Monthly internship report

Name: Legesse konne


ID: 0761/04
Department: civil engineering
Project: Dilla University Teaching and Referal Hospital
Contractor: flint stone engineering
Client: Dilla University
SECOND MONTH INTERNSHIP REPORT
Week No:1 Dates:05-08-2007 to10-08-2007

wee day Date Work performed Supervisor ‘s sign &


k comment
1 1 05/08/2007 -on Monday 05-08-2007 there is no work, for the reason of
holiday.
06/08/2007 -arrangement of reinforcement bar for 3rd floor beam on
2 block-2.
-form work (soffit board) placed for 2nd floor slab on block-6.
-reinforcement bar arranged on block-7 for 2nd floor beam &
slab
-concrete casting from 3rd floor column elevation on block-
1.
3 07/08/2007 “
4 08/08/2007 “
5 09/08/2007 -in office we prepared check list, take off sheet for bar
schedule, bar cutting, form work & concrete work for block-
19.
6 10/08/2007 “

Abstracts;
- Preparation of crest (post) form work, Preparation of soffit and side form work, Bar cutting,
bending, placing in position, fixing of bar, formwork placing, Casting of concrete, Curing of concrete.
Here in the site the used concrete quality for column, beam & slab is c-25 & steel quality
of S-300 for 6mm – 12mm diameter bar; also S-400 steel grade for 14mm diameter & above.
- Preparation of site diary, Preparation of check list, Preparation of take of sheet for (Bar schedule,
bar cutting, Form work, concrete work) are executed at office.
Week No:2 Dates:12-08-2007 to17-08-2007

week Da Date Work performed Supervisor ‘s sign &


y comment
2 1 12/08/2007 -arrangement of reinforcement bar continued for 3rd floor slab &
beam on block-2.
-Reinforcement work and PVC conduit for the electrical installation
is arranged for the 2nd floor slab and beams on block B-7.
-scaffolding & form work prepared for 2nd floor slab & beam on
block-5.
2 13/08/2007 -scaffolding & form work prepared for 2nd floor slab & beam on
block-2.
-scaffolding & form work prepared for 2nd floor slab & beam on
block-8.
-concrete casting for 2nd floor slab & beam on block-7.
-arrangement of reinforcement bar for 2nd floor beam on block-6.
3 14/08/2007 “
4 15/08/2007 “
5 16/08/2007 -form work prepared for basement column on block-17
-Detaching the formwork from the 3rd floor elevation column on
block B1.
-arrangement of reinforcement bar for 3rd floor slab & beam on
block-2.
-arrangement of reinforcement bar for 2nd floor beam on block-5,
block-6 & block-8
-column bar extending from ground floor on block-16.

6 17/08/2007 “

Abstract:
- Preparation of crest (post) form work, Preparation of soffit and side form work, Bar cutting,
bending, placing in position, fixing of bar, formwork placing, Casting of concrete & Curing of concrete are
executed in the site.
- Preparation of site diary, Preparation of check list, Preparation of take of sheet for (Bar
schedule, bar cutting, Form work, concrete work) are executed at office.
-me and other students who came for practice participate both in the site and at office. In the
site we check whether the concrete is properly cured or not, we check whether overlapping of
reinforcement bars are correct or not & other things which we see on plan but not exists on site. If there
is mistake while working, we comment on it, above all we learn from others. Whereas in office we
prepare take off and ask any question that we didn’t understand.
Week No:3 Dates:19-08-2007 to24-08-2007

week day Date Work performed Supervisor ‘s sign &


comment
3 1 19/08/2007 “

2 20/08/2007 -form work prepared for basement column on block-16.


-concrete casting for basement column on block-17.
-arrangement of reinforcement bar for 3rd floor beam on block-2.
-arrangement of reinforcement bar & PVC conduit continued for 2nd
floor beam & slab on block-5, block-6 & block-8

3 21/08/2007 “
4 22/08/2007 -arrangement of reinforcement bar continued for 3rd floor beam & slab
on block-2.
-form work prepared for 1st floor elevation column on block-11
-Reinforcement work and PVC conduit for the electrical installation is
arranged for the 3rd floor slab and beams on block B-2.
-arrangement of reinforcement bar continued for 2nd floor beam on
block-5
-concrete casting for basement column on block-16.

5 23/08/2007 “
6 24/08/2007 “

Abstract:
- After the placements of beams in all direction in their respective places, bar spacing
according to the design requirement would follows. Near the middle span of the slab the bars
may be cutoff depending on the requirement and/or depending on the design specification that
has been decided. At the site what I have seen is a little bit different from what I have learnt in
class. The engineers put an easy order taking an account the ease of construction.
. -The bars are put both in the longitudinal and transversal direction. Just after the
placement of the reinforcements pouring of concrete goes on. Care should be taken for
integrated construction. There should be a vibrator for proper concrete compaction to avoid
segregation.
Week No:4 Dates:26-08-2007 to01-09-2007

week day Date Work performed Supervisor ‘s sign &


comment
3 1 26/08/2007 -concrete casting for 3rd floor slab & beam on block-2.
-Detaching the formwork from the 1st floor slab & beam on block B-7.
-concrete casting for 2nd floor slab & beam on block-5, block-6 &
block-8.

2 27/08/2007 -concrete casting for 1st floor elevation column on block-11


-pit excavation for footing and form work for block 10
3 28/08/2007 -concrete casting for block 10 footing and trench excavation for
masonry wall
-leveling the ground surface between the block 10 and block 2
4 29/08/2007 -office work; takeoff sheet for hard core block 10&11
- ;takeoff sheet for HCB block 1 & 19
5 30/08/2007 -arrangement of reinforcement bar for 2nd slab on block 9
- Detaching the formwork from slab formwork for block 2
6 01/09/2007 -arrangement of reinforcement bar continued for 2nd slab on block 9
-office work; takeoff for concrete on block 9

Abstract:

-From continuing the previous week, this week also progressing the project as follows.. I
have seen in this week how to construct a solid slab. Slab reinforcement placed before the concrete
compactions are made. And also I have seen how the slab reinforcement arranged or placed according
to the design. After placing re-bar, cast concrete by appropriate compacter. After casting concrete
curing is done morning and evening in order to avoid cracking. The form work of slab displaced after 21
days. And also in this week extend the column from the first basement and column form work is made.

-Takeoff sheet: is tabular standard format in which dimension of items from the Working
drawing is transferred for further calculations. It is the process of reading drawing and calculating the
amount of materials/works needed. These quantities are calculated in a specially prepared tabular
format, so as to aid accurate preparation and enable checking/rechecking or adjusting of amounts &
correct errors if any. This format is used for calculating the amount of concrete casted in volume (m 3),
amount of lean concrete casted and formwork which are used in area (m2) and amount of skirting and
others in length (m).