Professional Documents
Culture Documents
Due Diligence Report Kotak
Due Diligence Report Kotak
Floor Status-
Builder Fire Line installed.
HVAC outlet on the floor connected to the main AHU.
Floor Screed condition worsen (only patches left).
Site Layout (4th Floor)-
Site Photographs-
4th floor-
Site Layout (6th Floor)-
Site Photographs-
6th floor-
Site Inspection- Aloft
Address- 5th & 6th floor Aloft, IGI T3 Road, Aerocity, Delhi Aerocity New Delhi, Delhi 110037
Building Age- 10 years
Physical Constraints-
Vehicle Movement only from Gate no. 4
Debris Removal only after 7 pm
No extra storage area anything will be provided for the material storage, everything needs to
be stacked at the floor area only. No space outside will be provided.
No Service lift only staircase accessible (ST-4).
Electricity connection will be provided.
Wide accessible road in front of the building for vehicle movement.
Floor Status-
Builder Fire Line installed.
HVAC outlet on the floor connected to the main AHU. The existing AC cassette is working.
Services work done needs to be remodified.
Floor screeding done (Patches left).
Finishing at some places done.
Site Photographs-
6th floor-
Checklist-