Summary of Emergency Works NWP/ i roads

No Package Road ID Work Section Description Work Cost

Reconstruction Culvert at CH
04+182 of Thiththakade to Culvert need to be
1 PU2-R2 29 04+182 Culvert 1,418,705.80
Manuwangama via Thissogama Reconstruction
Road

Provide Accesses from CH 00+000


to CH 00+700 RHS of Thiththakade
2 PU2-R2 29 00+000-00+700 RHS Accesses to be Provide 3,688,330.20
to Manuwangama via Thissogama
Road

Completion Surfacing Works from


CH 00+000 to CH 01+970 of
3 PU2-R2 28 00+000-01+970 Shoulder to be Completed 2,706,041.25
E/Mungandaluwa Ranaviru Lanka
Thilaka Mawatha to Karavita Road

Total Cost 7,813,077.25

Prepared by Checked by Recommended by

………………………………………. ……………………………………… …………………………………………………


I.M.S.K.Bandara (AQS) M.A.G.T.Mallawaarachchi (CE) T.I.Jayathilaka (ARE)

Page 1 of 4
Reconstruction Culvert at CH 04+182 of Thiththakade to Manuwangama via Thissogama Road

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT (Rs)
Bill Pay

3.1 STRUCTURE EXCAVATION AND BACKFILL

3.1.1 302(5) Excavation for structures, unsuitable soil Cu.m 23.72 4,650.00 110,298.00

3.1.2 302(8) Backfill with granular material Cu.m 2.22 6,500.00 14,430.00

6.1 CULVERTS

6.1.1 705(1) Aggregate backfill Cu.m 0.40 8,500.00 3,400.00

6.1.2 705(2) Filter medium Cu.m 0.40 7,500.00 3,000.00

6.1.3 705(3) Impervious layer Cu.m 7,500.00 7,500.00

6.1.4 706(1) Weep hole, PVC pipe (Type 600) - 75mm diameter L.m 3.60 1,500.00 5,400.00

6.1.5 808(5) Guard stone Nr 6.00 4,500.00 27,000.00

6.1.6 1001(1) Concrete: Grade 15 Cu.m 5.43 23,500.00 127,605.00

6.1.7 1001(3) Concrete: Grade 25 Cu.m 10.07 26,500.00 266,855.00

6.1.8 1002(1) Tor steel reinforcement M.t 0.273 330,000.00 90,090.00

6.1.9 1008(1) Formwork smooth finish Sq.m 8.96 2,850.00 25,536.00

6.1.10 1008(2) Formwork rough finish Sq.m 32.36 2,650.00 85,754.00

766,868.00

Allow for Price Escalation = 85% 651,837.80

Total 1,418,705.80

Prepared by Checked by Recommended by

………………………………………. ……………………………………… …………………………………………………


I.M.S.K.Bandara (AQS) M.A.G.T.Mallawaarachchi (CE) T.I.Jayathilaka (ARE)

Page 2 of 4
Provide Accesses from CH 00+000 to CH 00+700 RHS of Thiththakade to Manuwangama via
Thissogama Road

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT (Rs)
Bill Pay

3.1 STRUCTURE EXCAVATION AND BACKFILL

3.1.1 302(5) Excavation for structures, unsuitable soil Cu.m 62.56 4,650.00 290,904.00

5.1 ROAD SIDE AND LEADAWAY DRAINS

5.1.1 701(2) a Lining of drains with Concrete: Grade 15 (20) Cu.m 1.53 23,500.00 35,955.00

5.1.2 701(2) b Lining of drains with Concrete: Grade 20 (20) Cu.m 13.94 25,500.00 355,470.00

5.1.11 707(6) b Reinforced concrete pipes 600mm diameter lm 61.20 11,500.00 703,800.00

5.1.12 1002(1) Tor steel reinforcement M.t 0.255 330,000.00 84,150.00

5.1.13 1008(1) Formwork smooth finish Sq.m 26.69 2,850.00 76,066.50

5.1.14 1008(2) Formwork rough finish Sq.m 168.81 2,650.00 447,346.50

1,993,692.00

Allow for Price Escalation = 85% 1,694,638.20

Total 3,688,330.20

Prepared by Checked by Recommended by

………………………………………. ……………………………………… …………………………………………………


I.M.S.K.Bandara (AQS) M.A.G.T.Mallawaarachchi (CE) T.I.Jayathilaka (ARE)

Page 3 of 4
Completion Surfacing Works from CH 00+000 to CH 01+970 of E/Mungandaluwa Ranaviru
Lanka Thilaka Mawatha to Karavita Road

ITEM
DESCRIPTION UNIT QTY RATE AMOUNT (Rs)
Bill Pay

4.2 SHOULDERS

4.2.4 409(1) Earthen shoulders as compacted in position Cu.m 295.50 4,950.00 1,462,725.00

1,462,725.00

Allow for Price Escalation = 85% 1,243,316.25

Total 2,706,041.25

Prepared by Checked by Recommended by

………………………………………. ……………………………………… …………………………………………………


I.M.S.K.Bandara (AQS) M.A.G.T.Mallawaarachchi (CE) T.I.Jayathilaka (ARE)