Professional Documents
Culture Documents
Introduction To Cost Risk Analysis Risk Mitigation
Introduction To Cost Risk Analysis Risk Mitigation
2
Overruns are a Reality!
+200%
178%
Central Artery / Tunnel (Boston)
141%
+100% 96%
(MWD of So. Calif.)
L.A. Metro Red Line
Orig. Est. 1311 1970 4007 109 1200 19 8000 250 2400 310 9210 123 1560 362 153 110 35 360 55 1500 45
(in $mil.)
Current Est.
or Actual (in 1311 2190 4502 125 1500 25 11200 375 3600 500 15350 215 2750 656 300 274 93 1000 166 5000 163
$mil.)
MITIGATE RISKS
Invest in continuous and transparent QA/QC of
actual cost estimating process
Traditional vs. Risk-Based Estimation
5%
Design
Uncertainty and Project Delivery
Actual
Cost
10
CRA~VE Analytical Process
11
Step 1: Baseline Risk Assessment
Review Baseline Schedule & Cost
Costs to date
Flowchart: I-5 Grand Mound To Maytown Widening
0 Design
Approval North End North End
Design 4 (Maytown) (Maytown)
Documentation/ Bridge Bridge
PFA 1 (12 months) STAGE 1 STAGE 2 21
16 (10 months) (7 months)
Access Environmental Permits
Evaluation 2 5 (12 months)
(9 months)
North End (Maytown)
Road Median Widening North End North End
Environmental R/W Acquisition 17 (6 months) (Maytown) (Maytown)
Documentation 3 6 (12 months) Road Road
(14 months) West Side and Bridge
Widening STAGE 3
22 26
Wetland Mitigation (3 months) (7 months)
7 (8 months)
R/W SRA Utilities
Certification 23 (6 months)
10
Hydraulics Report
8 (12 months)
AD
15 Scatter Creek Area Scatter Creek Area Final
STAGE 1 Scatter Creek Area STAGE 3 Overlay
Geotechnical 30 (7 months) STAGE 2 32 (6 months) 33
9 (18 months) 31 (6 months) (3 months)
Agency Agreements
13 (9 months) Replace 12/118 & Replace 12/118 &
Widen 12/117 STAGE 1 Widen 12/117 STAGE 2
20 (8 months) 20b (8 months)
Other Agreements
14 (6 months)
3/06 9/06 9/07 1/08 4/08 9/08 1/09 7/09 1/10 4/10
Note: Not to Scale
(1) Assume single design/bid/build contract FISH WINDOWS
(2) Construction closure periods: Fish windows for activities (?) Winter weather shutdown (?) *Accelerated Process
12
Step 1: Baseline Risk Assessment
Integrating CRA and VE
Step 1: Baseline Risk Assessment
Risk Categories
¾ Budget Risk:
• Risk that budget elements will deviate from the estimate
• Examples: material price escalation, limited competition, labor
shortage
¾ Event Risk:
• Risk of internal or external events that force the project team to
work beyond the estimate just to meet the Project Scope and
Statement of Work.
• Examples: Environmental challenges, unforeseen subsurface
conditions, extreme weather, public pressure, public resistance
¾ Scope Risk:
• Risk of significant changes to project scope due to external
pressures.
• Examples: stakeholder pressure for a grander facility than the
budget accommodates, additions to meet permitting agency
demands
Step 1: Baseline Risk Assessment
Deriving Project-Specific Budget Escalation
Project-Specific
Escalation
240
Forecast ->
220 Median
Lower 10%
180
160
140
120
100
80
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
Year
15
Step 1: Baseline Risk Assessment
Examples of Event and Scope Risks
¾ Environmental Risks
CRAVE™
¾Hazmat
Process: Step 1
¾
Identifying
Utilities Risks the risks by category
¾ Drainage Risks
¾ Traffic Management
¾ Market Conditions Risks
¾ Procurement Risks
¾ Right of Way Risks
¾ Performance Standards
¾ Financial Risks
¾ Natural Disasters
¾ Etc.
16
Step 1: Baseline Risk Assessment
Risk Analysis Workshop - Consensus Based Forum
Cost Schedule
Delay of NEPA Increase Delay by 12
Process
33% $2M months
Incremental Incremental
Increase Cost Schedule
Delay
Overall Effect on
the
Project Cost
18
Step 1: Baseline Risk Assessment
Establishing Ranges for All Key Input Variables
80% Confidence
0.25
Interval
PROBABILITY DENSITY
0.2
0.15
0.1
0.05
0
0 2 4 6 8 10 12 14 16
Value of Time – Auto Driver or Passenger, 4/hour
Step 1: Baseline Risk Assessment
Identify, Quantify and Mitigate…
Step 1: Baseline Risk Assessment
Risk Register: Risk Identification
Step 1: Baseline Risk Assessment
Risk Register: Risk Quantification
Step 1: Baseline Risk Assessment
Risk Register: Risk Mitigation
Step 1: Baseline Risk Assessment
Integrating Individual Risks
24
Step 1: Baseline Risk Assessment
Risk-Adjusted Schedule
RISK-ADJUSTED CONSTRUCTION START & END DATES
UNDER DESIGN-BID-BUILD
May-2011 Oct-2014
Sep-2010 May-2014
Probability of Not Exceeding
Jun-2010 Sep-2013
May-2010 Jul-2013
May-2010 Jun-2013
May-2010 May-2013
May-2010 Oct-2012
0% May-2010 Aug-2012
Jan-2009 Jul-2009 Jan-2010 Jul-2010 Jan-2011 Jul-2011 Jan-2012 Jul-2012 Jan-2013 Jul-2013 Jan-2014 Jul-2014 Jan-2015
Baseline Construction Start RA Construction Start Date Baseline Construction End RA Construction End Date
25
Step 1: Baseline Risk Assessment
Under Different Procurement Alternatives
RISK-ADJUSTED CONSTRUCTION START & END DATES
UNDER ALTERNATIVE DELIVERY
May-2010 Aug-2013
May-2010 Jul-2013
Sep-2009 May-2013
Jun-2009 Sep-2012
May-2009 Aug-2012
May-2009 Jun-2012
May-2009 May-2012
0% May-2009 Aug-2011
Jan-2009 Jul-2009 Jan-2010 Jul-2010 Jan-2011 Jul-2011 Jan-2012 Jul-2012 Jan-2013 Jul-2013 Jan-2014 Jul-2014 Jan-2015
Baseline Construction Start RA Construction Start Date Baseline Construction End RA Construction End Date
26
Step 1: Baseline Risk Assessment
Risk-Adjusted Cost
Baseline Construction Cost, Non-Escalated Baseline Construction Cost, Escalated Baseline Project Costs (excluding iCap, Con & Equip)
Project Cost With Budget Risks, Escalated Project Cost With ALL Risks, Escalated
Cost ($Millions)
27
Step 1: Baseline Risk Assessment
Prioritization of Risks
Step 2: VE & Risk Response
Focused Risk Responses
Project Review
Assessment
• High cost areas
• Generate ideas
Screening
• Evaluate ideas
• Quantify Ideas
Recommendations
Step 2: VE & Risk Response
Developing Risk Response Strategies
Risk ID: C3 - E
Risk Name: Defective work results in schedule delay and additional costs
Activity Impacted: 27
Type of Risk: Schedule
Expected Value Total Risk Impact ($M): $3.40
Panelist Comments from Initial Risk Workshop: Would require a change order, may extend the length of
the contract.
Risk Response Strategy (select one):□ Avoid □ Transfer x Mitigate □ Accept
Notes on Strategy:
•Require schedule recovery whenever the Contractor’s CPM begins to fall behind
•Use incentive/disincentive clause to encourage contract to be completed on time
•Consider A+B bidding for these projects
•Add additional inspection
Cost to Mitigate ($M): ____________$1.0_to $2.0________
Impact
Risk Profile Prob.
Low Median High
Hz4: May need to engage with Water Board and/or DTSC (15, 18) $2.4 $4.0
D4: Delay in bridge site submittal holds up structures design start (9) $1.9 $3.8
C3: Defective work results in schedule delay and additional costs (27) $0.2 $2.5
32
Step 3: Risk Analysis on Response Strategies
Quantifying Mitigation Strategies at the Project Level
Mitigation
Value
33
Step 3: Risk Analysis on Response Strategies
Assessment of Alternatives
100%
60%
50%
40%
30%
20%
10%
0%
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00
35
Step 4: Tracking, Monitoring and Control
Informed Risk Allocation
MTO
Contractors
do not take
risks
They Price It
36
P3: Looking for Win-Win
38
HDR and Risk Assessment
¾ Conducted 500+ economic and financial studies in past 20
years
¾ Trustedby bond issuers and insurers; federal,
provincial/state and local agencies
¾ Risk-basedmodels for Transport Canada, FTA, FHWA, FRA,
FAA, DOJ, and DHS that have been submitted to
congressional committees, GAO and OMB
¾ Risk-based cost benefit analysis models for the Port
Authority of NY / NJ, Metrolinx, Move Ontario 2020, City of
London, City of Winnipeg, Vancouver to assess infrastructure
investments
HDR and Cost Risk Assessment
¾ Conducted cost risk analysis for various infrastructure
investment including bridges, highways, rail alignments,
ports, airports, tunnels, water treatment facilities, and
convention centers
¾ Led risk analysis studies for transportation agencies, such as
Caltrans, WSDOT, MNDOT, WISDOT, FDOT, UDOT,
TXDOT, ADOT and the FTA including Lower Manhattan
Recovery Office in New York City
¾ Conducted program cost risk analysis for a $35 billion
program by New York Dept. of Environmental Protection.
¾ Riskanalysis for over $10 billion rebuild program in New
Orleans on behalf of the US Army Corps of Engineers
Questions?
100% $281.5
$255.1
90% $247.7
Baseline Baseline
Non-Escalated Escalated $242.0
80% $236.9
$150.3 $172.8 $232.7
70%
$228.9
$226.1
60% BID PRICE
$223.3
02/07 ($219 M)
50% $220.5
$217.5
40% $214.9
$212.0
30% $209.3
$206.2
20%
$202.7
$199.6
10%
$195.9
0% $192.3
$186.9
$170.9
$135 $155 $175 $195 $215 $235 $255 $275 $295 $315
$90,000,000
Construction
ROW
$80,000.000
Project Development
$70,000,000
$60,000,000
$50,000,000
$40,000,000
$30,000,000
$20,000,000
$10,000,000
$0
Jan 05 Jul 05 Jan 06 Jul 06 Jan 07 Jul 07 Jan 08 Jul 08 Jan 09 Jul 09 Jan 10 Jul 10 Jan 11 Jul 11
35
Examples of Risk Mitigation
Note: This chart is based solely on the risk register: for each event risk, the expected cost
impact is calculated as the product of the probability of occurrence times the cost estimate,
both provided by the panelists.