Test Procedure for Interconnection Panel and TNB Panel Interlocking.

A. Preliminary Work

1. Rack in both circuit breakers into service position where applicable.


2. Check current differential relay communication between local and remote end is active.

B. Interlocking Test

No Initial Condition Action Result

TNB VCB Close (Service Position) TNB VCB Close (Service Position)
1. Close RE VCB
RE VCB Open (Service Position) RE VCB Close (Service Position)

2. TNB VCB Open (Service Position)


Close RE VCB No operation
RE VCB Open (Service Position)

3. TNB VCB Close (Service Position) TNB VCB Open (Service Position)
Open TNB VCB
RE VCB Close (Service Position) RE VCB Open (Service Position)

TNB VCB Open (Service Position)


4. RE VCB Open (Test Position) Close TNB VCB No operation
RE E/SW Close

TNB VCB Close (Service Position) TNB VCB Open (Service Position)
5. Simulate Comm. Fail
RE VCB Close (Service Position) RE VCB Open (Service Position)

TNB VCB Close (Service Position) TNB VCB Open (Service Position)
6. RE VCB Open (Test Position) Close RE Earth Switch RE VCB Open (Test Position)
RE E/SW Close

TNB VCB Open (Service Position) TNB VCB Open (Service Position)
Close TNB VCB by
7. RE VCB Open (Test Position) RE VCB Open (Test Position)
manual push button
RE E/SW Close RE E/SW Close