LAPORAN PRESTASI PEKERJAAN

Paket Pekerjaan : Rumah Type Keira Sudut Kontraktor : PT. Sanjaya Putra Utama
Proyek : Pesona Rorotan Laporan : Ke 9(Sembilan) - Termin VIII - 100%
Lokasi : Blok C2 No.11 Periode : 30 April s/d 28 Januari 2023
PRESTASI
BOBOT Bobot Prestasi
NO. URAIAN PEKERJAAN SAT QUANTITY Lalu Sekarang Jumlah
(%) (%) (%) (%) (%)
I PEKERJAAN PERSIAPAN 4.70 4.70
1 Direksi Keet dan Gudang M2 55.00 1.09 80.00 20.000 100.00 1.09
2 Listrik Kerja Ls 1.00 1.19 90.00 10.00 100.00 1.19
3 Air Kerja Ls 1.00 1.19 90.00 10.00 100.00 1.19
4 Uitzet & Bouwplank m' 33.00 0.45 100.00 - 100.00 0.45
5 Galian Tanah m3 23.97 0.25 100.00 - 100.00 0.25
6 Urugan Pasir (dibawah pondasi) m3 1.39 0.16 95.00 5.00 100.00 0.16
7 Lantai Kerja m3 0.14 0.01 95.00 5.00 100.00 0.01
8 Urugan Tanah Kembali (pondasi) m3 7.26 0.04 90.00 10.00 100.00 0.04
9 Urugan Tanah Kembali + Angkutan (levelling) m3 27.50 0.32 90.00 10.00 100.00 0.32

II PEKERJAAN PASANGAN 32.29 32.29


1 Pas. Rollag m' 24.30 0.87 80.00 20.00 100.00 0.87
2 Pas. Pondasi Batu Kali 1:6 m3 16.23 5.02 100.00 100.00 5.02
3 Pas. Bata Merah Press 1:3 (All Area) m2 71.40 1.98 100.00 100.00 1.98
4 Pas. Bata Merah Press 1:6 (All Area) m2 252.00 7.00 100.00 100.00 7.00
5 Pas. Bata Tempel m2 8.84 0.87 90.00 10.00 100.00 0.87
6 Pas. Batu Alam m2 9.20 0.91 90.00 10.00 100.00 0.91
7 Plesteran Dinding Kasar 1:6 m2 340.00 9.45 80.00 20.00 100.00 9.45
8 Penebalan Plester 5 cm m2 9.50 0.11 85.00 15.00 100.00 0.11
9 Plester Beton m2 41.00 0.73 90.00 10.00 100.00 0.73
10 Acian Dinding m2 338.00 4.02 90.00 10.00 100.00 4.02
11 Finishing Sudut / Skonengan m' 164.00 1.30 90.00 10.00 100.00 1.30
12 Tali Air Dinding Tampak m' 6.50 0.03 85.00 15.00 100.00 0.03

III PEKERJAAN BETON LT. DASAR 10.08 10.08


1 Foot Plat m3 0.87 1.30 100.00 - 100.00 1.30
2 Sloof Konstruksi m3 1.50 2.14 100.00 100.00 2.14
3 Kolom Konstruksi m3 1.33 1.89 95.00 5.00 100.00 1.89
4 Kolom Praktis m3 0.69 0.98 95.00 5.00 100.00 0.98
5 Balok Konstruksi m3 1.77 2.80 95.00 5.00 100.00 2.80
6 Topi-Topi m3 1.19 0.94 95.00 5.00 100.00 0.94
7 Waterproofing m2 1.19 0.03 95.00 5.00 100.00 0.03

IV PEKERJAAN BETON LT. ATAS 9.25 9.25


1 Kolom Konstruksi m3 0.86 1.36 90.00 10.00 100.00 1.36
2 Kolom Praktis m3 0.41 0.58 90.00 10.00 100.00 0.58
3 Balok Konstruksi m3 0.80 1.27 95.00 5.00 100.00 1.27
4 Ring Balok m3 0.29 0.44 95.00 5.00 100.00 0.44
5 Plat Lantai t=12 & t=10 cm m3 3.45 5.20 95.00 5.00 100.00 5.20
6 Topi-Topi t=10 cm m3 0.36 0.28 95.00 5.00 100.00 0.28
7 Waterproofing m2 5.00 0.12 85.000 15.00 100.00 0.12

V PEKERJAAN BETON LT. ATAP 3.25 3.25


1 Kolom Konstruksi m3 0.48 0.76 90.00 10.00 100.00 0.76
2 Ring Balok m3 0.37 0.58 90.00 10.00 100.00 0.58
3 Plat Lantai t=10 cm & T=12 cm m3 1.09 1.63 90.00 10.00 100.00 1.63
4 Topi-Topi t= 10 cm m3 0.36 0.28 95.00 5.00 100.00 0.28

VI PEK. KUSEN, DAUN PINTU DAN RANGKA JENDELA 9.91 9.91


Pintu (PJ1) Rangka Aluminium 4" + Daun Pintu Engineering
1 bh 1.00 1.78 70.00 30.00 100.00 1.78
wood
Pintu (PJ2) Rangka Aluminium 4" + Daun Pintu Engineering
2 bh 1.00 1.38 70.00 30.00 100.00 1.38
wood
Pintu (PJ3) Rangka Aluminium 4" + Daun Pintu Engineering
3 bh 1.00 1.19 70.00 30.00 100.00 1.19
wood
Pintu (P1) Rangka Aluminium 4" + Daun Pintu Engineering
4 bh 2.00 1.42 70.00 30.00 100.00 1.42
wood
5 Pintu (P2) KM/WC PVC ukuran overall 700x2.150 mm + knob bh 2.00 0.63 70.00 30.00 100.00 0.63

Bouvenlight Jungkit (BV), Kaca Polos 5 mm rangka dan kusen


6 bh 1.00 0.47 70.00 30.00 100.00 0.47
alumunium powder coating putih ukuran overall 600x450 mm
PRESTASI
BOBOT Bobot Prestasi
NO. URAIAN PEKERJAAN SAT QUANTITY Lalu Sekarang Jumlah
(%) (%) (%) (%) (%)
Jendela Jungkit + Fixed (J1), Kaca Polos 5 mm rangka dan
7 kusen alumunium powder coating putih ukuran overall bh 1.00 0.59 70.00 30.00 100.00 0.59
1.350x1.900 mm
Jendela Jungkit + Fixed (J2), Kaca Polos 5 mm rangka dan
8 kusen alumunium powder coating putih ukuran overall bh 1.00 1.19 70.00 30.00 100.00 1.19
1.225x1.850 mm + 750x1.850 mm
Jendela Jungkit + Fixed (J3), Kaca Polos 5 mm rangka dan
9 kusen alumunium powder coating putih ukuran overall bh 1.00 0.79 70.00 30.00 100.00 0.79
1.300x1.850 mm
Jendela Jungkit + Fixed (J4), Kaca Polos 5 mm rangka dan
10 kusen alumunium powder coating putih ukuran overall bh 1.00 0.47 70.00 30.00 100.00 0.47
600x1.350 mm

VII PEKERJAAN PENGGANTUNG DAN KACA 1.39 1.39


1 Pekerjaan Kaca Polos 5 mm m2 3.60 0.20 95.00 5.00 100.00 0.20
2 Kunci PALOMA HDP 67393 set 5.00 0.57 95.00 5.00 100.00 0.57
3 Engsel 4x3" 2BB psg 3.00 0.47 95.00 5.00 100.00 0.47
4 Engsel 3x2,5" 2BB psg 4.00 0.05 95.00 5.00 100.00 0.05
5 Rambuncis bh 4.00 0.03 95.00 5.00 100.00 0.03
6 Ramskar bh 8.00 0.07 95.00 5.00 100.00 0.07

VIII PEKERJAAN ATAP 2.46 2.46


1 Rangka Atap Konstruksi Baja Ringan m2 24.00 1.14 95.00 5.00 100.00 1.14
2 Atap Genteng Beton Flat ex. Mutiara m2 24.00 0.85 95.00 5.00 100.00 0.85
3 Nok Atap ex.Mutiara m' 4.00 0.03 95.00 5.00 100.00 0.03
4 Lisplank GRC Plank lebar 300 mm m' 14.00 0.44 95.00 5.00 100.00 0.44

IX PEKERJAAN PLAFOND 3.67 3.67


1 Beton Expose m2 11.00 0.13 70.00 30.00 100.00 0.13
2 Plafond Gypsum WR 9 mm + Rangka m2 10.50 0.45 70.00 30.00 100.00 0.45
3 Plafond Gypsum Board 9 mm + Rangka m2 49.00 2.14 90.00 10.00 100.00 2.14
4 List Plafond Got m' 85.00 0.84 85.00 15.00 100.00 0.84
5 Tali Air m' 14.50 0.11 70.00 30.00 100.00 0.11

X PEKERJAAN LANTAI 3.40 3.40


1 Floor Lantai tebal 3 cm m2 44.46 0.79 85.00 15.00 100.00 0.79
2 Lantai Rabat Beton tebal 5 cm carport m2 10.00 0.43 85.00 15.00 100.00 0.43
3 Lantai ASIATile uk. 40x40 cm m2 44.46 2.03 90.00 10.00 100.00 2.03
Lantai Keramik ASIA Tile uk. 20x20 cm area teras depan +
4 m2 4.44 0.15 85.00 15.00 100.00 0.15
belakang

XI PEKERJAAN INSTALASI AIR KOTOR 3.43 3.43


1 Pipa PVC Ø 3 " AW m' 41.00 0.81 80.00 20.00 100.00 0.81
2 Pipa PVC Ø 3 " D m' 10.00 0.15 80.00 20.00 100.00 0.15
3 Pipa PVC Ø 4 " D m' 24.50 0.43 80.00 20.00 100.00 0.43
Pipa PVC Ø 4 " D m' 24.00 0.42 80.00 20.00 100.00 0.42
4 Pipa PVC Ø 2 " AW m' 6.00 0.11 80.00 20.00 100.00 0.11
5 Roof Drain unit 3.00 0.08 100.00 100.00 0.08
6 Septicktank+Resapan Air (Pas. Bata) bh 1.00 1.38 80.00 20.00 100.00 1.38
7 Bak Kontrol unit 1.00 0.05 60.00 40.00 100.00 0.05

XII PEKERJAAN INSTALASI AIR BERSIH 2.84 2.84


1 Pipa PVC Ø 1/2" AW m' 12.10 0.07 85.00 15.00 100.00 0.07
2 Pipa PVC Ø 3/4" AW m' 21.00 0.13 85.00 15.00 100.00 0.13
3 Pipa PVC Ø 1" AW m' 23.00 0.15 85.00 15.00 100.00 0.15
4 Gate Valve Ø 3/4" AW unit 3.00 0.01 100.00 100.00 0.01
5 Gate Valve Ø 1" AW unit 1.00 0.01 100.00 100.00 0.01
6 Kran Taman Ø 1/2" unit 2.00 0.02 85.00 15.00 100.00 0.02
7 Ground Tank 500 Liter unit 1.00 0.79 85.00 15.00 100.00 0.79
8 Watern Torn 500 Liter unit 1.00 0.79 85.00 15.00 100.00 0.79
9 Mesin Pompa unit 1.00 0.87 85.00 15.00 100.00 0.87

XIII PEKERJAAN INSTALASI LISTRIK 3.03 3.03


1 Instalasi Stop Kontak / Lampu (TANPA LAMPU) ttk 28.00 1.77 70.00 30.00 100.00 1.77
2 Instalasi Stop Kontak AC ttk 2.00 0.14 70.00 30.00 100.00 0.14
3 Instalasi Stop Kontak Pompa ttk 1.00 0.06 70.00 30.00 100.00 0.06
4 Panel MCB + Box MCB set 1.00 0.27 70.00 30.00 100.00 0.27
5 Saklar Seri bh 6.00 0.07 70.00 30.00 100.00 0.07
6 Saklar Tunggal bh 2.00 0.01 70.00 30.00 100.00 0.01
7 Saklar Hotel bh 2.00 0.09 70.00 30.00 100.00 0.09
8 Kabel Toefoer NYY 3x6 mm m' 17.00 0.45 80.00 20.00 100.00 0.45
9 Arde / Pentahanan ttk 1.00 0.17 70.00 30.00 100.00 0.17
PRESTASI
BOBOT Bobot Prestasi
NO. URAIAN PEKERJAAN SAT QUANTITY Lalu Sekarang Jumlah
(%) (%) (%) (%) (%)
XIV PEKERJAAN KM / WC BAWAH 1.42 1.42
1 Lantai Keramik ASIA Tile uk. 20x20 m2 1.99 0.07 80.00 20.00 100.00 0.07
2 Dinding Keramik ASIA Tile uk. 20x25 m2 10.89 0.49 80.00 20.00 100.00 0.49
3 Closet Duduk Type CW 637 J / SW 637 J ex. TOTO bh 1.00 0.63 100.00 100.00 0.63
4 Jet Washer Type TB19 CSMCR ex. TOTO bh 1.00 0.04 100.00 100.00 0.04
5 Shower Jet Type TX 423 S ex. TOTO bh 1.00 0.06 100.00 100.00 0.06
6 Soap Holder S6N bh 1.00 0.02 100.00 100.00 0.02
7 Floor Drain TX 1EAV1 bh 1.00 0.02 100.00 100.00 0.02
8 Waterproofing m2 3.74 0.09 80.00 20.00 100.00 0.09

XV PEKERJAAN KM / WC ATAS 1.51 1.51


1 Lantai Keramik ASIA Tile uk. 20x20 m2 2.36 0.08 80.00 20.00 100.00 0.08
2 Dinding Keramik ASIA Tile uk. 20x25 m2 11.93 0.54 80.00 20.00 100.00 0.54
3 Closet Duduk Type CW 637 J / SW 637 J ex. TOTO bh 1.00 0.63 100.00 100.00 0.63
4 Jet Washer Type TB19 CSMCR ex. TOTO bh 1.00 0.04 100.00 100.00 0.04
5 Shower Jet Type TX 423 S ex. TOTO bh 1.00 0.06 100.00 100.00 0.06
6 Soap Holder ex. ONDA bh 1.00 0.02 100.00 100.00 0.02
7 Floor Drain bh 1.00 0.04 100.00 100.00 0.04
8 Waterproofing m2 4.23 0.10 90.00 10.00 100.00 0.10

XVI PEKERJAAN MEJA DAPUR 0.40 0.40


1 Meja Beton finish ASIA Tile ukuran 20x25 m' 2.28 0.11 80.00 20.00 100.00 0.11
2 Dinding Keramik ASIA Tile uk. 20x25 m2 1.28 0.06 80.00 20.00 100.00 0.06
3 Kitchen Zink Sandimas DD 408 bh 1.00 0.17 70.00 30.00 100.00 0.17
4 Kran Kitchen type V 634 T ex. ONDA bh 1.00 0.04 100.00 100.00 0.04
5 Tali Air 1x1 cm m' 3.48 0.02 30.00 70.00 100.00 0.02

XVII PEKERJAAN CAT 3.95 3.95


1 Cat Dinding Interior ex. Mowilex m2 187.87 1.19 70.00 30.00 100.00 1.19
2 Cat Dinding Eskterior ex. Mowilex m2 185.50 1.59 80.00 20.00 100.00 1.59
3 Cat Plafond Interior ex. Mowilex m2 48.50 0.30 80.00 20.00 100.00 0.30
4 Cat Plafond Eksterior ex. Mowilex m2 21.70 0.18 80.00 20.00 100.00 0.18
5 Cat Plint Lantai Ftalit Kansai m' 57.00 0.67 60.00 40.00 100.00 0.67
6 Cat Listplank Ftalit Kansai m2 2.31 0.02 90.00 10.00 100.00 0.02

XVIII PEK. FINISHING TANGGA 1.30 1.30


Hand Railing Tangga Kayu Kamper Samarinda uk. 6/8 cm +
1 m' 5.00 0.13 80.00 20.00 100.00 0.13
Plat Dudukan
2 Lantai ASIATile uk. 40x40 cm m2 6.70 0.30 90.00 10.00 100.00 0.30
3 Stepnosing Tangga m' 13.60 0.75 80.00 20.00 100.00 0.75
4 Plint Tali Air m' 15.16 0.12 80.00 20.00 100.00 0.12

XIX PEK. BESI 2.10 2.10


1 Railing Tangga Besi Hollow 40x40 mm + 20x20 mm m' 3.50 2.10 80.00 20.00 100.00 2.10

XX PEK. LAIN - LAIN 1.55 1.55


1 Gambar As Built Drawing Ls 1.00 1.19 80.00 20.00 100.00 1.19
2 Tutup Ground Tank Unit 1.00 0.13 80.00 20.00 100.00 0.13
3 Tutup Bak PAM Unit 1.00 0.11 80.00 20.00 100.00 0.11
4 Bak PAM Unit 1.00 0.05 80.00 20.00 100.00 0.05
5 Pas. Bata Dudukan Torn m2 1.00 0.07 80.00 20.00 100.00 0.07

CATATAN : JUMLAH BOBOT PRESTASI 100.00


BOBOT PRESTASI YANG LALU 84.93
BOBOT PRESTASI SEKARANG 15.07

Jakarta, 28 Januari 2023

Disetujui, Diajukan Oleh,


Head Office Kontraktor Pelaksana
PT. Nusa Kirana R.E PT. Sanjaya Putra Utama

Aditiya Yongki Gunawan


GM Property Development & Project Direktur