Professional Documents
Culture Documents
Managing Project
Managing Project
Project
PROJECT
MANAGEMENT
1. What is a Project?
1. What is a Project?
A project is temporary
► It has a definite start and end date
► Thereby having a defined scope and resources
► A project is also unique
► It is not routine everyday operational work with repetitive output
► It is a specific set of activities designed to accomplish a well-defined unique
objective
Project Management
4. Cost
► Project managers are responsible for estimating,
budgeting and controlling costs so the project
can be completed within the approved budget.
The Six Constraint of Operations
Management
5. Risk
► A project manager must be able to reasonably foresee
failures at every step of a project, and prepare for them
accordingly. This can involve playing out what-if scenarios
and formulating contingency plans:
❖ What if a supplier fails to deliver?
❖ What if we lose any number of resources due to illness or transfer?
❖ What if the market takes a huge swing?
❖ What if our competitor launches a similar product at the same
time?
6. Resources
➢ Every project requires resources like human resources,
financial resources, technological resources and other
resources need to meet the project requirement.
Project Management Life Cycle
Five Phases
Project Management Life Cycle
1. Initiation Phase
Project Management Life Cycle
2. Planning Phase
Project Management Life Cycle
3. Execution Phase
Project Management Life Cycle
4. Monitoring and Control Phase
Project Management Life Cycle
5. Closure Phase
The Importance of Project Management
1. Strategic Alignment
⮚ ensures what is being delivered is right, and will deliver real value against the business
opportunity
⮚ ensure there’s rigor in architecting projects properly
2. Leadership
⮚ brings leadership and direction to projects
⮚ vision, motivation, removing roadblocks, coaching, and inspiring the team to do their
best work.
3. Clear Focus & Objectives
⮚ ensures there’s a proper plan for executing on strategic goals.
4. Realistic Project Planning
⮚ ensures proper expectations are set around what can be delivered, by when, and for
how much.
5. Quality Control
⮚ ensures the quality of whatever is being delivered, consistently hits the mark.
Work Breakdown Structure
A C
E
Start H
B D G
Project Management Techniques
Project Controlling
Determining the Project Schedule
After completing AON project network and had been drawn showing all activities and their
precedence relationships, the next step is to determine the project schedule to identify the
planned starting and ending time for each activity.
To find the critical path, we calculate two distinct starting and ending times for each activity.
These are defined as:
Earliest Start (ES) – earliest time at which an activity can start, assuming all predecessors
have been completed.
Earliest Finish (EF) – earliest time at which an activity can be finished
Latest Start (LS) – latest time at which an activity can start so as to not delay the completion
time of the entire project.
Latest Finish (LF) – latest time by which an activity has to finish so as to not delay the
completion time of the entire project
Project Management Techniques
Project Controlling
Determining the Project Schedule
We use two-pass process to determine these time schedules for each activity, forward pass
and a backward pass.
Forward Pass
Earliest Start Time Rule. Before an activity can start, all its immediate predecessor must be
finished.
► If an activity has only single immediate predecessor, its ES equals to EF of the predecessor.
► If an activity has a multiple immediate predecessor, its ES is the maximum of all EF values
of its predecessors.
ES = Max (EF of all immediate predecessors)
Earliest Finish Time Rule. The earliest finish time (EF) of an activity is the sum of the earliest start
time (ES) and its activity time.
EF = ES + Activity time
Project Management Techniques
Project Controlling
Determining the Project Schedule
Backward Pass
Backward pass begins with the last activity in the project. For each activity, we first determine its LF value,
followed by its LS value. The following two rules are used in this process.
Latest Finish Time Rule. Before an activity can start, all its immediate predecessors must be finished.
► If an activity is an immediate predecessor for just a single activity, its LF equals to the LS of the activity the
immediately follow it.
► If an activity has a multiple immediate predecessor, its LF is the minimum of all LS values of all activities.
LF =Minimum (LS of all immediate following activities)
Latest Start Time Rule. The latest start time (LS) of an activity is the difference of its
latest finish time (LF) and its activity time.
LS=LF -Activity Time
Project Management Techniques
Project Controlling
Determining the Project Schedule
Calculating Slack Time and Identifying the Critical Path
After we have computed the earliest and latest time for all activities, find the amount of
slack time that each activity has. Slack is the length of time an activity can be delayed
without delaying the entire project.
Slack = LS – ES or Slack = LF – EF
The activities with zero slack are called critical activities and are said to be on the
critical path. The critical path is a continuous path through the project network that:
► Starts at the first activity in the project.
► Terminates at the last activity in the project.
► Includes only critical activities.
❖ slack time is the amount of time that a task in a project network can be delayed without causing a
delay to: subsequent tasks ("free float") project completion date ("total float")
Project Management Techniques
Project Controlling
Determining the Project Schedule
Notation Used in Nodes for Forward and Backward Pass
Project Management Techniques
Project Controlling
Project Management Techniques
Project Controlling
Project Management Techniques
Project Controlling
Network Diagrams and Approaches
AON Network for Milwaukee Paper
A C
E
Start H
B D G
Critical Path
A C F
0 0 E H
B D G
Critical Path
A C F
0 0 E H
B D G
Critical Path
A C F
0 0 E H
B D G
3
Critical Path
A C F
2 2
0 0 E H
B D G
3
Critical Path
A C F
2 2
0 0 E H
B D G
3 4
Critical Path
A C F
2 2
0 0 E H
0 4
B D G
3 4
Critical Path
A C F
2 2 3
0 0 E H
0 4
B D G
3 4
Critical Path
A C F
2 2 3
0 0 E H
0 4
B D G
3 4 5
Critical Path
A C F
2 2 3
0 0 E H
0 4 2
B D G
3 4 5
Critical Path
0 A C F
2 2 3
0 0 E H
0 4 2
B D G
3 4 5
Critical Path
0 A 2 C F
2 2 3
0 0 E H
0 4 2
B D G
3 4 5
Critical Path
0 A 2 C F
2 2 3
0 0 E H
0 4 2
0 B D G
3 4 5
Critical Path
0 A 2 C F
2 2 3
0 0 E H
0 4 2
0 B 3 D G
3 4 5
Critical Path
0 A 2 2 C F
2 2 3
0 0 E H
0 4 2
0 B 3 D G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 E H
0 4 2
0 B 3 D G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 E H
0 4 2
0 B 3 3 D G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 E H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 4 E H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 4 E 8 H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 E H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 4 E H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 F
2 2 3
0 0 4 E 8 H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 4 F
2 2 3
0 0 4 E 8 H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 H
0 4 2
0 B 3 3 D 7 G
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 H
0 4 2
0 B 3 3 D 7 8 G
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 H
0 4 2
0 B 3 3 D 7 8 G 13
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 13 H
0 4 2
0 B 3 3 D 7 8 G 13
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 13 H 15
0 4 2
0 B 3 3 D 7 8 G 13
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 13 H 15
0 4 2 15
0 B 3 3 D 7 8 G 13
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 13 H 15
0 4 13 2 15
0 B 3 3 D 7 8 G 13
3 4 5
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 13 H 15
0 4 13 2 15
0 B 3 3 D 7 8 G 13
3 4 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3
0 0 4 E 8 13 H 15
0 4 13 2 15
0 B 3 3 D 7 8 G 13
3 4 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 3 13
0 0 4 E 8 13 H 15
0 4 13 2 15
0 B 3 3 D 7 8 G 13
3 4 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 10 3 13
0 0 4 E 8 13 H 15
0 4 13 2 15
0 B 3 3 D 7 8 G 13
3 4 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 10 3 13
0 0 4 E 8 13 H 15
0 4 8 13 2 15
0 B 3 3 D 7 8 G 13
3 4 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
3 4 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
3 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
3 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
3 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
3 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1 1 1
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 0
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1 1 1
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0 6 6
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 0
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1 1 1
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0 6 6
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 0
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1 1 1 0 0
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0 6 6
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 0 0 0
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1 1 1 0 0
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0 6 6
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
0 0 0 0
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1 1 1 0 0
1 3 4 4 4 8 8 5 13
Critical Path
0 A 2 2 C 4 4 F 7
0 0 0 0 6 6
0 2 2 2 2 4 10 3 13
0 0 4 E 8 13 H 15
CRITICAL PATH 0 0 0 0
0 4 4 8 13 2 15
0 B 3 3 D 7 8 G 13
1 1 1 1 0 0
1 3 4 4 4 8 8 5 13
Project Management Techniques
Project Controlling
Determining the Project Schedule
Variability in Activity Times
The impact of variability time is important to address in deciding the schedule for a project. To
address this issues, we will be using the Project Evaluation and Review Techniques (PERT).
Three Time Estimates in PERT
In PERT, we employ a probability distribution based on three times estimates for each
activity as follows:
Optimistic Time (a) = time an activity will take if everything goes as planned. In estimating
this value, there should be only a small probability (say 1/100) that
the activity time will be < a.
Pessimistic Time (b) = time an activity will take assuming very unfavorable condition. In
estimating this value, there should also be only a small probability
that the activity time be >b.
Most Likely Time (m) = most realistic estimate of the time required to complete an activity.
Project Management Techniques
Project Controlling
Determining the Project Schedule
Variability in Activity Times
When using PERT, we often assume that activity time estimates follow the beta probability
distribution. This continuous distribution is often appropriate for determining the expected
value and variance for activity completion times.
To find the expected activity time, t, the beta distribution weights the three time
estimates as follows:
t = (a + 4m + b)/6
To compute the dispersion or variance of activity completion time we use the
formula.
Variance = [(b-a)/6]2
❖ The beta distribution is a weighted average in which more weight is given to the most likely estimate.
Computing Project Variance
and Standard Deviation
0.11+0.11+1.00+1.78+0.11=
3.11
Standard Deviation = (σp)
σp = √3.11 =1.76
Computing Project Variance
and Standard Deviation
0.11+0.11+1.00+1.78+0.11=
3.11
Standard Deviation = (σp)
σp = √3.11 =1.76 ±1.76
Standard Deviation
7157
Normal Distribution Table
Project Z score = 0.57
71.57%
Probability that the
project will finished
on scheduled date
“Today a reader, tomorrow a leader. ”
– Margaret Fuller