Emergency Works Estimates Rate Breakdown PU 09.08.2023
Emergency Works Estimates Rate Breakdown PU 09.08.2023
Reconstruction Culvert at CH
04+182 of Thiththakade to Culvert need to be
1 PU2-R2 29 04+182 Culvert 1,418,705.80
Manuwangama via Thissogama Reconstruction
Road
Page 1 of 4
Reconstruction Culvert at CH 04+182 of Thiththakade to Manuwangama via Thissogama Road
ITEM
DESCRIPTION UNIT QTY RATE AMOUNT (Rs)
Bill Pay
3.1.1 302(5) Excavation for structures, unsuitable soil Cu.m 23.72 4,650.00 110,298.00
3.1.2 302(8) Backfill with granular material Cu.m 2.22 6,500.00 14,430.00
6.1 CULVERTS
6.1.4 706(1) Weep hole, PVC pipe (Type 600) - 75mm diameter L.m 3.60 1,500.00 5,400.00
766,868.00
Total 1,418,705.80
Page 2 of 4
Provide Accesses from CH 00+000 to CH 00+700 RHS of Thiththakade to Manuwangama via
Thissogama Road
ITEM
DESCRIPTION UNIT QTY RATE AMOUNT (Rs)
Bill Pay
3.1.1 302(5) Excavation for structures, unsuitable soil Cu.m 62.56 4,650.00 290,904.00
5.1.1 701(2) a Lining of drains with Concrete: Grade 15 (20) Cu.m 1.53 23,500.00 35,955.00
5.1.2 701(2) b Lining of drains with Concrete: Grade 20 (20) Cu.m 13.94 25,500.00 355,470.00
5.1.11 707(6) b Reinforced concrete pipes 600mm diameter lm 61.20 11,500.00 703,800.00
1,993,692.00
Total 3,688,330.20
Page 3 of 4
Completion Surfacing Works from CH 00+000 to CH 01+970 of E/Mungandaluwa Ranaviru
Lanka Thilaka Mawatha to Karavita Road
ITEM
DESCRIPTION UNIT QTY RATE AMOUNT (Rs)
Bill Pay
4.2 SHOULDERS
4.2.4 409(1) Earthen shoulders as compacted in position Cu.m 295.50 4,950.00 1,462,725.00
1,462,725.00
Total 2,706,041.25