Professional Documents
Culture Documents
Design and Testing of An Arc Resistant Power Trans
Design and Testing of An Arc Resistant Power Trans
1088/2631-8695/ad2f88
PAPER
1. Introduction
The explosion of power transformers due to internal low impedance arcing is a concern for manufacturers and
utility companies with a probability of transformer explosion failure leading to fire on the order of 0.1% per
service year [1]. Catastrophic consequences such as: oil leaks and toxic fires are a threat to personal safety, an
environmental concern, and potential economic losses. A rupture resistant tank, that contains the arc energy by
plastic deformation, has been proven to be a robust solution to mitigate the risk of fire if arcing occurs inside the
transformer tank [2]. However if high-energy arcing occurs in other oil-filled compartments such as bushing
turrets, which is one of the major causes of transformer fires according to [1], one must account for the local
peak pressures appearing at this fault location. These local pressure rises can, as will be shown in this paper by
simulation and experimental data, be much higher and faster than for an equivalent arcing energy inside the tank
[2], due to the smaller surrounding volume and stiffer geometry. At the same time there is currently limited
guidance in [1] and [3] on how to design turrets for internal arcing.
This paper is a continuation of previous work on rupture resistant tanks, but unlike [2] instead focusing on
internal arcing inside the turret and its failure mode. It presents the design and testing of a full-scale 510-kV,
415-MVA HVDC converter transformer prototype designed to withstand the resulting pressure of a 20 MJ low-
impedance fault in oil occurring inside the turret in 100 ms, as proposed by the IEEE guide for this transformer
voltage class [3]. The transformer handles the resulting peak pressures by relying on a reinforced turret design. In
addition, an improved test setup compared to [2] was developed, which enabled experiments with higher power
and shorter duration.
Experiments are important for increasing overall knowledge and confidence in current design calculation
methods. To ensure that the latest knowledge was utilized when designing our test setup, a review of past
investigations and experiments was conducted.
An investigation on circuit breakers concluded that arc energy dissipation can be broken down into; loss at
contacts, radiated heat, oil heat to its boiling point, breakdown of oil into gas, heat of gas, expansion of gas and
dissociation of the hydrogen formed [1]. The authors also concluded that the average gas temperature is
approximately 2,000 °K and the gas generation rate can be considered as a linear function of the energy at
standard temperature and pressure. Its noteworthy to mention that more recent studies indicate gas
temperature in the range of 1,500–2,100 °K [4]. Other later arcing experiments [5] also includes more detailed
measurements of the released arc energy, showing a small pulsating behavior in an overall linear trend.
The pressure difference between the gas and the surrounding liquid creates pressure waves in the tank until it
stabilizes after a certain time. The authors of arcing tests on distribution transformers with high-speed
photography concluded that the pressure against the tank was due to gas bubble expansion and the kinetic
energy of oil movement [6, 7]. In addition, the impulse pressure immediately after the arc ignition produced a
rupture of the distribution transformers, with a shape similar to that of the turrets studied in this paper. Another
transformer arcing experiment showed a correlation between the gas bubble volume measured using a high-
speed camera and pressure sensors on the tank [5]. This means that the mechanical resistance of transformers
depends on the gas bubble pressure rise and its duration; other aspects of the arc energy dissipation mentioned
above are not relevant.
The energy generated by an arc in oil experiments is difficult to control, and there is a risk of damage to the
laboratory equipment and overall security. In addition, producing a transformer rupture requires a high-power
source, which limits the laboratory availability for energy levels upwards 20 MJ. The highest reported energy of
an arc in oil experiment was performed in a on-load tap changer oil compartment with an arc energy of 10 MJ
[8]. Other techniques have been used to simulate the gas bubble pressure rise from an arc in oil; for example, a
special powder combustion vessel has been used on a water filled 275 kV transformer up to an equivalent arc
energy of 11.2 MJ [9]. Another experimental approach is to suddenly discharge compressed gas in the
transformer, it has been first used in 1959 [10]. Subsequently, this experimental method showed good
agreement with electrical arc in oil tests on pole-type distribution transformers [11]. Finally, 210 MVA
transformer tests with sudden discharge of compressed gas have produced, to our knowledge, the highest
equivalent arc energy (up to about 30 MJ) and measured pressure rise (1,000 kPa) ever reported.
An important parameter which influences the pressure rise of transformers is the duration. For a while the
effect of the arcing duration was misunderstood. Note that the power industry references and practices such as
the proposed equation (2), which assumes isothermal expansion of the gas bubble generated in the oil, are based
on a short-duration arc of 50 to 100 ms because of circuit breaker response time [1, 12]. However, this topic was
investigated in 2020, and a numerical study [2] showed larger tank plastic work for shorter arc duration despite
similar maximum pressures; thus, short-duration arcs are more severe for mechanical structures. Thus, an
arcing test of 20 MJ in 50 ms is creating more structural damage than an arcing test of 20 MJ in 1 s. Therefore, the
speed of gas bubble expansion is important when analyzing and comparing transformer mechanical resistance.
Over the years several authors focused on transformers tank strength under internal arcing by experiments
[2, 5, 9, 10, 13–17] and numerical simulations [18–21]. Despite the catastrophic consequences of an arc located
in a turret is known, only a few studies are covering this topic. A first investigation of a turret failure suggests that
retrofitting designs mitigate the risk of turret projections based on numerical simulations [22]. Another
numerical study analyzed the resistance of a tank and bushing turrets for an arc of 4,8 MJ located at the windings
or at the tap changer. The results show the importance of the arc location where higher stress is observed on the
tank in comparison with the bushing turrets [23]. Moreover, a numerical model simulates an arc of 21 MJ in 59
ms at the entrance of a turret to reproduce a 415 MVA converter transformer accident. The results show a peak
pressure in the turret in about 10 ms where the maximum stress appears at the joint between the turret and the
tank [24]. A bushing turret failure to a 570 MVA GSU transformer highlight the vulnerability of an arc located in
this component [25]. An arc in oil test on a turret prototype submitted to energy of 3,54 MJ in about 150 ms
resulted in a peak pressure of about 1,75 MPa. A high pressure and temperature mixture of oil and gas was
discharged through the turret pressure relief devices, but their reducing effect is not clear since no test
comparison without devices are available.
The remainder of this paper presents the transformer design in section 2. and experimental testing of the
mechanical resistance by sudden discharge of compressed gas to produce high energy and pressure in section 3.
The paper is summarized and concluded in section 4.
2
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 1. Experimental test model compared with HVDC converter transformer rated at 415 MVA.
2. Transformer design
The technical solution described in this paper relies on a reinforced turret design. An ideation process was
followed, and the stated solution was selected from several ideas; including venting by pressure relief devices,
rupture discs, and designing a turret with a greater possibility of expansion. The decision point during the
selection phase was that the arcing pressure rise is too fast to be discharged, the considered system region is too
small to absorb the energy via deformation, and the most efficient method is to reinforce the turret to contain the
extreme pressure, which peaks within the first cycle, without rupturing. This passive protection solution relies
on the turret handling this initial peak without the need for an additional relief device. This reinforced turret is
designed to resist an arc energy level by assuming normal circuit breaker operation on the network to interrupt
the power. Then, the transfer of pressure thru the lower turret flange into the transformer tank designed to
absorb energy by plastic deformation. Ultimately resulting in a uniform residual pressure within the transformer
which can later be vented by the tank pressure relief device.
The test objects included a turret, Resin Impregnated paper (RIP) bushing, mock-up active part and tank.
The test facility limitations and manufacturing costs had to be considered when deciding on the size of the test
tank; inner dimensions of 5 m length × 3 m width × 4 m height were used. Figure 1 compares the test setup with
the HVDC converter transformer rated at 415 MVA, where it can be observed that while the dimensions of
turret and tank height and width are equal, the length of the test tank is smaller. This will lead to a more
conservative test setup because the residual pressure will be higher owing to the lower tank volume.
3
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
The tank water is added to a Euler domain. Then, pressurized air was injected in 100 ms near the bottom of
the bushing, which is the most likely arcing location. The amount of air was controlled to be equivalent to the
volume created during an arc energy of 20 MJ in oil. The intention of the simulation was to replicate the loading
conditions used in the experiment. Note that rupture is not considered for this explicit dynamic analysis, and it is
assumed that the resulting pressure levels and distribution will be conservative for a design that ruptures. The
rupture failure mode was assessed by the static nonlinear finite element analysis described in section 2.1.2. The
numerical results in figure 3 show the expansion of the air bubble over time, displaying a significant fluid transfer
between the turret and the tank.
The pressure was monitored by gauges initially included in the model where the average pressure near the
turret cover reached a peak pressure of 7,942 kPa, as shown in figure 3. This peak pressure was used as the target
design value for the reinforced turret to withstand. Note, the pressure peak is reached before the full expansion
of the air bubble. In addition, a more uniform pressure distribution between the turret and tank is reached after
approximately 200 ms. Finally, pressure propagation result of the explicit dynamic simulation is shown in
figure 13 where it is compared with the experimental measurements.
4
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 3. (a) Air bubble evolution and (b) Pressure distribution in water over time.
Parameter Symbol ISO 10025–2 S355J2 ISO 898 Class 8,8 E70C
5
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 5. (a) Stress of the 550 kV turret,(b) submodel mesh and (c) fastener strain result in a rupture.
modeled using 3D solid elements, and a preload force of 34.4 kN was applied to replicate the tightening torque in
the first step of the simulation. In the subsequent steps, pressure was applied to the inner surfaces of the turret.
The results in figure 5 shows the equivalent stress for a pressure load of 1.1 MPa. The result shows maximum
stress on the fastener near the tank wall; therefore, this region was subjected to further analysis. A submodel was
created, meshed by solid elements where the mesh size of the fastener is refined to 1 mm, as shown in figure 5. A
strain-based rupture criterion was used to predict the failure when the equivalent plastic strain eeP exceeded the
ultimate plastic strain euP throughout the thickness of the part under consideration. This criterion, equation (1),
has been validated by pressurized experiments on a tank wall [17] and recommended by a comparative
numerical investigation with other criteria [18]. The simulation results predicted a rupture when the turret
arcing pressure reaches 1,025 kPa.
eeP euP troughout the thickness (1)
6
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 6. (a) Displacement, (b) stress, and (c) strain results of the reinforced turret.
where F is the dynamic amplification factor, k is the arc energy conversion factor (= 5.8 ×10−4 m3/kJ), E is the
arc energy to withstand (kJ), c is the tank expansion coefficient (m3/kPa), and Ph is the hydrostatic pressure (kPa)
at the middle height of the tank.
2.2.3. Result
The global model was analyzed, and the tank design pressure was established. The result can be seen in table 2.
A submodel analysis of the areas with the highest deformation confirmed a safe design at a design pressure
equivalent to a fault of 20 MJ. The highest strain was obtained at tank cover weld, which is the first rupture point
at an energy level >20 MJ with a good safety margin. The overall strain and stress levels at the tank walls and
cover also displays safe values at design pressure as can be seen in figure 7.
3. Experiments
7
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 7. (a) Strain and (b) stress of the test object at tank design pressure.
Figure 8. Test setup including both test objects and part of gas injection equipment.
550 kV Turret Test: Testing of a conventional 550 kV turret subjected to an energy level of 20 MJ to produce a
rupture as predicted by static nonlinear finite element analysis.
Reinforced Turret Test: The reinforced turret subjecting to an arc energy of 20 MJ will, according to the static
nonlinear finite element analysis, handle the resulting pressures without ruptures, which will be proven by the
experimental test. The success of the reinforced turret test was based on the absence of ruptures or leakages from
the turret or from anywhere else in the transformer. The explicit dynamic simulation results were compared
with pressure measurements.
The total test objects will include a turret, RIP bushing, mock-up active part, and a tank, which is required to
capture the correct pressure propagation. Figure 8 compares the two test objects, and it can be observed that the
main reinforcement consists of an increase in the size of all ISO 898 class 8.8 bolts from M12 to M36, and an
increase in shell thickness from 6 to 8 mm. But as well an increase in flange thickness to handle the higher bolt
8
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 9. Schematic cross section view of test setup including test object and gas injection equipment.
pretension and decrease the risk of leakage. One can also see the pressure sensors P1—P13 which are mounted in
the same locations on both test objects.
3.2. Methodology
The experimental method used in our study reproduced the effect of an arc in oil by injecting the corresponding
mechanical energy, which leads to a pressure rise. Only part of the electrical energy from a fault is transferred to
mechanical energy owing to various dissipative mechanisms. Approximately 24% [1] of the electrical energy
Eelec (MJ) is converted to gas bubble enthalpy; mechanical energy Emech (MJ) which leads to a pressure rise within
the transformer.
Emech
= 0.243 (3)
Eelec
To reproduce an arc in oil with 20 MJ of electrical energy, the experimental setup needs to inject a gas equivalent
to 4.86 MJ of mechanical energy.
9
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
injection started and air flowed thru the 10 m long pipe into the test object. A pressure sensor in the pressure
chamber registers the initiation and triggers a signal to stop the airflow after approximately 100 ms, which was
performed by a mechanical valve. The later consisted of a 6-inch class 1500 swing check valve, which was
modified with an electromagnet, allowing minimum flow restrictions in open position and a controllable and
fast closing mechanism. Valve is closed by the air flow and closing time is estimated to be in the range of a couple
of milliseconds. The test was monitored using seven pressure sensors on the tank and six were located on the
turret. A high-speed camera documented the planned sequence of events during the tests.
P2 V2 - P1 V1
DE = (4)
g-1
Where P1 and P2 are initial and final vessel pressures respectively (Pa); V1 and V2 are initial and final vessel
volume respectively (m3) and γ is the perfect gas constant for air (1.4). In our model, ΔE represents the
mechanical energy leaving the pressure vessel, and is denoted ΔEmec (MJ). Additionally, both V1 and V2 can be
substituted by Vpv and equation (4) can then be written as:
(P2 - P1) Vpv
∆Emec = (5)
g-1
By rearranging (5) and substituting (P2 - P1) with ΔP one can express the corresponding pressure drop in the
pressure vessel as a function of mechanical energy as:
Finally, using (6) one can calculate the required pressure drop needed to inject 4.86 MJ as 1,834 kPa.
The required pressure drop does not vary with P1, but the mass flow rate out of the vessel is a function of this
initial pressure. Therefore, the required injection duration will be influenced by P1. The burst pressure of the
rupture discs was 162 bars, and for this reason P1 was maintained at approximately 165 bar during the entire
calibration and both tests.
The required pressure drop according to (6) assumes, as mentioned, that all the mechanical energy leaving
the pressure vessel enters the test object at the end of the injection system. This would be true if the pressure
vessel could inject directly into the test object; however, in practice a 10 m long pipe was used with a non-
negligible volume (0.1 m3) and friction; therefore, a small portion of the energy will not reach the test object.
This effect was validated by explicit dynamic simulations of the test equipment where the initial pressure of the
pressure vessel was released through the piping and closed after 100 ms. First, the simulation could not
reproduce the pressure drop due to components of the piping system (valves) or friction in the piping. Thus, the
piping diameter of the model is adjusted by trial and error until it fits the mechanical energy leaving the vessel
measurement of a calibration test, the pressure drop recording is used with the calculation of (6). Second, from
the numerical simulation results, the difference between the energy leaving the pressure vessel and that leaving
the end of the piping is approximately 3%. Therefore, the targeted mechanical energy released from the vessel
was increased to 5.01 MJ to achieve an injection of 4.86 MJ. The target test parameters are listed in table 3. The
acceptance criteria for the calibration were specified as an acceptable accuracy of ±20% with respect to the of
injection duration and arc energy injected. And with an acceptable reproducibility between trials of
maximum 10%.
10
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 10. (a) Ruptured M12 stud bolts from lower flange connection. Vertical position of the turret assembly; (b) Initial, (c) 30 ms
after bolt ruptured and (d) at maximum displacement.
11
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
estimated by the static nonlinear finite element analysis. This peak pressure, occurring after approximately 10
ms, which is later followed by decreasing pulsations, is in good agreement with real arc in oil experiments at
lower energy levels [5].
Figure 13 compares the measurements at the top and middle of the turret with the explicit dynamic
simulation during the first 60 ms. The first pressure peak appears in the middle of the turret at the arcing
location, and one can later follow the pressure propagated with a peak pressure of 8,323 kPa appearing a couple
of milliseconds later at the locations of sensors P12 & P13. The FEA peak is approximately 20% higher than the
measurements, with a delay of about 4.5 ms. One reason for the slight delay was because injection system was not
considered in the explicit dynamic simulation model. In general, the simulation results overestimate the
measurement in the turret, which should be considered safe for the design. Finally, the peak of 6,655 kPa is more
than six times higher than the peak pressure (1,000 kPa) measured during the test [2] with similar arc energy,
where the injection location was inside the transformer tank.
Figure 14 shows the evolution of the average pressure measured by the six sensors in the turret and the seven
sensors on the tank during the first 200 ms of the reinforced turret test. The average turret pressure reached a
maximum of 2,563 kPa while the maximum average tank pressure measured in the test was 405 kPa. The tank
pressure continued to rise for approximately 100 ms which was almost 10 times slower than the reinforced turret
pressure rise (10 ms). Additionally, it is worth noting that the maximum average tank pressure was
approximately 14 times lower than the average value measured near the reinforced turret cover (5,532 kPa).
Figure 15. shows the pressure evolution from seven sensors on the tank (P1-P7) as well as their average. This
figure also shows the average tank pressure obtained from the explicit dynamic simulation, as well as the tank
12
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 13. Reinforced turret test comparison between pressure measurements and simulation.
Figure 14. Reinforced turret test comparison between average turret and tank pressure measurements.
Figure 15. Reinforced turret test comparison between Tank pressure measurements and simulation.
13
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
Figure 16. Reinforced turret test tank deformation (a) before injection and (b) after, with arcing and hydrostatic pressure removed.
design pressure calculated by (2). The maximum average tank pressure from the simulation was 369 kPa,
whereas the maximum average tank pressure from the test was 405 kPa; a difference of approximately 10%. The
tank design pressure of 475 kPa, calculated by nonlinear static analysis and (2), displayed a good safety margin
and confirmed it as a safe method for designing tanks against internal arcing. As shown in figure 15 there are
multiple peaks above the design pressure, with a maximum tank peak pressure of 867 kPa, observed on the back
wall (P6) after 81 ms. However, these short duration peaks, lasting roughly 2–4 ms, are not a concern for tank
integrity, which is proven by the experiment. This result is in good agreement with section 2.2.1in [1], indicating
that the tank can withstand very high local peak pressures for shorter times, since it is the displacement of the
tank walls causing the ruptures, not the pressure itself. According to the high-speed recording, the tank wall
displacement reached its maximum after approximately 200 ms. This is well in line with the average tank
pressure measurements in figure 15, which displayed a rather stable and uniform residual pressure of 275 kPa
after 200 ms.
The remaining overpressure was released through the Pressure Relief Device (PRD). Figure 16 shows the
remaining deformation of the tank when the arcing and hydrostatic pressures were removed. The tank
displacement was measured at multiple points along the tank height, with a maximum at the center of the tank
wall with a permanent displacement of 87 mm, whereas the maximum displacement from the nonlinear static
analysis was 109 mm. The high-speed video recording indicates a similar PRD activation time for both tests, and
in the 550 kV turret test, it occurred after the rupture of the bolted connection. This is also in good agreement
with a previous tank test [2] with a recorded PRD activation time of approximately 57 ms. The discharge of water
was observed after about 300 ms, then the measurement show a slow relief of the pressure where after 5 s the
average pressure in the tank was 225 kPa and after 10 s it was reduced to 180 kPa. Finally, it is safe to assume that
the PRD had no impact on reducing the peak pressure inside the turret because it occurred already after 10 ms.
4. Conclusion
This study focusing on high-energy low-impedance faults occurring inside a transformer turret, which is one of
the major causes of transformer fires [1]. The governing design principle proposed is based on a reinforced turret
that contains the extreme initial pressures and transfers the arc energy into a transformer tank designed to resist
the load. The reinforced turret was dimensioned for a peak pressure obtained by an explicit dynamic analysis,
and later verified by nonlinear static finite-element analysis and proven experimentally with, to our knowledge,
the highest arc energy level ever performed in a transformer turret, equivalent to an electrical arc in oil of 23 MJ
in 100 ms.
Some of the main findings from simulations and experiments are:
• Resulting peak pressure of 6,655 kPa for an arc inside the turret is roughly six times higher than an arcing
location inside the tank.
14
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
• Experimental tests of the original 550 kV turret and the reinforced turret, with the same arc energy levels,
demonstrated the robustness of the new design.
• In general, the simulation results overestimate the measurement in the turret. While this demonstrates a safe
and conservative design approach, it also indicates possibility for future improvements in the method.
Finally, we concluded that suggested reinforced turret makes it is feasible to design a rupture resistant
transformer that will significantly reduce the risk of fires and improve overall safety of the substation, while
offering:
• A robust and maintenance free solution offering passive protection without the need of additional relive
devices.
• Potential to be optimized for different arc energy levels and voltage class for turrets, cable boxes and chimneys.
• Possibility for retrofit. Which assumes tank has already been designed to handle the arc energy and will require
minor welding work at site to change mounting flange on transformer cover.
Acknowledgments
The authors gratefully acknowledge the entire Hitachi Energy Power Transformer factory in Ludvika for their
contributions in designing and manufacturing the test setup and performing the experiments.
The data cannot be made publicly available upon publication because they contain commercially sensitive
information. The data that support the findings of this study are available upon reasonable request from the
authors.
ORCID iDs
References
[1] 2013 Guide for Transformer Fire Safety Practices Technical Brochures 537-2013 CIGRÉ
[2] Brodeur S and Dastous J-B 2020 Design and testing of an arc resistant power transformer tank IEEE Trans. Power Delivery 35 669–706
[3] 2016 IEEE Guide for Tank Rupture Mitigation of Liquid-Immersed Power Transformers and Reactors IEEE Std C57.156-2016 pp 1–26
[4] Yan C et al 2021 Experimental study on the gas bubble temperature around an Arc under insulation oil IEEE Trans. Power Delivery 36
1245–8
[5] Yan C, Xu C and Liu H 2023 Research on oil pressure rise and fluctuation due to arcing faults inside transformers IEEE Trans. Power
Delivery 38 1483–92
[6] Barkan P, Damsky B L, Ettlinger L F and Kotski E J 1976 Overpressure phenomena in distribution transformers with low impedance
faults: experiment and theory IEEE Trans. Power Appar. Syst. 95 37–48
[7] Cuk N P 1990 Oil tank explosion resistance Canadian Electrical Association, Technical Report 149 D491
[8] Zhao Y et al 2022 Study on pressure spread characteristics of Arc fault in the oil compartment of OLTC 2022 IEEE Int. Conf. on High
Voltage Engineering and Applications (ICHVE) pp 1–4
[9] Kawamura T, Ueda M, Ando K, Maeda T, Abiru Y, Watanabe M and Moritsu K 1988 Prevention of tank rupture due to internal fault of
oil-filled transformer CIGRE 12-02_1988
[10] Ringlee R J and Roberts N W 1959 Tank pressures resulting from internal explosions Transactions of the American Institute of Electrical
Engineers. Part III: Power Apparatus and Systems 78 1705–10
[11] Dastous J-B, Foata M and Hamel A 2003 Estimating overpressures in pole-type distribution transformers II: prediction tools IEEE
Trans. Power Delivery 18 120–7
[12] Abi-Samra N, Arteaga J and Darovny B 2009 Power transformer tank rupture and mitigation—a summary of current state of practice
and knowledge by task force of IEEE power transformer subcommittee IEEE Trans. on Power Delivery 24 1959–67
[13] Hamel A, Dastous J-B and Foata M 2003 Estimating overpressures in pole-type distribution transformers I: tank withstand evaluation
IEEE Trans. Power Delivery 18 113–9
[14] Pan Z, Deng J, Xie Z, Peng X, Hou M and Zhou H 2023 Research on simulation and verification experiment method for pressure
characteristics of converter transformer tank under internal Arc fault Presented at 2023 the 6th Int. Conf. on Energy, Electrical and Power
Engineering pp 1128–34
[15] Muller S, Petrovan-Boiarciuc M and Périgaud M 2009 Pressure wave propagation induced by short circuits inside power transformers:
development of a simulation tool, comparisons with experiments and applications Int. J. Multiphys. 3 361–86
[16] Park W H, Lee J W and Chung S H 2023 DPRS transformer dynamic pressure resistant system—II Transformer Magazine 10 102–9
[17] Bélanger S, Brodeur S, Dastous J B and Soucy N 2014 Experimental and numerical studies of large steel plates subjected to high pressure
loading Presented at the World Congr. Comput. Mech. Session - (Barcelona, Spain) pp 1–10
15
Eng. Res. Express 6 (2024) 015318 J Johansson and S Brodeur
[18] Brodeur S, Lê V N and Champliaud H 2021 A nonlinear finite-element analysis tool to prevent rupture of power transformer tank
Sustainability 13 1048–64
[19] Dastous J-B, Taschler E, Bélanger S and Sari M 2017 A comparison of numerical methods for modeling overpressure effects from low
impedance faults in power transformers Procedia Eng. 202 202–223
[20] Dastous J-B 2023 Enhancements in power transformer Arc-resistant specifications Presented at CIGRÉ Transformer Research and Asset
Management Joint Colloquium - (Split, Croatia) pp 1–14
[21] Luo L, Sui M, Sun J, Zhao Y, Wang K, Li J and Zhang N 2023 A study of pressure development and oil-immersed transformer tank
deformation during an arcing event considering strong FSI 2023 Panda Forum on Power and Energy (PandaFPE) pp 2302–8
[22] Dastous J-B, Lanteigne J and Foata M 2010 Numerical method for the investigation of fault containment and tank rupture of power
transformers IEEE Trans. Power Delivery 25 1657–65
[23] Chen S, Guo Z, Xie Q, Xiao W and Qu G 2023 Balance design concept for ultra-high voltage transformer against arc fault explosion and
its realization 2023 International Conference on Power System Technology (PowerCon) (Jinan, China) pp 1–8
[24] Li B, Hao Z, Ding G, Zhang Y, Xue Z and Wu X 2021 Modeling and Analysis of Tank Rupture Due to Internal Electrical Fault in Oil-
filled Power Transformer Presented at 2021 Int. Conf. on Advanced Electrical Equipment and Reliable Operation (Beijing, China) pp 1–5
[25] Ryadi M et al 2023 Mitigation of fire due to high energy internal arc in bushing turrets Presented at Presented at CIGRÉ Transformer
Research and Asset Management Joint Colloquium (Split, Croatia) pp 1–8
[26] Foata M and Dastous J-B 2010 Power transformer tank rupture prevention Presented at CIGRÉ Transformer Technology Conf. (Paris,
France) pp 1–10
[27] Foata M, Iordanescu M and Hardy C 1988 Computational methods for the analysis of explosions in oil-insulated electrical equipment
IEEE Trans. Power Delivery 3 286–93
16