Execution Plan For Retaining Wall
Execution Plan For Retaining Wall
Execution Plan For Retaining Wall
Preparation of Approach Road Excavation work for Ist& 2nd Excavation work for 3rd& 4th
18.03 TO 20.03 at Nallah Side for Disposal work Span upto 50% Span upto 50% Fitter & Helper - 15 Nos
1st Week
Excavation work for 5th& 6th
21.03 TO 23.03 Span upto 50% Shoring Work Shoring Work Unskilled Labour - 12 Nos
Ist Span & 2nd Span 50 % Ht Ist Span & 2nd Span 50 % Ht Ist Span & 2nd Span 50 % Ht
25.03 TO 27.03 Breaking Breaking Breaking Long Boom Excavator - 1 No
Exavation of the required Shoring work on the Nullah Exavation of the required portion
portion on the Nullah side upto side for the 3rd Span on the STP side upto Rock Level
Rock Level for the 3rd span for the 3rd span
15.04 to 17.04 Initiation of breaking work for Breaking work for Shear Key Breaking work for Shear Key in
Shear Key in 2nd span in 2nd Span 2nd Span
Initiation of cutting and bending cutting and bending of steel Initiation of cutting and Bending
5th Week of steel for Shear Key for Shear Key reinforcement of Raft Reinforcement
reinforcement
3rd Span upto Bottom Level 3rd Span upto Bottom Level
Breaking Breaking Disposal of Debris
cutting and Bending of Raft cutting and Bending of cutting and Bending of Vertical
Reinforcement Vertical Reinforcement Reinforcement
Shoring work on the Nullah Exavation of the required portion
side for the 4th Span on the STP side upto Rock Level
Exavation of the required for the 4th span
portion on the Nullah side upto
Rock Level for the 4th span
22.04 to 24.04 Initiation of breaking work for Breaking work for Shear Key Breaking work for Shear Key in
Shear Key in 3rd span in 3rd Span 3rd Span
4TH Span upto Bottom Level 4th Span upto Bottom Level
Breaking Breaking Disposal of Debris
Preparation of Formation level PCC Work completion of 3rd Concreting of Raft of the 1st
25.04 to 27.04 of PCC for 3rd Span Span Span
Initiation of cutting and bending cutting and bending of steel Initiation of cutting and Bending
of steel for Shear Key for Shear Key reinforcement of Raft Reinforcement for 2nd
reinforcement for 2nd span Span
5th Span & 6th Span 50 % Ht 5th Span & 6th Span 50 % Ht
Breaking Breaking Disposal of Debris
Initiation of breaking work for Breaking work for Shear Key Breaking work for Shear Key in
Shear Key in 4th span in 4th Span 4th Span
Shoring work on the Nullah Exavation of the required portion
side for the 4th Span on the STP side upto Rock Level
Exavation of the required for the 4th span
29.04 to 01.05 portion on the Nullah side upto
Rock Level for the 4th span
Initiation of 1ST span wall 1st Initiation of 1ST span wall 1st Initiation of 1ST span wall 1st Lift
Lift upto 2 m Height Lift upto 2 m Height upto 2 m Height
cutting and Bending of Raft cutting and Bending of cutting and Bending of Vertical
Reinforcement of 2nd Span Vertical Reinforcement of Reinforcement span
7th Week 2nd span
7th Week
Shoring work on the Nullah Exavation of the required portion
side for the 5th Span on the STP side upto Rock Level
Exavation of the required for the 5th span
portion on the Nullah side upto
Rock Level for the 5th span
Preparation of Formation level PCC Work completion of 4th
2.05 to 4.05 of PCC for 4th Span Span
Concreting work of the 1st Lift Initiation of 2nd Lift wall of 2nd Lift wall of 1st Span
wall of 1st span 1st Span
5TH Span upto Bottom Level 5th Span upto Bottom Level
Breaking Breaking Disposal of Debris
2nd Lift wall of 1st Span Concreting of 2nd Lift wall of Initiation of 3rd Lift wall of 1st
1st span span
6.05 to 8.05 Concreting work of the Raft of Initiation of the 1st Lift wall
2nd span of 2nd Span 1st Lift wall of 2nd Span
Initiation of cutting and bending cutting and bending of steel Initiation of cutting and Bending
of steel for Shear Key reinf for for Shear Key reinf for 3rd of Raft Reinforcement for3rd
3rd Span Span Span
Initiation of breaking work for Breaking work for Shear Key Breaking work for Shear Key in
Shear Key in 5th span in 5th Span 5th Span
8th Week
Shoring work on the Nullah Exavation of the required portion
side for the 6th Span on the STP side upto Rock Level
Exavation of the required for the 6th span
portion on the Nullah side upto
Rock Level for the 6th span
9.05 to 11.05 Concreting of 3rd Lift wall of 1st
3rd Lift wall of 1st span 3rd Lift wall of 1st span Span
Concreting of 1st Lift wall of Initiation of 2nd Lift wall of 2nd
1st Lift wall of 2nd Span 2nd Span span
cutting and Bending of Raft cutting and Bending of cutting and Bending of Vertical
Reinforcement of 3rd Span Vertical Reinforcement of Reinforcement 3rd span
3rd span
6TH Span upto Bottom Level 6TH Span upto Bottom Level
Breaking Breaking Debris Removal
Preparation of Formation level PCC Work completion of 5th
of PCC for 5th Span Span
Initiation of Final Level Wall for
1st Span Final Level Wall for 1st Span Final Level Wall for 1st Span
Initiation of cutting and bending cutting and bending of steel Initiation of cutting and Bending
9th Week of steel for Shear Key reinf for for Shear Key reinf for 4th of Raft Reinforcement for4th
4th Span Span Span
Initiation of breaking work for Breaking work for Shear Key Breaking work for Shear Key in
Shear Key in 6th span in 6th Span 6th Span
Concreting of Final Level of 1st Initiation of 3rd lift wall of
Span 2nd Span 3rd lift wall of 2nd Span
cutting and Bending of Raft cutting and Bending of cutting and Bending of Vertical
Reinforcement of 4th Span Vertical Reinforcement of Reinforcement 4th span
4th span
Preparation of Formation level PCC Work completion of 6th
of PCC for 6th Span Span
Concreting of 3rd lift wall of Initiation of 4th Lift wall of 2nd
3rd lift wall of 2nd Span 2nd Span span
Concreting of 1st Lift wall of 3rd
1st Lift wall of 3rd span 1st Lift wall of 3rd span Span
19.05 to 21.05
Shuttering and Reinforcement Shuttering and
Reinforcement for 4th Span Shuttering and Reinforcement
for 4th Span Raft Raft for 4th Span Raft
10th Week Initiation of cutting and bending cutting and bending of steel Initiation of cutting and Bending
of steel for Shear Key reinf for for Shear Key reinf for 5th & of Raft Reinforcement for 5th &
5th & 6th Span 6th Span 6th Span
Initiation of 1st Lift wall of
Concreting of 4th span Raft 4th span 1st Lift wall of 4th span
4th(Final ) Lift wall of 2nd Concreting of Final Lift of 2nd
4th(Final ) Lift wall of 2nd span span Span
22.05 to 24.05
Initiation of 2nd Lift wall of 3rd
Span 2nd Lift wall of 3rd Span 2nd Lift wall of 3rd Span
Backfilling with compaction of Backfilling with compaction Backfilling with compaction of
1st Span of 1st Span 1st Span
cutting and Bending of Raft cutting and Bending of cutting and Bending of Vertical
Reinforcement of 5th Span & Vertical Reinforcement of Reinforcement 5th Span & 6th
6th span 5th Span & 6th span span
Filter media placement in the Filter media placement in Filter media placement in the
26.05 to 28.05 2nd span the 2nd span 2nd span
11th Week
26.05 to 28.05
Concreting of 1st lift wall of Initiation of 2nd Lift wall of 4th
1st Lift wall of 4th span 4th Span span
Concreting of 2nd Lift of 3rdInitiation of 3rd Lift wall of
Span 3rd Span 3rd Lift wall of 3rd Span
11th Week
Shuttering and Reinforcement Shuttering and
Reinforcement for 5th Span Shuttering and Reinforcement
for 5th Span Raft Raft for 5th Span Raft
2.06 to 4.06 Backfilling with compaction of Backfilling with compaction Backfilling with compaction of
1st & 2nd span of 1st & 2nd span 1st & 2nd span
Initiation of 3rd Lift wall of 4 th
span 3rd Lift wall of 4 th span 3rd Lift wall of 4 th span
Concreting of the Final Lift wall
Final Lift wall of 3rd Span Final Lift wall of 3rd Span of 3rd Span
12th Week
Initiation of 1st Lift wall of
Concreting of 6th span Raft 6th Span 1st Lift wall of 6th Span