Professional Documents
Culture Documents
GT Report Jubilee HIlls
GT Report Jubilee HIlls
Submitted to
M/S GVK Infrastructure and Projects,
Hyderabad
TABLE OF CONTENTS
Page No.
1. INTRODUCTION
1
SGECS
1.0 Introduction
1.1 Project Description
The Client(M/S.GVK Projects ) has proposed to carry out soil investigations and field
testing for the Planned Multistoreyed Building ( Cellar + Stilt + 5 Floors) that was
proposed to be built on open plot at Jubilee Hills,Hyderabad. The site is in close
proximity to busy IT Hub and has well connected road network to all parts of city. M/s
Sai Ganapathi Engineering Consultancy Services(SGECS) was entrusted with the task of
carrying out soil exploration ,field testing and reporting of key findings of Ground
Investigation and testing.
1.2 Purpose of Study
The overall purpose of this study is to conduct a geotechnical investigation to assess the
stratigraphy and to develop geotechnical recommendations for foundation design for
the various structures planned in the project area. To accomplish these purposes the
study was conducted in the following phases:
Drilling boreholes at 5 locations identified by Consultants.
Conducting SPT in Bore Holes and core drilling in rock.
Testing samples in laboratory to determine the engineering properties of the
strata.
Analyzing all field and laboratory data to develop geotechnical recommendations
for foundations.
2
SGECS
a diamond shoe bit was used to assist the casings to advance .The work was in general
accordance with IS 1892 – 1979.
Standard Penetration Test ( SPT ) were conducted in the boreholes at 1.5 m depth
intervals by connecting the split spoon sampler to SPT rod and driving it by 45 cm using
a 63.5 kg hammer falling freely from a height of 75 cm . The test was conducted in
accordance with IS 2131 – 1981.
The number of blows for each 15 cm of penetration of the split spoon sampler was
recorded . The number of blows required to penetrate the initial 15 cm of the split
spoon is ignored for seating the sampler due to possible presence of loose materials or
cutting from the drilling operation. The cumulative number of blows required to
penetrate the balance 30 cm out of 45 cm is termed as the SPT or N values.
The N values are presented on the soil profile for each borehole. Refusal to further
boring penetration was considered when the N value exceeds 50 blows for 30 cm
penetration or when practical refusal to further penetration was encountered.
Disturbed samples were collected from split spoon after conducting the SPT. The
samples were preserved in transparent polythene bags. Undisturbed samples were
collected by attaching 75 mm diameter thin walled ‘Shelby’ tubes(in cohesive soils) and
driving the sampler using the 63.5 kg hammer in accordance with IS 2132 – 1986. The
tubes were sealed with wax at both ends .All samples were transported to our
laboratory at Uppal for further examination and testing.
2.2 Rock Drilling
Rotary drilling through the rock was performed using heavy-duty skid mounted Joy
Voltas 12B diamond coring rotary drill machine. The drill machine has a hydraulic feed
and is driven by a bevel gear system run by a 28 HP Leister engine. The drill chuck has
four jaws to accommodate NW size drill rods.
Drilling and sampling of the rock was performed using a NX size double tube core barrel.
Tungsten Carbide bit and 48 carat impregnated diamond bit was used to drill through
hard rock. It was attached to the end of a core barrel, which is connected to the
machine by a string of NW drill rods and rotated by the drilling machine.
Water was circulated through the drill rods to the bottom of the hole. The water serves
the purpose of lubrication, cooling and protection of the diamond drill bit in addition to
flushing the cuttings out of the hole. A reciprocating pump was used to circulate the
water. While drilling through soft rock that is likely to collapse, casing was installed. A
NX casing (80 mm OD) was used. The casing with a diamond shoe bit was used to assist
the casing to advance.
3
SGECS
2.3 Groundwater
Groundwater level was measured in the boreholes in 24 hours after drilling and
sampling was completed. The measured water levels are recorded on the individual soil
profiles.
3.0 LABORATORY TESTS
The laboratory testing has been carried out in our laboratory. The testing program was
aimed at verifying the field classifications and developing parameters for engineering
analysis. All testing was performed in accordance with the current applicable IS
specifications. The following tests were conducted on selected soil / rock samples
recovered from the boreholes.
The percent Core Recovery(CR) and Rock Quality Designation (RQD) was measured for
each core run. The percent recovery is defined as the percent ratio of the cumulative
length of core sample recovered to the total length of the core run. The Rock Quality
Designation (RQD) is defined as the ratio of the cumulative length of core pieces 10 cm
or longer to the total length of the core run, expressed as percentage. Details of samples
collected are presented on the rock profiles and RQD at various depths. The net
effective drilling time, a qualitative assessment of the nature of the strata, is also
included on the borehole logs.
Laboratory tests were conducted on selected soil samples, groundwater samples and
rock cores to determine its physical and engineering properties. The testing procedures
were in accordance with current applicable IS specifications. The following tests were
conducted on selected samples recovered from the boreholes:
4
SGECS
5
SGECS
6
SGECS
As per IS 1893 (Part-1): 2002, Table-1; liquefaction is likely in fine sands below water
table.
Based on a review of all soil parameters like in-situ density, measured groundwater
levels, fines content; we are of the opinion that liquefaction is not likely to take place at
the site in the event of a major earthquake.
According to Fig.1 of IS:1893 (Part1)-2002 showing seismic zones, the proposed site falls
under Zone-II. The design for seismic forces should be done considering the project in
Zone-II.
5.0 FOUNDATION ANALYSIS AND RECOMMENDATIONS
5.1 General
A suitable foundation for any structure should have an adequate factor of safety
against exceeding the bearing capacity of the supporting soils. Also the vertical
movements due to compression of the soils should be within tolerable limits for
the structure. We consider that foundation designed in accordance with the
recommendations given herein will satisfy these criteria.
7
SGECS
where:
qnet safe= safe net bearing capacity of soil based on the shear failure criterion.
p = overburden pressure
Rw = water table correction factor
F = Factor of safety, taken as equal to 2.5 in accordance with
IS:1904-1986.
8
SGECS
The area shall be excavated upto the foundation level. In most of the locations
hard rock is likely to be encounted. All loose soils should be removed and the
exposed foundation bearing surface should be watered and compacted
properly using rammers / rollers. The surface should then be protected from
disturbances due to construction activities so that the foundations may bear
on the natural undisturbed ground.
9
SGECS
10
SGECS
check the cut slopes for stability and stabilization measures shall be
considered.
In fractured rockmass the excavation will be self supporting if cut heights or up
10m and in case of deeper cuts it is recommended to provide 3ft/1m bench to
have self supporting cut in rockmass. The retaining walls shall have gravel
packing with weep holes arrangement behind the wall.
6.0 CLOSURE
We appreciate the opportunity to perform this investigation for you and have
pleasure in submitting this report. Please contact us when we can be of further
service to you.
for SGECS
Subbarao Mukunda
(Principal Geotechnical Consultant)
11
APPENDIX-II
Field Borelogs
SGECS
Depth of NX
Casing (m)
1981
Nature of
Run No.
RQD %
TCR %
Sample
Legend
From (M)
15-30 cm
30-45 cm
N' Value
0-15 cm
To (M)
Depth
Color
Loss
(M)
From To
Depth of NX
Casing (m)
1981
Nature of
Run No.
RQD %
TCR %
Sample
Legend
From (M)
15-30 cm
30-45 cm
N' Value
0-15 cm
To (M)
Depth
Color
Loss
(M)
From To
Depth of NX
Casing (m)
1981
Nature of
Run No.
RQD %
TCR %
Sample
Legend
From (M)
15-30 cm
30-45 cm
N' Value
0-15 cm
To (M)
Depth
Color
Loss
(M)
From To
Depth of NX
Casing (m)
1981
Nature of
Run No.
RQD %
TCR %
Sample
Legend
From (M)
15-30 cm
30-45 cm
N' Value
0-15 cm
To (M)
Depth
Color
Loss
(M)
From To
Depth of NX
Casing (m)
1981
Nature of
Run No.
RQD %
TCR %
Sample
Legend
From (M)
15-30 cm
30-45 cm
N' Value
0-15 cm
To (M)
Depth
Color
Loss
(M)
From To
Uniaxial Compressive
Uniaxial Compressive
Dry Density gms/cm3
Moisture Content %
Strength(Dry),Mpa
Confining Pressure
Strength(Sat),Mpa
Plasticity Index %
Angle of Internal
Weight(gms/cc)
Natural Density
Specific Gravity
Specific Gravity
Weight(gm/cc)
Saturated Unit
SAMPLE DESCRIPTION
Porosity(%)
Sample No.
Depth (m)
gms/cm3
Gravel %
Index(%)
Plastic %
Location
Liquid %
Dry Unit
Kg/cm2
Kg/cm2
Friction
Sand %
Clay %
Silt %
Location
BH-02 0.00-3.00 CORE MW-SW Grade III Rockmass 2.63 2.66 2.56 87.23 61.12
0.00-1.00 DS Sand
Jubilee
Hills BH-03 1.00-4.00 DS Completely Weathered Rock 100 2.54 34.30
Building
4.00-7.00 CORE MW-SW Grade III Rockmass 2.71 2.74 5.23 67.54 78.54
BH-05 4.00-7.00 CORE MW-SW Grade III Rockmass 2.69 2.71 3.54 56.87 68.32
Ref Calculations
2. The footing rests on horizontal rock surface and the rock under the footing is under compression
similar to that of specimen in triaxial compression test.
The rock mass is modelled in Roclab based on field drilling record and laboratory test results on
intack rock.
where
qa = allowable safe bearing capacity in MPa ϒ = Unit Weight of Rock
m & s are Hoek and Brown rockmass constants D = Depth of Embedment
σu( r ) = Uniaxial Compressive Strength of Intact Rock
σ'3 = Confining stress at foundation level,MPa Cf1 = correction factor for shape
FoS = Factor of Safety (as per table 5.4 of Duncan C Wylie)
qs = overburden pressure
Job ref
Project: Construction of C+S+5 Floors Building
Ref Calculations
qa = 0.9891 MPa
= 989.1 KPa
Bearing Capacity from Bell's Solution ( For weak and closely fractured rockmass)
Nc 2 N ( N 1)
where Nq ( N )^ 2
B = Width of Footing,m
Cf1 & Cf2 = Correction Factors N 0.5( N )^ 2
ϒ = Unit Weight of Rock
D = Depth of Embedment N Tan 2(45 / 2)
Nc,Nq & Nϒ = Bearing Capacity factors
qa = 809.53 kPa
Shear Based SBC computations gives higher Safe Bearing Capacity for foundation on rockmass by
adopting Mohr-Coulomb strength criteria and this approach does not consider the affect of jointing or
discontinuities in rockmasses.
hence a min of shear criteria approach and rock mass strength criterion is recommended
Recommended to consider SBC of 65T/sq.m to 80 T/sq.m for foundations on rock with dowels
Job ref
Project: Construction of C+S+5 Floors Building
Ref Calculations
Method:1
k-value prediction
k= p/δ where p = load intensity corresponding to 1.25mm settlement
135
k = = 108000 kN/m3
1.25
Method: 2
Determination of Modulus of Subgrage Reaction :
Eq 9.9 - "foundation
engg by Bowles
ks=40(𝐹𝑆)𝑞𝑎
ks - soil stiffness in kN/m3
FS - Factor of Safety
qa - allowable bearing capacity(kPa)
ks = 19428.80 (Max)
ks = 108000 (Min)
ks = 63714.40 (Average)
BH_2
BH_3
BH_5
BH_6