PROJECT: FIRE SUPPRESSION SYSTEM SITE NO.

: SINGITA GRUMET

COMMISSIONING CHECK SHEET FOR THE SYSTEM Sheet No.1

EQUIPMENT NO. : ETN YN 80-26 1-45 D65 10-7


SERIAL NO. : DATE :
LOCATION : COMMISSIONED ON :

Checked
ITEM POINTS TO BE CHECKED by REMARKS
1 Water supply pipeline tested.
2 Electric Driven Pump Controller properly installed and
working.
3 Supply voltage matches with motor rating.
4 Diesel Engine Pump Controller properly installed and
working
5 Control wiring is properly done.
6 Mounting arrangement for proper operation to avoid causing
vibrations
7 Pump motor alignment properly done.
8 Pressure gauges properly working.
9 Jockey Pump Motor Power properly connected.
10 Jockey Pump hydraulics properly working
11 Non return valve installed.
12 Overload setting and fuse rating.

THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT
SPECIFICATIONS.

CHECKED BY CONTRACTOR: _____________________


Signature

WITNESSED BY CLIENT: ______________________


Signature

WITNESSED / ACCEPTED BY CONSULTANT: ____________________


Signature