ID Task Task Name Duration Start Finish Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half

Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
Mode M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
1 Fiber Optic Network Phase 6&7 333 days Tue 6/28/22 Thu 7/20/23
2 Kick off 1 day Tue 6/28/22 Tue 6/28/22
7 Milestone 1 141 days Wed 5/18/22 Fri 10/28/22
8 Preliminary Preparation
56 Material 256 days? Tue 8/2/22 Fri 5/26/23
78 Line SLNG-KLAI 3 days Fri 11/3/23 Mon 11/6/23
82 Line KLAI - BBTU 0 days Mon 11/6/23 Mon 11/6/23 11/6
86 Line YGPN-BBTU/BPHE 54 days Mon 11/6/23 Sat 1/6/24
90 Line BRNG-SMYH 12 days Sat 1/6/24 Fri 1/19/24
94 Line PMJY-PLTG 3 days Fri 1/19/24 Mon 1/22/24
98 Line PJML-PYSF 9 days Mon 1/22/24 Wed 1/31/24
102 Line PYSF-SSLG 18 days Wed 1/31/24 Tue 2/20/24
106 Line LKUT-TJGS 9 days Tue 2/20/24 Thu 2/29/24
110 Line UTMJ-TTKJ 3 days Thu 2/29/24 Sat 3/2/24
114 Line TTKJ-SNAI 6 days Sat 3/2/24 Fri 3/8/24
118 Line SDAI-UTMJ 3 days Fri 3/8/24 Mon 3/11/24
122 Line PSRI-PYSF 9 days Mon 3/11/24 Wed 3/20/24
126 Line SNAI-SLNG 3 days Wed 3/20/24 Fri 3/22/24
130 Line PSRI-SSLG 12 days Fri 3/22/24 Thu 4/4/24
134 Line BBTU-SDAI 33 days Thu 4/4/24 Sat 5/11/24
138 Line LKUT-KLAT 27 days Sat 5/11/24 Tue 6/11/24
142 Line PROI-TJID 9 days Tue 6/11/24 Thu 6/20/24
146 Line DMHT-TNHQ (UG + OPGW) 3 days Thu 6/20/24 Sat 6/22/24
150 Line SHMS-DMHT 6 days Sat 6/22/24 Fri 6/28/24
154 Line PIDH-PMRN 6 days Fri 6/28/24 Thu 7/4/24
158 Line BBTC-PMRN 6 days Thu 7/4/24 Wed 7/10/24
162 Line BBTG-BTRK 12 days Wed 7/10/24 Tue 7/23/24
166 Line BBTC-TPGR 9 days Tue 7/23/24 Thu 8/1/24
170 Line SGBT-NLDC 9 days Thu 8/1/24 Sat 8/10/24
174 Line NRWG-LKDG 9 days Sat 8/10/24 Tue 8/20/24
178 Line KCPK-SDCA 3 days Tue 8/20/24 Thu 8/22/24
182 Line SGBT-SHMS 3 days Thu 8/22/24 Sat 8/24/24
186 Line BBTG-BSTA 9 days Sat 8/24/24 Tue 9/3/24
190 Line KSBG-BJTG 9 days Tue 9/3/24 Thu 9/12/24
194 Line CBDK-SRYA 12 days Thu 9/12/24 Wed 9/25/24
198 Survey 1 day? Wed 8/3/22 Wed 8/3/22
199 Tools & Machinery 230 days? Thu 7/7/22 Fri 3/31/23
Task Project Summary Manual Task Start-only Deadline

Project: Simple Project Plan Split Inactive Task Duration-only Finish-only Progress
Date: Mon 11/6/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone