Professional Documents
Culture Documents
Fire Alarm System MS (R1)
Fire Alarm System MS (R1)
Fire Alarm System MS (R1)
METHOD STATEMENT
FOR
CONTENTS
4.0 METHODOLOGY
6.0 APPENDICES
RISK ASSESSMENTS
ITP
RELATED CHECKLISTS
Rev.00
Lunar Electro
Method Statement
Quality Assurance 3 of 7
This method of statement specifies the detailed requirements and procedures for the
testing and commissioning of Fire Alarm System at LUXEMBOURG PAVILION @ EXPO 2020
a. Project Manager shall be responsible for the overall implementation of the project quality
plan and Testing and Commissioning
b. Commissioning Engineer:
The commissioning engineer of M/s Sibca Electronics and Lunar engineer are jointly
responsible for the correct testing and commissioning to ensure that all test sheets are
properly executed and documented. The system is commissioned as per the
authority/project requirements.
Safety Advisor:
The safety advisor is to monitor the work activities to ensure works are carried out
safely and in accordance with the approved method statements and risk assessments,
to stop any unsafe activities and to advise how to correct unsafe acts or conditions.
All the safety precautions shall be followed as per the Client, consultant and main
contractor requirement.
Operatives trained with safe procedure for testing the fire alarm devices and accessories.
Mandatory PPE (Safety shoes, High visibility vest, hand gloves, eye protection and hard
hat) need to wear at all time.
All operatives and staff to attend the site-specific safety induction to ensure all site rules
are communicated and understood.
Method statements to be in place and approved, all operatives and staff involved with the
activities within this method statement are to be fully briefed on the sequence and safe
systems of work.
Work at height
Only trained person to Erect, Modify and dismantle the Scaffold/ Podium Scaffolding.
Safe working procedures of the Mobile scaffold/ Podium/ladder to be followed. Safety on
work at height has been addressed in the Risk Assessment. All the mobile tower scaffold
erectors will be third party trained.
Inspection and Tag System need to be ensured while working on scaffolding.
Rev.00
Lunar Electro
Method Statement
Quality Assurance 4 of 7
Scaffolding/ Podium shall be inspected and tagged by trained and certified person re-
inspected and re-tagged as per the MS.
Mandatory PPE Helmet, glove, safety shoe, high viz vest must wear at all the time along
with task specific PPE. Specially working at height.
4.0 Methodology
Pre-commissioning:
Testing Procedure:
Continuity:
Check the loop in and loop out continuity.
Rectify by checking the device continuity for short circuit if the required continuity is
not achieved.
Terminate to the loop in and loop out points of the Fire Alarm Control Panel.
Rev.00
Lunar Electro
Method Statement
Quality Assurance 5 of 7
Monitor module
Monitor modules are using for to interface with third party system(like FM200,Foam
System, Zone control valve/Flow switches etc)
All third party systems are activated by specialist contractor and check the interfaces
are done properly and correct messages are displayed in the panel.
Zone control valves/flow switches are operated by fire fighting vendor by activating the
drain valve and Check if the correct message is displayed on the panel display.
At the completion of the testing of all devices the number of faults in the panel will be
minimized and approach zero. Reports can be generated with panel status.
The electrical power source for the fire alarm panel will be turned off and panel tests will be
performed during battery powered stage.
Rev.00
Lunar Electro
Method Statement
Quality Assurance 6 of 7
Visually check for the LCD Display, LED status, wiring and batteries in the control
panel.
On the LCD display check for date & time, normal state display, alarm state display,
trouble state display, panel buzzer, key functions and LED display.
Battery to be sized for required backup and check the operation by disconnecting and
connecting the batteries. Check for status indication
Schedule operations, network operation, auxiliary outputs and alarm from other nodes to
be checked.
The interface with PAVA system, fans, Access door, etc. is achieved by activation of
Control relay module in Alarm condition.
The interface with Fire Fighting equipment’s, status monitoring of flow control and
supervisory valves, FM200 and Foam system status monitoring is achieved by the
monitoring module. Check if the correct message is displayed in sequence.
Sprinkler flow switches will be activated individually by opening the test valve at the
zone control valve station and running water to drain.
Check if the correct message is displayed on the panel display.
Prerequisites:
The following items are pre-requisites to the commencement of testing and commissioning:
a. A written notice of testing and commissioning is to be issued to the Consultant / Engineer
prior to any testing activity.
b. All device loops and notification circuits, networks cables reached sleeved and marked
inside each fire alarm cabinet in order to terminate to cards. .
c. All device loops and notification circuits should be cleared from cable faults ie. There
should not be any short circuit or open circuit.
d. Proper termination to the devices and interface units and all are addressed as per
drawing/schematic
e. To ensure the loop incoming and outgoing cables are properly identified in the Panels.
f. All other faults to be rectified
h. Permanent power supply or temporary power with UPS backup to the FACP.
Rev.00
Lunar Electro
Method Statement
Quality Assurance 7 of 7
In general the following test equipment’s shall be used for checking / commissioning the
system mentioned above.
General Electrical tools
Calibrated Digital multi-meter
Smoke tester(aerosol)
Heat tester.
Db meter
5.0 APPENDICES
RISK ASSESSMENT
ITP
RELATED CHECKLISTS
Rev.00