Schedule - 05-11-2022
Schedule - 05-11-2022
Schedule - 05-11-2022
(West)
Project Start Date -24-07-2022
Start Date Finish Date
Sr.No. Items/Activities Days
ST DT
A
1 Footing & Cable trench area 3 8/25/2022 8/27/2022
B Rubble Soling 2 8/13/2022 8/15/2022
C PCC M15 2 8/15/2022 8/16/2022
D Plum Concrete 1 9/4/2022 9/5/2022
E Reinforcement Steel 3 8/17/2022 8/19/2022
1 Footing & Plinth Level Column 4 8/23/2022 8/26/2022
2 Plinth Level Beam 3 9/4/2022 9/6/2022
3 Column 6 9/22/2022 9/27/2022
F Centering, Shuttering 2 8/20/2022 8/21/2022
1 Footing & Plinth Level Column 2 8/27/2022 8/28/2022
2 Plinth Beam 2 9/8/2022 9/9/2022
3 Column 4 9/18/2022 9/21/2022
G Rcc M30 Concrete 1 9/3/2022 9/3/2022
1 Footing & Plinth Level Column 1 8/29/2022 8/29/2022
2 Plinth Beam 1 9/10/2022 9/10/2022
3 Column 1 9/29/2022 9/29/2022
H Brick Work in Super Structure 4 9/1/2022 9/3/2022
C Electrical Work 10
Chart Title
Checker plate fixing work
Plinth platform framework in structural steel work
Structural steel painting work
MS structural staircase
Plinth platform framework in structural steel work
Structural steel painting work
MS structural staircase
Plinth platform framework in structural steel work
Structural steel painting work
Schedule of completion of Construction of Sub Station At Gajanan builder Jogeswari
(West)
Project Start Date -24-07-2022
Start Date Finish Date
Sr.No. Items/Activities Days
ST DT
A Exacavtion
1 Footing & Cable trench area 3 8/25/2022 8/27/2022
B Rubble Soling 2 8/13/2022 8/15/2022
C PCC M15 2 8/15/2022 8/16/2022
D Plum Concrete 1 9/4/2022 9/5/2022
E Reinforcement Steel 3 8/17/2022 8/19/2022
1 Footing & Plinth Level Column 4 8/23/2022 8/26/2022
2 Plinth Level Beam 3 9/4/2022 9/6/2022
3 Column 6 9/22/2022 9/27/2022
F Centering, Shuttering 2 8/20/2022 8/21/2022
1 Footing & Plinth Level Column 2 8/27/2022 8/28/2022
2 Plinth Beam 2 9/8/2022 9/9/2022
3 Column 4 9/18/2022 9/21/2022
G Rcc M30 Concrete 1 9/3/2022 9/3/2022
1 Footing & Plinth Level Column 1 8/29/2022 8/29/2022
2 Plinth Beam 1 9/10/2022 9/10/2022
3 Column 1 9/29/2022 9/29/2022
H Brick Work in Super Structure 4 9/1/2022 9/3/2022