25. SNI 6.

29 1 M2 PASANG BEKISTING UNTUK SLOOF


Bahan
3
0.045 M Kayu Terentang / Mall Rp. 1,516,800.00 = Rp. 68,256.00
0.300 Kg Paku 1" - 2" Rp. 21,500.00 = Rp. 6,450.00
0.100 Liter Minyak Bekisting Rp. 15,600.00 = Rp. 1,560.00
Tenaga
0.300 Oh Pekerja Rp. 75,000.00 = Rp. 22,500.00
0.260 Oh Tukang Rp. 90,000.00 = Rp. 23,400.00
0.026 Oh Kepala Tukang Rp. 100,000.00 = Rp. 2,600.00
0.005 Oh Mandor Rp. 0.00 = Rp. 0.00
Jumlah Rp. 124,766.00

26. SNI 6.30 1 M2 PASANG BEKISTING UNTUK KOLOM


Bahan
3
0.040 M Kayu Terentang / Mall Rp. 1,516,800.00 = Rp. 60,672.00
0.400 Kg Paku 1" - 2" Rp. 21,500.00 = Rp. 8,600.00
0.200 Liter Minyak Bekisting Rp. 15,600.00 = Rp. 3,120.00
3
0.015 M Balok Kayu Rp. 1,516,800.00 = Rp. 22,752.00
2.000 Btg Dolken Kayu Galam Ø 8 - 10 P = 4 m Rp. 7,100.00 = Rp. 14,200.00
Tenaga
0.300 Oh Pekerja Rp. 75,000.00 = Rp. 22,500.00
0.330 Oh Tukang Rp. 90,000.00 = Rp. 29,700.00
0.033 Oh Kepala Tukang Rp. 100,000.00 = Rp. 3,300.00
0.006 Oh Mandor Rp. 0.00 = Rp. 0.00
Jumlah Rp. 164,844.00

27. SNI 6.31 1 M2 PASANG BEKISTING UNTUK BALOK


Bahan
3
0.040 M Kayu Terentang / Mall Rp. 1,516,800.00 = Rp. 60,672.00
0.400 Kg Paku 1" - 2" Rp. 21,500.00 = Rp. 8,600.00
0.200 Liter Minyak Bekisting Rp. 15,600.00 = Rp. 3,120.00
3
0.015 M Balok Kayu Rp. 1,516,800.00 = Rp. 22,752.00
2.000 Btg Dolken Kayu Galam Ø 8 - 10 P = 4 m Rp. 7,100.00 = Rp. 14,200.00
Tenaga
0.320 Oh Pekerja Rp. 75,000.00 = Rp. 24,000.00
0.330 Oh Tukang Rp. 90,000.00 = Rp. 29,700.00
0.033 Oh Kepala Tukang Rp. 100,000.00 = Rp. 3,300.00
0.006 Oh Mandor Rp. 0.00 = Rp. 0.00
Jumlah Rp. 166,344.00

28. 1 M3 PEKERJAAN SLOOF BETON 15 X 20


3
1.000 M Beton Rp. 675,040.00 = Rp. 675,040.00
111.450 Kg Besi Beton Rp. 12,023.50 = Rp. 1,340,019.08
2
13.333 M Bekisting Sloof Rp. 124,766.00 = Rp. 1,663,505.08
Jumlah Rp. 3,678,564.15
3
29. 1 M PEKERJAAN KOLOM 15 x 15
3
1.000 M Beton 1 : 2 : 3 Rp. 675,040.00 = Rp. 675,040.00
142.464 Kg Besi Beton Rp. 12,023.50 = Rp. 1,712,915.90
2
13.330 M Bekisting Kolom Rp. 164,844.00 = Rp. 2,197,370.52
Jumlah Rp. 4,585,326.42
30. 1 M3 PEKERJAAN KOLOM 20 x 20
3
1.000 M Beton 1 : 2 : 3 Rp. 675,040.00 = Rp. 675,040.00
127.408 Kg Besi Beton Rp. 12,023.50 = Rp. 1,531,890.09
2
20.000 M Bekisting Kolom Rp. 164,844.00 = Rp. 3,296,880.00
Jumlah Rp. 5,503,810.09
31. 1 M3 PEKERJAAN KOLOM 25 x 25
3
1.000 M Beton 1 : 2 : 3 Rp. 675,040.00 = Rp. 675,040.00
90.860 Kg Besi Beton Rp. 12,023.50 = Rp. 1,092,455.21
2
13.333 M Bekisting Kolom Rp. 164,844.00 = Rp. 2,197,865.05
Jumlah Rp. 3,965,360.26