Ogindi Rap
Ogindi Rap
03 Mar '24 10 Mar '24 17 Mar '24 24 Mar '24 31 Mar '24 07 Apr
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1
2 Project Duration 30 days Mon 26/02/2
3 LMC Projects 15 days Mon 26/02/2
4 Data Collection For Chuka Water and 6 days Mon
Sewer Project 26/02/24
5 Data Collection For Chogoria Water 6 days Tue
and Sewer Project 05/03/24
6 Draftig and submission of RAP 3 days Wed
reports For Chuka and Choria Sewer 13/03/24
and Water
7 Runyenjes S&W Supply Lines 13 days Fri 01/03/24
8 Provision of Final kmz and Digitised 0 days Fri 01/03/24 01/03
RIMs for Runyenjes Project by the
Client
9 Field Inspection and Data Collection 6 days Mon
For Runyenjes 11/03/24
10 Drafting and Submisision Of RAP 2 days Tue
Report for Runyejes 19/03/24
11 Meru Sewer and Water Lines 2 days Tue 19/03/24
12 Field Inspection and Data collectio 2 days Tue
Remaining Section of Meru 19/03/24