LC0166-LUX-MST-EL-005-Central Battery Based Emergency Lighting System R01
LC0166-LUX-MST-EL-005-Central Battery Based Emergency Lighting System R01
Comments :
D Rejected
ENGINEER’S SIGNATURE
EX2020-LP/PM/02
Submittal Review Notes
Ver: 01; Rev: 0A; August 2014
P.O. Box 26739 Submittal No.: EX2020-LP-MS-22 Date: 12-Feb-20
Dubai, UAE.
Revision No.: 00 File Note:
Tel: +971 4 388 1616
Fax: +971 4 380 6161 Title/Description: MS for Central Battery Based Emergency Lighting System
Project Name: Luxembourg Pavilion Project Number: P250251
Contract No. Contractor’s Name: NŰSSLI Adunic AG
TYPE OF SUBMITTALS
Shop Drawings Work Inspection Request Material Inspection Request
CONTRACTOR
4. Risk assessment was not reviewed and approved by contractor HSE & PM prior submitting for engineers
review.
WME Electrical Comments:
1. Refer comments noted on the submittal and comply.
2. Installation:
- Check list for Installation of CBS shall be provided.
- Sub circuit monitoring shall be explained. (MCB level monitoring to be provided)
- Work station installation and graphics shall be explained.
3. Testing and Commissioning:
- Step by step procedure of testing and commissioning shall be clearly explained.
4. Details shall include but not limited to:
- Normal operation of light.
- Lux level calculation.
- 3 Hrs discharge test.
- Luminarie and Battery failure function.
- Sub circuit monitoring.
- Transfer to battery source and retransfer to normal function
5. Check list for T&C of CBS shall be provided.
6. Test report format for lux level and discharge test shall be provided.
Date Received Date Returned:
DESIGN CONSULTANT SIGNATURE
For and Behalf of
WME Consultants
Page 1 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
TABLE OF CONTENT
3 DEFINITIONS 3
5 RESPONSIBLE PERSON/S 4
8 INSTALLATION PROCEDURE 5
8 INSPECTION PLAN 11
10 RECORDS 11
11. ATTACHMENT 12
Page 2 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
This Method Statement defines the step‐by‐step procedure for installation, testing & commissioning
of Central Battery System. This method statement should ensure that the installation, testing &
commissioning work is executed safely and in accordance with the contract specification &
requirements. This method statement aims to ensure that the work quality assurance and quality
control activities are conducted in a systematic manner, works are inspected and conformance is
verified and documented.
This method statement relates to the Testing & Commissioning of Central Battery
System for the Luxembourg Pavilion Project, EXPO 2020.
3. DEFINITIONS
IR : Inspection Request
MS : Method Statement
Page 3 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
Ensure that all required testing equipment’s are calibrated and in good working condition
before being used.
5. RESPONSIBLE PERSON/S:
5.1.2.Make sure all submittals are given to Main Contractor, consultant & Authority for MEP
Works as per scheduled date.
5.1.3.Make sure that all the MEP works follow the progress of civil works at site and no
complaints arise from Main Contractor/Client/Consultant as per program of work.
5.1.4.Responsible for all permits concerned, control measures, plant and labour needed to
execute the works according to the scope/program are available and workable.
5.1.5.To Co‐ordinate with project & site engineer, QA/QC engineer, safety officer, foreman
for a safe and proper execution of the works.
5.1.6.To guide specific attention to all safety measures in coordination with safety officer.
5.2.1.Follow‐up with suppliers for receipt of materials at Stores/Site as per LPO’s issued.
Page 4 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
5.2.2.Carry out the work at site & monitor manpower’s work as per approved shop drawing
and as per specifications to the quality required, for approval by the Main
Contractor/Consultant.
5.2.3.Allocate labor for various activities in consultation with the Foreman as per
requirements at site on a daily basis.
5.2.4.Handle inspection for daily activities and get approval on the same.
5.2.5.Coordination to all site team and to the project coordinator for any arises issues on
site.
5.3.2.Handle inspection for daily activities and get approval on the same from consultant.
5.3.3.Monitoring site condition and ensure that installation is done as per approved material
submittal, approved shop drawing, approved method statement and consultant
requirements.
5.4.1 Will be responsible for the day to day activities on site, for Emergency Light Central
Battery System Commissioning, report preparation and demonstration of system
commissioning. The technician is a Sibca engineer who are the specialist manufacturers.
6.1 Testing & commissioning to be carried out based on approved drawings and shall be
coordinated well before testing & commissioning to other services.
Page 5 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
6.2 M/s Lunar shall give adequate notice to Contractor of the dates for testing &
commissioning so that, if necessary, Project Manager may present to witness the
testing.
7 INSTALLATION PROCEDURE:
7.1.3 Care shall be taken to prevent damage and distortion to the materials
during lifting and transportation.
7.1.4 All the Materials must be handled at every point of loading and
unloading by approved lifting tackle.
7.1.5 The QA/QC's contractor Engineer will inspect and ensure the delivered
materials are as per approved materials submittal.
7.2.2 All relevant approved shop drawings are available at site for the
execution of job.
7.2.3 The work area shall be inspected by safety to commence the installation
work
7.2.4 Ensure that the work area is ready and safe to start the installation of
Central battery based Emergency lighting system.
7.2.5 Ensure that all required material are available at site and are of
approved specifications, submittals and as per the requirement of the
area shop drawings (i.e. Make, Size, Model/Type etc.)
7.2.6 Ensure the materials are stored correct and there are no marks of
damage or deformity of any kind before issuing the material from site
store. All material and accessories shall also be free of dust, scale or oil.
7.2.7 Ensure that prior to installation that all building surfaces are ready. Civil
work is completed and is in a suitable clean and dry condition. Any
Page 6 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
7.3.2 Cables shall be installed through embedded PVC conduits and any
missing additional point cabling shall be installed direct to the soffit slab
or wall surface
7.3.3 Use cable manufacturers cable cleats, clips, glands and strands.
7.3.4 Prior to pulling of cables, check and ensure there are no sharp edges in
the trunking to prevent damage while pulling cables.
7.3.5 Ensure before cable pulling (Size and Type) as per approved shop
drawings/Approved Material submittal.
7.3.6 Ensure the identification for in‐cable & out‐cable for addressable
purpose during testing & commissioning stage.
7.3.7 Prior for termination wiring should be tested for stray voltage, short
circuits and ground faults prior for connection to device.
7.3.9 Where trunking is used ensure that required space capacity is available.
7.4.1 Check the type & size of wire used is as per specification and approved
Material Submittal and civil defense requirements.
7.4.2 Install luminaires as per latest approved shop drawing & manufactures
recommendation.
7.4.3 Ensure that conduits used for such cabling should not be used by other
system.
Page 7 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
7.4.4 Install the luminaires based on approved height & location shown on
approved shop drawing.
7.4.7 Proper care shall be taken in defining type of system i.e., maintained,
non‐ maintained and switched maintained.
7.4.8 After installation cover the luminaires with plastic, protection from dirt
moisture… etc.
7.5.1 Mark the fixing position of the Central battery system as per approved
shop drawing and in coordination with other services.
7.5.2 Check the location where the panel to be erected is clean & in
acceptable condition. The floor should be horizontally leveled.
7.5.3 Shift the particular Central battery system cabinet to the work place,
packing will be removed at the position of installation.
7.5.4 Install Central Battery Panel accessories & Central Monitoring unit based
on the latest approved shop drawing & manufacturer recommendation.
7.5.5 The name plate will be checked against equipment data sheet to
confirm conformity with the approval.
7.5.6 Fix the system with proper metal plugs and bolts. Ensure the installation
is straight and leveled.
7.5.9 Ensure the incoming terminals and interconnecting terminals are free
from dust and damage.
7.5.10 Cables shall be installed through embedded PVC conduits and any
missing additional point cabling shall be installed direct to the soffit slab
or wall surface.
Page 8 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
7.5.14 Install Central Battery Panel .Sub Panel & Central Monitoring unit based
on the latest approved drawing & manufacturer recommendation.
7.5.15 Use appropriate sixe of bolts/anchors for fixing the Central Battery Panel
Make sure it is level & plumb
7.5.16 Ensure the all circuits identified/labelled and marked in the panel
7.5.17 Check the type & size of wire used is correct as per specification,
approved material submittal & local civil defense requirement
7.5.20 Terminate all the circuits to its respective breakers with proper ferrule
identification.
7.5.23 Clean the central battery cabinets after dressing with blower to blow out
all the small particles dust after the termination work.
7.5.25 Place the approved schematic drawing copy inside the central battery
cabinet door
7.5.27 Check all the cable installation from emergency DB to emergency SMDB
have been completed (normal & emergency).
8.1.2 Visually check Control Panels to ensure that all equipment is installed in
line with Approved Construction drawings, Approved Material
Page 9 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
8.2.1 The following checks will be made prior to powering up the system.
8.2.3 Disconnect Lamps, Address modules, Central Battery Panels and from
power circuit and connect 500VDC Megger Tester between Phase to
Neutral, Neutral to Ground as well as Phase to Ground. The Values of
resistance measured must be in excess of 1000 Mega Ohms. This has to
be done by the JV and the necessary Megger & Continuity Reports have
to be filled in by them & submitted to specialist for review. These
reports then form part of the Testing & Commissioning document.
8.2.4 Address each individual emergency light and exit fitting as in layout
drawings.
8.2.5 Carry out local testing of the cable with fixtures with an ELCB associated
with it in order to cross verify the status prior to its connection to CBS
Panel.
Testing Procedure:
The following checks will be made prior to powering up the system
by the INOTEC/SIBCA engineers who are the specialist manufacturers.
The Emergency Lighting System power cabling has to be mandatory
Meggered and Continuity Checked & rectified of all Open/Short/Earth
Faults prior to commencement of connection & powering up of the
circuits
Disconnect Lamps, Address modules, Central Battery & Substation
Panels & PC from power circuit and connect 500VDC Megger Tester
between Phase to Neutral, Neutral to Ground as well as Phase to
Ground. The Values of resistance measured must be in excess of 1000
Mega Ohms. This has to be done by the EFECO and the necessary
Megger & Continuity Reports have to be filled in by them & submitted
to SIBCA for review. These reports then form part of the Testing &
Commissioning document.
Address each individual emergency light and exit fitting as in layout
drawings.
Page 10 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
Page 11 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
8.3.11 Ensure all components connected to the control panel report back full
status and are fault free
8.4.1 After successful commissioning the results will be recorded on the test
sheets contained within respective section of this document.
9 INSPECTION PLAN:
Page 12 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
General Requirements:
10.1.2 All working area shall be end circled by warning tapes and warning sign
boards in place before commencement of works where practicable
10.1.3 Access and exit routes to be obstructed and labeled and known to all
employees at site.
10.1.4 Risk assessment will be established detailing the hazards involved and
actions that will be taken to reduce those hazards
11 RECORDS:
12 ATTACHMENTS
Page 13 of 14
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
PANEL NAME:
CPS / CPUS
LOCATION:
PANEL REFERENCE
2.SIMULATION CHECKS
a) Simulate Mains Failure by switching off the Incoming Supply of the CPS/CPUS
b) Check operation of the CPS/CPUS
c)Check operation of all related field devices for correct operation
Name
Signature
Date
Lunar Electro Document
Method Statement Ref:LC0166‐LUX‐
MST‐EL‐005
Quality Assurance
PANEL NAME:
CPS / CPUS
LOCATION:
PANEL REFERENCE ADDRESS
REFERENCE DRAWING:
2.CONTINUITY/INSULATION MEASUREMENT
a)Carry out continuity test of all panel wiring/cabling
b)Dedicated mains supply installed: Yes/No
c)All fittings installed: Yes/No
d)All fittings addressed correctly: Yes/No
e)Wiring fault free: Yes/No
Name
Signature
Date
PROJECT : DUB/0317 - LUXEMBOURG PAVILION - C50 @ EXPO 2020
CONSULTANT : M/s WME ENGINEERING CONSULTANTS.
GENERAL CONTRACTOR : M/s NUSSLI SATAL PROJECT MANAGEMENT LLC.
LOCAL CONTRACTOR : M/s AL AHMADIAH CONTRACTING & TRADING LLC.
MEP CONTRACTOR : M/s. LUNAR ELECTRO MECHANICAL CONTRACTING LLC
1 Preliminary Checks:
6 Operational Testing:
15 Remarks
Project Eng. - Sub Cont MEP CONTRACTOR M/s. MAIN CONTRACTOR M/s. CONSULTANT
SNO CIRCUIT DETAILS LOCATION LUX LEVEL LIGHT FITTING TYPE REMARKS
REMARKS:
BATTERY NO VOLTAGE BEFORE CHARGING VOLTAGE AFTER FULL CHARGE STARTING VOLTAGE AFTER 1 HOUR AFTER 2 HOUR AFTER 3 HOUR
REMARKS:
Ensure that all material submittals are AFE/ Project Specification, contract
1 Compliance to Specification EX I R R +H Material Submittal
approved QAQC Engineer drawings.
Commissioning Method
Statement and Specification,
Emergency modules installed at
Mock-up Inspection for Installation of DEWA Regulations, Civil
correct & accessible location and
4 cenral battery and emergency lighting AFE /QAQC Engineer defence requirement, EX I R I+H Checklist
other parameters as per
system Relevant standard and
specification & Checklist
Manufacturers
Recommendations
Commissioning Method
Statement and Specification,
Duration test for rated time, light
Final Inspection for Installation of DEWA Regulations, Civil
output and other parameters as
5 cenral battery and emergency lighting AFE /QAQC Engineer defence requirement, EX I R I+H Checklist
per Project and System
system Relevant standard and
Specification & Checklist
Manufacturers
Recommendations
LEGEND
EX Execution M Monitoring H Holdpoint
R Review Documents only Progressive S Surveillance Inspection
Ref: REV:01
SEVERITY RATING: MATRIX
People/Equipment/Production Please Note
If the severity rating lies between 1 to 9, then corrective actions
needs to be taken by concerned persons with documentary
Health Safety loss & Environmental Impact evidence provided
Probability
Priority OH&S Environmental 1 2 3 4 5
Slight injury (No lost
1 to 3 time). First Aid Slight Incident
Very Low - VL Case. 1 1 2 3 4 5
4-9 Acceptable Low - L Minor injury / Illness Minor Incident 2 2 4 6 8 10
Severity
Moderate injury / Moderate
10-16 > 4 weeks Medium - M Illness Incident 3 3 6 9 12 15
Serious injury / Serious
20-25 within 1 month High - H illness Incident 4 4 8 12 16 20
>25 Immediate (within 1 Fatal / Permanent
Major Incident
week) Very High - VH disability 5 5 10 15 20 25
Working group Designation Certain
May Very or
Unlikely Happen Likely Likely Imminent