Professional Documents
Culture Documents
ICC Bhoomi Vishramyog JSA
ICC Bhoomi Vishramyog JSA
Authorized Signatory
Annexure – 1 Job Safety Analysis OHS-11/R-01:OHS – 11 F – 01 - JSA
Job Task
Job : Construction Of Substation At Bhoomi Vishramyog Don Bosco Borivali West
S. No. Job Steps in Sequence Potential Hazard Control Measures Accountability
JSA Done By (Team) :
Department performing Task Transmission
S. No. Name Department
Equipment / Tools Required Dumper Y 5 Mr. Dhanjay Patil Site In Charge (ICC)
D Shackle/D
Y 7 Mr. Suresh Ambre AEML projects
Clamp
Safety Shoe Y
Safety Helmet Y
Safety Jacket Y
Safety Goggle Y
PPE Required
Hand Gloves Y
Face Mask Y
JSA Approved By:
Name Date Signature
Contractor / Working Agency & M/S Industria lcoating co
Order No. S.SERV/ MSC/ 296255 Mr. Pradip Sarode
1.5Apppropriate PPE, such as Safety Helmet , safety shoes, glouse, masks, earplug, full Contractor's Project Coordinator/ Contractor's Project Manager/
1)Physical Hazard due to lack of awareness & engaging incompetent body safety harness shall be available (part of standard PPE's ) Site supervisor will be Contractor's Safety officer/ AEML Site-In-Charge
Persons present at sitedurng all activity
4.1 All workers shall use Nose/Face Mask during the work and maintain practice as per Contractor's Project Coordinator/ Contractor's Project Manager/
Contractor's Safety officer/ AEML Site-In-Charge
SOP of Covid 19
Contractor's Project Coordinator/ Contractor's Project Manager/
Contractor's Safety officer/ AEML Site-In-Charge
4.2 Consuming & spitting gutka, pan, tobaco,on site shall not be allowed
4.4 Screening of persons of temparatures,at the entry of site by using infra red non Contractor's Project Coordinator/ Contractor's Project Manager/
Contractor's Safety officer/ AEML Site-In-Charge
cntact Thermo Meter (Confirming to CE norms )
4.5 Employees having fever running nose, short of breath shall not be alowed to enter Contractor's Project Coordinator/ Contractor's Project Manager/
Contractor's Safety officer/ AEML Site-In-Charge
site
Contractor's Project Coordinator/ Contractor's Project Manager/
Contractor's Safety officer/ AEML Site-In-Charge
1.1 First Aid Box shall be available with medicine,
1.3 All employees shall be explained the provision of First Aid, assembly point and Contractor's Project Coordinator/ Contractor's Project Manager/
2 Emergency Response management
Contractor's Safety officer/ AEML Site-In-Charge
emergency contact number
Contractor's Project Coordinator/ Contractor's Project Manager/
1) Health detoration & poor impact during any injury, damage
Contractor's Safety officer/ AEML Site-In-Charge
damage due to physical, biological hazards etc. 1.4 First aid to be given immediately to the needy before shifting to Hospital
1)Electrocution due to Underground power Cables & Damage to Contractor's Project Coordinator/ Contractor's Project Manager/
existing U.G. utilities. Contractor's Safety officer/ AEML Site-In-Charge
1.5 Intimation to electrical team
3.1 Materials to be handled safely with all required PPEs and using suitable tools- Contractor's Project Coordinator/ Contractor's Project Manager/
Construction material loading/ tackles. Contractor's Safety officer/ AEML Site-In-Charge
unloading (like 3. Injury due to improper handling of materials while loading-
5
Bricks,cement,excavation unloading.
Tools,sand,aggregates etc.) Contractor's Project Coordinator/ Contractor's Project Manager/
3.2 Supervision should be carried out throughout the job by competent supervisor Contractor's Safety officer/ AEML Site-In-Charge
4. Injury due to inadequate manpower during work. Contractor's Project Coordinator/ Contractor's Project Manager/
4. Sufficient manpower must be provided to carry out safe material handling activities Contractor's Safety officer/ AEML Site-In-Charge
1.Workers should be given and made wear proper PPE ,hand gloves etc.Also the job Contractor's Project Coordinator/ Contractor's Project Manager/
1.Injury to workers due not wearing PPE,handgloves etc
specific safety training should be given. Contractor's Safety officer/ AEML Site-In-Charge
6 Soling
2.Competent supervisor should be there to to tell workers how to handl soling stone Contractor's Project Coordinator/ Contractor's Project Manager/
2.Injury due to improper handling of rubble soling stone
properly and placed it in properly without getting injuried. Contractor's Safety officer/ AEML Site-In-Charge
3.Injury to workers while shifting R/F steel from steel yard to actual 3.While shifting steel saftey officer should insure proper pathway for that and also while Contractor's Project Coordinator/ Contractor's Project Manager/
positioned and while fitting the steel in as per design drwaing fitting it into position it fitter should used properly inspected tools fit for the job. Contractor's Safety officer/ AEML Site-In-Charge
1.1 Leather/ cut resistant cotton hand gloves to be used for handling sharp edged Contractor's Project Coordinator/ Contractor's Project Manager/
shoring material Contractor's Safety officer/ AEML Site-In-Charge
1.2 Side shield spectacles/googles to be used while cutting wooden materials by wood Contractor's Project Coordinator/ Contractor's Project Manager/
cutting M/c. Contractor's Safety officer/ AEML Site-In-Charge
1. Injury to workmen during improper cutting & fixing wooden
shoring material
Contractor's Project Coordinator/ Contractor's Project Manager/
1.3 Supply should be taken from 30m A ELCB equipped board. Contractor's Safety officer/ AEML Site-In-Charge
1.4 Wiring should be done safely by using cable or conduit running properly and should Contractor's Project Coordinator/ Contractor's Project Manager/
not be laid between the walkway and also running wire should not have any joints Contractor's Safety officer/ AEML Site-In-Charge
2.1 All the shoring supports, vertical props, horizontal cross bracing etc. should be Contractor's Project Coordinator/ Contractor's Project Manager/
2. Injury to workmen due to collapse of shoring/sides
strong enough to withstand required sides & soil pressure. Contractor's Safety officer/ AEML Site-In-Charge
3.1 Nails to be removed from the planks prior lifting the material & must be collected in
proper labelled bin marked for nails. Contractor's Project Coordinator/ Contractor's Project Manager/
3. Injury to workmen due to nails attached with planks, battens.
3.1 No shoring material with protruding nails to be kept at Contractor's Safety officer/ AEML Site-In-Charge
site.
Contractor's Project Coordinator/ Contractor's Project Manager/
4.1 Area barricade to restrict entry. Contractor's Safety officer/ AEML Site-In-Charge
Timber fixing & dismantling for
9
Shuttering/ shoring works Contractor's Project Coordinator/ Contractor's Project Manager/
4.2 Ensure full body safety harness anchor by each workmen. Contractor's Safety officer/ AEML Site-In-Charge
4.6 Ensure recommended PPE should be worn the worker such as safety shoes,helmet, Contractor's Project Coordinator/ Contractor's Project Manager/
hand gloves goggles & dust mask. Contractor's Safety officer/ AEML Site-In-Charge
1. Leather/ cut resistant cotton hand gloves to be used for handling sharp edged Contractor's Project Coordinator/ Contractor's Project Manager/
shoring material Contractor's Safety officer/ AEML Site-In-Charge
1.1 Side shield spectacles/googles to be used while cutting wooden materials by wood Contractor's Project Coordinator/ Contractor's Project Manager/
cutting M/c. Contractor's Safety officer/ AEML Site-In-Charge
1. Untrained worker,lack of skill awareness Personal injury
Contractor's Project Coordinator/ Contractor's Project Manager/
1.2 Supply should be taken from 30mA ELCB equipped board. Contractor's Safety officer/ AEML Site-In-Charge
1.4 Wiring should be done safely by using cable or conduit running properly and should Contractor's Project Coordinator/ Contractor's Project Manager/
not be laid between the walkway and also running wire should not have any joints Contractor's Safety officer/ AEML Site-In-Charge
3) Hazardous Material, noise, dust, Skin contanct with cement & Eye Contractor's Project Coordinator/ Contractor's Project Manager/
contact 3.2 Thoroughly wash the exposed body part with fresh water and soap after the work. Contractor's Safety officer/ AEML Site-In-Charge
4.3 Proper connection through MCB+ELCB with and ensure plug top shall be provided Contractor's Project Coordinator/ Contractor's Project Manager/
Contractor's Safety officer/ AEML Site-In-Charge
2.1 Use of Dust mask for handling dry cement. Contractor's Project Coordinator/ Contractor's Project Manager/
Contractor's Safety officer/ AEML Site-In-Charge
2) Hazardous Material, Skin contact,Eye contact & Contractor's Project Coordinator/ Contractor's Project Manager/
2.2 Throughly wash the exposed body part with fresh water and soap after the work.
Dust,Respirator hazard, Skin Irritation Contractor's Safety officer/ AEML Site-In-Charge
2.3 Use of PPE such as Safety shoes, gumboot,rubber handgloves, goggle & nose Contractor's Project Coordinator/ Contractor's Project Manager/
mask. Contractor's Safety officer/ AEML Site-In-Charge
2.1 Use of proper PPEs - welding shield,safety shoes,safety helmet,safety Contractor's Project Coordinator/ Contractor's Project Manager/
goggle,highlighter jacket Contractor's Safety officer/ AEML Site-In-Charge
2) Barricading of work area, Personal injury,Major Contractor's Project Coordinator/ Contractor's Project Manager/
2.2 Whole area under working will be properly barricaded
burns Contractor's Safety officer/ AEML Site-In-Charge
3.1 Safety shoes safety helmet safety goggle florecent jacket cotten
Contractor's Project Coordinator/ Contractor's Project Manager/
hand gloves to be used. Area under working to be properly cordoned Contractor's Safety officer/ AEML Site-In-Charge
off.
S. No. Job Steps in Sequence Potential Hazard Control Measures Accountability
3.2 Before lifting of material with lifting equipment safety supervisor Contractor's Project Coordinator/ Contractor's Project Manager/
inspect all tied slings are in proper way,then only material to be lifted. Contractor's Safety officer/ AEML Site-In-Charge
3) Lifting of materiel and moving to work location, 3.3 No person stand below the lifted load Precautaions to be taken to Contractor's Project Coordinator/ Contractor's Project Manager/
Trap hazard Fall hazard person may get injured Fatal Contractor's Safety officer/ AEML Site-In-Charge
accidents
prevent load swing. Tied with guide rope
Contractor's Project Coordinator/ Contractor's Project Manager/
3.4 Predefining all the work location for above work. Contractor's Safety officer/ AEML Site-In-Charge
3.5 While moving the material it will be kept tied at both end with Contractor's Project Coordinator/ Contractor's Project Manager/
guide rope. Contractor's Safety officer/ AEML Site-In-Charge
3.6 Proper and uniform stacking to be done on leveled surface with Contractor's Project Coordinator/ Contractor's Project Manager/
packing. Contractor's Safety officer/ AEML Site-In-Charge
3.1) Use of proper PPEs as per SPCL norms use of ELCB and proper fuse in main supply
board to be there. only SPCL approved scaffolds to be used for working at Contractor's Project Coordinator/ Contractor's Project Manager/
height,competent supervisor to be present at all time during hot work activities. Contractor's Safety officer/ AEML Site-In-Charge
3.2 Use of proper PPEs such as safety shoes,gumboots,helmet,rubber hand Contractor's Project Coordinator/ Contractor's Project Manager/
3) Liquithane Applied Potential Hazard glovs,dustmask,ear plug Hand gloves, Goggles) Contractor's Safety officer/ AEML Site-In-Charge
Hand injury / Inhalation of gas/Dust
Control/Mitigation Measures Contractor's Project Coordinator/ Contractor's Project Manager/
3.3 The hazards, risks and control measures identified for the membrane application Contractor's Safety officer/ AEML Site-In-Charge
work on building roof top have been communicated to all involved workers
3.5 Use of proper PPEs such as safety shoes,gumboots,helmet,rubber hand Contractor's Project Coordinator/ Contractor's Project Manager/
glovs,dustmask,ear plug Contractor's Safety officer/ AEML Site-In-Charge
Contractor's Project Coordinator/ Contractor's Project Manager/
3.6 Provide rope for lifting / lowering material. Contractor's Safety officer/ AEML Site-In-Charge
Contractor's Project Coordinator/ Contractor's Project Manager/
3.7 Scaffolding should be inspected by safety person before starting the work Contractor's Safety officer/ AEML Site-In-Charge