability
procedure in accordance with ASME Code and Project Specifications 6‐17‐0003
Rev. 4 , 6‐82‐0004 Rev. 1 and ITP 6‐82‐1010 Rev. 1 “Inspection and test plan for
incoming material (checking for contractor’s supplied materials)”.
Positive Material Identification Procedure (PMI), quantitative and recordable
measure method in accordance with Project Specification 6‐82‐0002 Rev. 3, API
578 3rd Edition (2018) and API 560 5th Edition (2016). Acceptable PMI
instruments shall be either “Portable X‐Ray fluorescence” or “Optical Emission”
type.
Elements to be analyzed for P11, P22, and P9 shall be Cr and Mo. Acceptance
criteria shall be:
Base metal: within 10% of the range specified in the applicable material
standard.
Deposited weld metal: within 12.5% of the range specified in the
applicable welding consumable specification.
Visual Examination Procedure (VT) in accordance with ASME B31.3 2016 Edition
and ASME V 2017 Edition (Article 9). Acceptance criteria shall be as per table
341.3.2 of ASME B31.3 2016 Edition (normal fluid service) and section 3.6.3 &
3.6.4 of 6‐17‐0003.
VT procedure shall be prepared by a person qualified to ASNT Level III in visual
testing.
Cold bending Procedure (including information about bending procedure, visual
inspection & dimensional control after bending), in accordance with Section 332
of ASME B31.3 2016 Edition, Section 2.5 of Project Specification 6‐17‐0003 Rev.
14
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 15 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
4 and PFI Standard ES‐24. Tolerances for thinning, flattening and wrinkling of
bends shall be in accordance ASME B31.3 2016 Edition PFI Standard ES‐24, the
most stringent. (Finished surface shall be free of cracks and substantially free
from buckling. Thickness after bending of forming shall b not less than that
required by the design. Flattening of a bend: the difference between maximum
and minimum diameters at any cross section shall not exceed 8% of nominal
outside diameter).
Radiographic Test Procedure (RT) in accordance with Article 2 & Article 22 of
ASME V 2017 Edition, ASME B31.3 2016 Edition and Section 4.3 of Project
Specification 6‐17‐003 Rev. 4.
RT procedure shall be got approved from the Owner’s Inspector before
proceeding.
RT procedure shall be prepared by a person qualified to ASNT Level III in
radiographic testing.
Type of RT sources and films shall be as indicated in section 4.3.2 and Appendix
VI of 6‐17‐0003 Rev. 4.
Acceptance criteria shall be in accordance with section UW‐51 of ASME VIII Div.
1 2017 Edition and table 341.3.2 of ASME B31.3 2016 Edition (normal fluid
service), the most stringent.
Ultrasonic Test Procedure (UT) in accordance with Article 4 of ASME V 2017
Edition. Acceptance criteria shall be in accordance with Section 344.6.2 (a) of
ASME B31.3 2016 Edition.
UT procedure shall be prepared by a person qualified to ASNT Level III in
Ultrasonic testing.
Magnetic Particle Test Procedure (MT) in accordance with Article 7 of ASME V
2017 Edition and Section 7.4.6 of B034‐0MN‐80‐45‐SP‐0002 Rev. 0. Acceptance
criteria shall be in accordance with section 344.3.2 of ASME B31.3 2016 Edition.
15
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 16 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
Post Weld Heat Treatment Procedure at 730±10ºC during 2 hours for welds
between P9 material (pipe‐pipe) and welds between P9 material and P11
(pipe‐weldolets). (Above 315ºC, heating rate shall be 150ºC/h and cooling rate
to 315ºC shall be 60ºC/h).
Post weld heat treatment shall be carried out using electrical resistance coil
method (see section 7.4.5 of B034‐0MN‐80‐45‐SP‐0002 Rev. 0) and shall comply
with section 3.9 of 6‐17‐0003 Rev. 4 and ASME B31.3 2016 Edition.
Hardness test procedure in accordance with sections 3.9.2 & 4.4 of 6‐17‐0003
Rev. 4. Equipment to be used in production shall be a portable Vickers digital
harness tester (Poldi hardness testers are not permitted). Acceptance criteria
shall be maximum value of 225 HB, as per section 1.17.3 of 6‐44‐0051 Rev. 6
and section 1.23.c of 6‐44‐0054 Rev. 6.
Dimensional Control Procedure (tolerances for fabrication shall be as per
applicable Codes, Section 7.4.1 of Project Specification B034‐0MN‐80‐45‐SP‐
0002 Rev. 0, Section 2.3 of Project Specification 6‐17‐0003 Rev. 4. Dimensional
requirements of welds (weld reinforcement & undercuts) shall be in accordance
with Section 3.6.2 of 6‐17‐0003 Rev. 4 or table 341.3.2 of ASME B31.3 2017
Edition, the most stringent.
16
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 17 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
17
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 18 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
18
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 19 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
Cold bending of P9 pipes in accordance with Section 332 of ASME B31.3 2016
Edition.
Inspection of bends: 100% Visual (no cracks or linear indications shall be
present) and dimensional inspection of bends. (Finished surface shall be free of
cracks and substantially free from buckling. Thickness after bending of forming
shall b not less than that required by the design. Flattening of a bend: the
difference between maximum and minimum diameters at any cross section
shall not exceed 8% of nominal outside diameter).
Heat Treatment of bends is not required as per section 332.4 of ASME B31.3
2016 Edition.
Joint preparation, fit‐up and tack welding.
Removal of temporary tack welds by grinding or chipping and ground smooth of
the area without reduction of wall thickness. Magnetic particle test (MT)
inspection to verify the absence of linear indications.
Root pass welding (with GTAW process).
100% visual examination and dimensional control of root pass welds.
Welding (fill & cover passes).
Post heating of welds of between P9‐P9 material or welds between P9‐P11
materials shall be carried out, immediately after welding (prior to dropping the
preheat and before PWHT), as required in section 3.9.1 of Project Specification
6‐17‐0003 Rev. 4: at 300ºC minimum during 30 minutes. Welds shall be allowed
to cool to room temperature in a slow and uniform manner under the cover of
mineral wool.
Other Cr‐Mo steels (P22‐P22, P11‐P22) shall be cooled under the cover of
mineral wool from the recommended preheat temperature.
100% visual examination and dimensional control of cover passes.
10% magnetic particle test of cover passes (per welder and shift) of branch
welds, including fillet welds before Post Weld Heat treatment. Branch welds
19
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 20 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
shall consist of the welds between the pipe & reinforcement element
(weldolet), welds between weldolets and running pipes, welds between nozzle
and flanges.
10% Radiographic test (RT) per welder and shift of butt‐welds and branch
connections (welds between weldolets and pipes, welds between pipes and
flanges) before Post Weld Heat treatment.
10% Ultrasonic examination per welder and shift, before PWHT, may be applied
instead of radiography when the configuration makes radiographic examination
difficult to interpret or impossible to perform (welds between weldolets and
manifolds, fillet welds). When ultrasonic examination is impractical, magnetic
particle examination may be permitted (see section 4.3.7 of 6‐17‐0003 Rev. 4).
100% PMI of base metal and welds before Post Weld Heat Treatment in
accordance with Project Specification 6‐82‐0002.
Post Weld Heat Treatment of welds between P9 material (pipe‐pipe) and
welds between P9 material and P11 (pipe‐weldolets) at 730 ± 10 ºC during 2
hours (above 315ºC heating rate shall be 150ºC/h and cooling down to 315ºC
shall be done with a rate of 60ºC/h).
Post Weld Heat Treatment of welds between P22 material (manifold‐
manifold, manifold‐reducer) and between P22 material and P11 material
(reducer‐flange, manifold‐weldolet) at 690 ± 10ºC during 2 hours. (Above
315ºC, heating rate shall be 150ºC/h and cooling down to 315ºC shall be done
with a rate of 60ºC/h).
Monitoring of PWHT cycle and review of PWHT graph and report.
100% visual examination after Postweld Heat Treatment.
100% Hardness test after Post Weld Heat Treatment (maximum acceptance
value shall be 225 HB). Harness test shall be performed in base material, heat
affected zone and weld.
20
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 21 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
100% magnetic particle test of cover passes of branch welds (vent & drains,
including fillet welds), after PWHT, in accordance with section 7.4.6 of Project
Specification B034‐0MN‐80‐45‐SP‐0002 Rev. 0. Branch welds shall consist of the
welds between the pipe & reinforcement element (weldolet), welds between
weldolets and running pipes, welds between nozzle and flanges.
100% Radiographic test (RT) of all butt welds and branch connections (welds
between weldolet and pipes, welds between pipes and flanges) after Post Weld
Heat treatment in accordance with section 4.3.1 of 6‐17‐0003 Rev. 4, section
11.q, 11.r & 12.3.d of 2‐12‐7.
100% Ultrasonic examination after PWHT may be applied instead of radiography
when the configuration makes radiographic examination difficult to interpret or
impossible to perform (welds between weldolets and manifolds, fillet welds),
see section 4.3.7 of 6‐17‐0003 Rev. 4, 12.3.d of 2‐12‐7 and 17.2.2.f of API 560.
When ultrasonic examination is impractical, magnetic particle examination may
be permitted (see section 4.3.7 of 6‐17‐0003 Rev. 4).
Hydrostatic test of coils shall not be performed at workshop. It shall be
performed on site.
Purged and filled of coil with nitrogen and blanked off (see section 7.18.6 of
B034‐0MN‐80‐45‐SP‐0002 Rev. 0).
100% Dimensional control.
Final inspection.
Protection of all fabricated assemblies (including flange faces and other
machined faces) with easily removable rust preventive. Coil ends beveled for
welding shall be coated with heavy grease (see section 6 of Project Specification
6‐17‐0003 Rev. 4).
Packing, marking and preparation for shipping.
Nameplate review.
Review of Final Quality Dossier.
21
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 22 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
3. HOT OIL CONVECTION COIL OF CCR HEATER – CARBON STEEL MATERIAL, ASME B31.3 2016
EDITION, MDMT = 15ºC:
‐ Required documentation:
Inspection and test plan in accordance with ITP 5011 Rev. 0 included in Project
Specification 6‐82‐5000 Rev. 0 and considering the requirements indicated in
these fabrication requirements. At least, 4 columns shall be included in each ITP:
MANUFACTURER, TECNICAS REUNIDAS, TPIA & EIL.
Welding dossier (Weld map marking clearly all weld joints, WPS, PQR) in
accordance with the specific Codes, Project Specifications and requirements of
section 1.2 of this document. Fabrication shall not commence until all involved
documents have been reviewed and returned to Vendor either with minor
comments or without comments.
Welders Qualifications in accordance in accordance with the specific Codes,
Project Specifications and requirements of section 1.2 of this document.
Weld control sheets. Information there included shall be, at least, the following:
Heater number, Coil reference, Weld number/identification, Base Material
Specifications and base material heat number, WPS reference, Welding
Consumable specification and heat number, Welding date, Welder
identification, NDTs report number and date of test, PMI report number and
date of test, PWHT report number and date, Hardness report number and
date…. See an example in Annex I of this document.
Welding Repair Procedure (in accordance with applicable Code Requirements
of ASME B31.3 2016 Edition and Sections 3.6.7 & 5 of 6‐17‐0003 Rev.4). Only
two repairs per joint are permitted. No welding repairs shall be carried out
without the approval of Client and TR Inspector.
22
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 23 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
23
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 24 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
24
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 25 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
25
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 26 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
‐ Fabrication/Tests:
Cutting of materials and marking transfer (when needed). Welding ends
preparation (when applicable).
Beveling (when needed or when required) shall be carried out by the coil
manufacturer by grinding/machining and shall be in accordance with the
corresponding figure of ASME B16.25 as per table 1.7 of Project Specification 6‐
44‐0051, table 1.4 of Project Specification 6‐44‐0053 and table 1.6 of Project
Specification 6‐44‐0054.
100% visual inspection and dimensional control of welding edges.
Dressed bevels shall be examined by Magnetic Particle Test in accordance with
Guide ASTM E709 to confirm that the bevels are free from linear indications 1,6
mm or longer, as per Section 3.2 of Project Specification B034‐0MN‐80‐45‐SP‐
0003 Rev.0. Magnetic particle test on material bevel ends is mandatory when
coil manufacturer bevels some material or makes any additional work on
existing bevels.
Joint preparation, fit‐up and tack welding.
Removal of temporary tack welds by grinding or chipping and ground smooth of
the area without reduction of wall thickness. Magnetic Particle Test (MT)
inspection to verify the absence of linear indications.
Root pass welding (with GTAW process).
100% visual examination and dimensional control of root pass welds.
Welding (fill & cover passes).
100% visual examination and dimensional control of cover passes.
100% magnetic particle test of cover passes of branch welds (vent & drains,
including fillet welds) in accordance with section 7.4.6 of Project Specification
B034‐0MN‐80‐45‐SP‐0002 Rev. 0. (Branch welds shall consist of the welds
between the pipe & reinforcement element (weldolet), welds between
weldolets and running pipes, welds between nozzle and flanges).
26
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 27 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
100% Radiographic test (RT) of all butt welds and branch connections (welds
between weldolet and pipes, welds between pipes and flanges), in accordance
with section 4.3.1 of 6‐17‐0003 Rev. 4, sections 11.p & 11.q of UOP Specification
2‐12‐7.
100% Ultrasonic examination may be applied instead of radiography when the
configuration makes radiographic examination difficult to interpret or
impossible to perform (welds between weldolets and running pipe, fillet welds),
see section 4.3.7 of ‐17‐0003 Rev. 4 and 17.2.2.f of API 560. When ultrasonic
examination is impractical, magnetic particle examination may be permitted
(see section 4.3.7 of 6‐17‐0003 Rev. 4).
Intermediate welds of finned tubes shall be performed in accordance with the
requirements of section 2.19 of B034‐0MN‐80‐45‐SP‐0003 Rev. 0, section 3.7.6
of 6‐17‐0003 Rev. 4, section 3.13 of 6‐17‐0001 Rev. 5, EIL Standard 7‐17‐0607
Rev. 5:
Complete the tube weld joint following the corresponding WPS.
RT of the Intermediate welds shall be done before welding of bridging
pieces.
Welding of bridging pieces (which shall be spaced as close as possible,
depending upon the tube diameter), according to EIL Standard 7‐17‐
0607 Rev 5 and section 3.7.6 of 6‐17‐0003. Weld continuously with only
one run using stringer bead technique with a thin electrode (less than
2.0 mm diameter) with the size of weld restricted to 2 or 3 mm.
Hydrostatic test of each convection finned tubes at ground after welding
of bridging pieces and before assembly of finned tubes in convection
section.
After hydrotest tubes shall be cut to final length as per drawing (see
section 7.18.6 of B034‐0MN‐80‐45‐SP‐0002 Rev. 0) in case of end pipes
are not beveled. Beveling (when needed) shall be made in in accordance
27
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 28 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
4. STEAM SUPERHEATER CONVECTION COIL OF CCR – P22 MATERIAL, ASME I 2017 EDITION,
IBR, MDMT = 15ºC:
‐ Required documentation:
28
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 29 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
Inspection and test plan in accordance with ITP 5011 Rev. 0 included in Project
Specification 6‐82‐5000 Rev. 0 and considering the requirements indicated in
these fabrication requirements. At least, five columns shall be included in each
ITP: MANUFACTURER, TECNICAS REUNIDAS, TPIA, EIL & IBR.
Welding dossier (Weld map marking clearly all weld joints, WPS, PQR) in
accordance with the specific Codes, Project Specifications and requirements of
section 1.2 of this document. Fabrication shall not commence until all the
involved documents have been reviewed and returned to Vendor either with
minor comments or without comments.
Welders Qualifications in accordance in accordance with the specific Codes,
Project Specifications and requirements of section 1.2 of this document. IBR.
Weld control sheets. Information there included shall be, at least, the following:
Heater number, Coil reference, Weld number/identification, Base Material
Specifications and base material heat number, WPS reference, Welding
Consumable specification and heat number, Welding date, Welder
identification, NDTs report number and date of test, PMI report number and
date of test, PWHT report number and date, Hardness report number and
date…. See an example in Annex I of this document.
Welding Repair Procedure (in accordance with the requirement of applicable
Codes ASME I & IBR and Section 3.6.7 & 5 of 6‐17‐0003 Rev.4). Only two repairs
per joint are permitted. No welding repairs shall be carried out without the
approval of Client and TR inspector.
Material Certificates of welding consumables in accordance with EN 10204 3.1
(for chemical properties and mechanical properties).
Procedure for material inspection at reception and material traceability
procedure in accordance with ASME Code and Project Specifications 6‐17‐0003
Rev. 4, 6‐82‐0004 Rev. 1 and ITP 6‐82‐1010 Rev. 1 “Inspection and test plan for
incoming material (checking for contractor’s supplied materials)”.
29
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 30 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
30
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 31 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
Post Weld Heat Treatment Procedure 730 ± 10 ºC during 2 hours (above 315ºC
heating rate shall be 150ºC/h and cooling down to 315ºC shall be done with a
rate of 60ºC/h). Post weld heat treatment shall be carried out using electrical
resistance coil method (see section 7.4.5 of B034‐0MN‐80‐45‐SP‐0002 Rev. 0)
and shall comply with section 3.9 of 6‐17‐0003 Rev. 4, ASME I 2017 Edition and
IBR.
Hardness test procedure in accordance with sections 3.9.2 & 4.4 of 6‐17‐0003
Rev. 4. Equipment to be used in production shall be a portable Vickers digital
harness tester (Poldi hardness testers are not permitted). Acceptance criteria
shall be maximum value of 241 HB.
Dimensional Control Procedure (tolerances for fabrication shall be as per
applicable Codes, Section 7.4.1 of Project Specification B034‐0MN‐80‐45‐SP‐
0002 Rev. 0, Section 2.3 of Project Specification 6‐17‐0003 Rev. 4. Dimensional
requirements of welds (weld reinforcement & undercuts) shall be in accordance
31
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 32 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
with Section 3.6.2 of 6‐17‐0003 Rev. 4 or Section PW‐35 of ASME I 2017 Edition,
the most stringent.
General dimensions shall be verified in accordance with the corresponding
checklist (Heater quality check reporting formats) included in Annex II of Project
Specification 6‐17‐0017 Rev. 0.
Hydrostatic test procedure including cleaning and drying (all segments of coil
shall be thoroughly drained immediately after the test and flushing of coil after
hydrostatic test with compressed air shall be performed), as required in section
4.13.vii of B034‐0MN‐80‐45‐SP‐0002 Rev. 0, section 4.2 of 6‐17‐0003 Rev. 4,
Section PG‐99 of ASME I 2017 Edition, API 560 2016 Edition and IBR
requirements. Water used for hydrostatic testing shall be potable. In case of
non‐drainable heaters or where the total evacuation of the water cannot be
ensured, coil shall be hydro tested with De‐Mineralized water having
preservative chemicals.
Nitrogen blanketing procedure as required in section 7.18.6 of B034‐0MN‐80‐
45‐SP‐0002 Rev. 0.
Packing, marking, shipping procedure and preservation specification in
accordance with Section 8 of Project Specification 6‐17‐0001 Rev. 5 and Section
7 of Project Specification 6‐17‐0003 Rev 4. All assemblies and joints shall be
marked as indicated in section 7.2 of 6‐17‐0003 Rev. 4. According to section 8
of Project specification 6‐17‐0001 Rev. 5 and section 7.3 of Project Specification
6‐17‐0003 Rev. 4, all material shall be supplied with proper wrapping and
packing so that they will be preserved in as new condition during transportation,
handling and under the rainy/corrosive outdoor condition of storage at site.
Packing shall be suitable for rail or road transport and also seaworthy if
transported by sea. Open ends shall be capped to prevent entrance of foreign
matter.
Quality dossier index.
32
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 33 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
Packing list.
As‐built drawings.
Final Quality Dossier. It shall be available for review during intermediate
inspections and final inspection. Equipment shall not be released for shipment
until the Final Quality Dossier are in TR possession.
All statutory approvals from IBR are in Vendor’s scope including the necessary
co‐ordination and liaison work in this respect. Any change/addition required to
be made to meet the requirements and full satisfaction of statutory authority
shall be carried out by Vendor with the approval of Contractor and part of his
scope without any time and cost implications to the owner.
‐ Pre‐inspection meeting (PIM).
‐ Material reception:
100% visual inspection, check of marks and dimensional control (including
thickness control of materials) of base materials and welding consumables.
Inspection shall be performed in accordance with ITP 6‐82‐1010 Rev. 1. Material
inspection records as per Project Specification 6‐82‐1010 Rev. 1 and traceability
records as per Project Specification 6‐82‐0004 Rev. 1 shall be maintained.
Review of welding consumables certificates.
‐ Fabrication/Tests:
Cutting of materials and marking transfer (when needed). Welding ends
preparation (when applicable).
Beveling (when needed or required) shall be carried out by the coil
manufacturer by grinding/machining and shall be in accordance with the
corresponding figure of ASME B16.25 as per table 1.7 of Project Specification 6‐
44‐0051, table 1.4 of Project Specification 6‐44‐0053 and table 1.6 of Project
Specification 6‐44‐0054.
100% visual inspection and dimensional control of welding edges.
33
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 34 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
34
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 35 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
35
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 36 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
36
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 37 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
are free from linear indications 1,6 mm or longer, as per Section 3.2 of
Project Specification B034‐0MN‐80‐45‐SP‐0003 Rev.0.
Pipes shall be purged by compressed air/hot air to remove water and
moisture.
Hydrostatic test of coils to be performed after written clearance has been
obtained from the EIC (see section 4.2 of 6‐17‐0003 Rev. 4). Test pressure shall
be maintained for a minimum period of 1 hour.
Purged and filled of coil with nitrogen and blanked off (see section 7.18.6 of
B034‐0MN‐80‐45‐SP‐0002 Rev. 0).
100% Dimensional control.
Final inspection.
Protection of all fabricated assemblies (including flange faces and other
machined faces) with easily removable rust preventive. Coil ends beveled for
welding shall be coated with heavy grease (see section 6 of Project Specification
6‐17‐0003 Rev. 4).
Packing, marking and preparation for shipping.
Nameplate review.
Review of Final Quality Dossier, including the corresponding IBR form.
Vendor shall comply with all IBR regulations for this convection coil. Vendor
shall arrange for inspection of coils and all necessary IBR documentation and
approvals.
5. STEAM GENERATION AND BFW CONVECTION COILS OF CCR HEATER – CARBON STEEL
MATERIAL, ASME I 2017 EDITION, IBR, MDMT = 15ºC:
‐ Required documentation:
Inspection and test plan in accordance with ITP 5011 Rev. 0 included in Project
Specification 6‐82‐5000 Rev. 0 and considering the requirements indicated in
37
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 38 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
38
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 39 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
Visual Examination Procedure (VT) in accordance with ASME I 2017 Edition, IBR
and ASME V 2017 Edition (Article 9). Acceptance criteria shall be as ASME I 2017
Edition and section 3.6.3 & 3.6.4 of 6‐17‐0003.
VT procedure shall be prepared by a person qualified to ASNT Level III in visual
testing.
Radiographic Test Procedure (RT) in accordance with Article 2 & Article 22 of
ASME V 2017 Edition, ASME I 2017 Edition, IBR and Section 4.3 of Project
Specification 6‐17‐003 Rev. 4.
RT procedure shall be got approved from the Owner’s Inspector before
proceeding.
RT procedure shall be prepared by a person qualified to ASNT Level III in
radiographic testing.
Type of RT sources and films shall be as indicated in section 4.3.2 and Appendix
VI of 6‐17‐0003 Rev. 4.
Acceptance criteria shall be in accordance with section UW‐51 of ASME VIII Div.
1 2017 Edition and Section PW‐51 of ASME I 2017 Edition, the most stringent.
39
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 40 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
40
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 41 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
41
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 42 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
42
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 43 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
100% Radiographic test (RT) of all butt welds and branch connections (welds
between weldolet and pipes, welds between pipes and flanges), in accordance
with section 4.3.1 of 6‐17‐0003 Rev. 4, sections 11.p & 11.q of UOP Specification
2‐12‐7.
100% Ultrasonic examination may be applied instead of radiography when the
configuration makes radiographic examination difficult to interpret or
impossible to perform (welds between weldolets and running pipe, fillet welds),
see section 4.3.7 of ‐17‐0003 Rev. 4 and 17.2.2.f of API 560. When ultrasonic
examination is impractical, magnetic particle examination may be permitted
(see section 4.3.7 of 6‐17‐0003 Rev. 4).
Intermediate welds of finned tubes shall be performed in accordance with the
requirements of section 2.19 of B034‐0MN‐80‐45‐SP‐0003 Rev. 0, section 3.7.6
of 6‐17‐0003 Rev. 4, section 3.13 of 6‐17‐0001 Rev. 5, EIL Standard 7‐17‐0607
Rev. 5:
Complete the tube weld joint following the corresponding WPS.
RT of the Intermediate welds shall be done before welding of bridging
pieces.
Welding of bridging pieces (which shall be spaced as close as possible,
depending upon the tube diameter), according to EIL Standard 7‐17‐
0607 Rev 5 and section 3.7.6 of 6‐17‐0003. Weld continuously with only
one run using stringer bead technique with a thin electrode (less than
2.0 mm diameter with the size of weld restricted to 2 or 3 mm.
Hydrostatic test of each convection finned tubes at ground after
welding of bridging pieces and before assembly of finned tubes in
convection section.
After hydrotest tubes shall be cut to final length as per drawing (see
section 7.18.6 of B034‐0MN‐80‐45‐SP‐0002 Rev. 0) in case of end pipes
are not beveled. Beveling (when needed) shall be made in in accordance
43
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 44 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
44
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 45 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 EIL PROJECT Nº: B034
INTERHEATER HTR (MR-H-03), Nº 3 INTERHEATER HTR (MR-H-04), HOT OIL TRSA PROJECT Nº:
CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION, 33117
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER
CONVECTION SECTION
45
CCR PRESSURE PARTS FABRICATION REQUIREMENTS SHEET 46 OF 46
PROJECT: BS-VI MS BLOCK PROJECT KOCHI REFINERY
EQUIPMENT: CCR HEATER
EIL PROJECT Nº: B034
CHARGE HEATER (MR-H-01), Nº 1 INTERHEATER HTR (MR-H-02), Nº 2 INTERHEATER HTR (MR-H-03), Nº 3
TRSA PROJECT Nº: 33117
INTERHEATER HTR (MR-H-04), HOT OIL CONVECTION SECTION, STEAM SUPERHEATER CONVECTION SECTION,
STEAM GENERATION CONVECTION SECTION & BFW ECONOMIZER CONVECTION SECTION