Work Methodology For Toilet Construction
Work Methodology For Toilet Construction
INDEX
1. INTRODUCTION
1.1 GENERAL
1.2 DESCRIPTION O F ACTIVITY
2. SCOPE OF WORKS
2.1 GROUND FLOOR LEVEL
2.2 FIRST F LOOR LEVEL
3. MOBILIZATION
3.1 RESPONSIBILITIES
3.2 EQUIPMENT
3.3 TRAFFIC MANAGEMENTS
1.2 GENERAL
ALL WORKS WILL BE CARRIED OUT IN ACCORDANCE WITH INSTRUCTIONS TO TENDERER’S AND IN CONSTANT
COORDINATION WITH THE CLIENT’S REPRESENTATIVE. THE METHOD OF STATEMENT TO BE FOLLOWED WILL MAINTAIN
COST SCHEDULE RESOURCE EQUILIBRIUM AND CONSIDER AND COMMUNICATE IT ’S IMPACT ON THE SOCIAL LIFE OF THE
STAFF WORKING AROUND THE PROJECT SITE.
TO ENSURE THAT THE MATERIALS AND RELATED ACTIVITIES ARE EXECUTED SAFETY AND IN ACCORDANCE WITH THE
CONTRACT REQUIREMENTS AND THAT ALL QUALITY ASSURANCE / CONTROL ACTIVITIES ARE CONDUCTED IN A
SYSTEMATIC MANNER. TO ENSURE THAT WORKS ARE INSPECTED, CONFORMANCE IS VERIFIED AND DOCUMENTED.
2. SCOPE OF WORKS
3. MOBILIZATION
- ALL CONTRACTOR’S LABOUR AND MACHINERY WILL BE PRESENTED ON SITE IN SUFFICIENCY TO COMPLETE THE
WORKS ON TIME.
3.1 RESPONSIBILITIES
A. THE PROJECT MANAGER OF CONSTRUCTION MANAGER SHALL BE RESPONSIBLE FOR THE OVERALL
IMPLEMENTATION OF THIS PROCEDURE FOR SUSPENDED CEILING WORKS, ENSURING THE WORKS DESCRIBED IN
THIS STATEMENT ARE CONDUCTED TO REQUIRED CODES, STANDARDS AND BEST PRACTICES IN CONFORMANCE
WITH APPROVED DRAWINGS AND SPECIFICATIONS.
B. SITE ENGINEER ALONG WITH FOREMAN WILL ENSURE THAT THE WORKS ARE CARRIED OUT IN ACCORDANCE
WITH THE SPECIFICATIONS, APPROVED DRAWINGS AND IN ACCORDANCE WITH THIS METHOD STATEMENT .
C. SAFETY OFFICER SHALL ENSURE IMPLEMENTATION OF ALL SAFETY PROCEDURES AND REGULATIONS AS PER OUR
HSE PLAN AND IN ACCORDANCE WITH THE SAFETY PLAN SET BY CONTRACTOR, HE SHALL CONDUCT TRAINING
AND TOOL BOX TALKS ON THE HAZARDS, DANGERS AND CONTROLS BEFORE COMMENCEMENT OF WORKS. HE
SHALL OBSERVE AND ENSURE THAT QATAR REGULATIONS ARE COMPLIED WITH.
3.2 EQUIPMENT’S
- BELOW ARE THE EQUIPMENT’S AVAILABLE INVOLVED IN THE EXECUTION OF FIT-OUT WORKS:
A. SCAFFOLDING WITH FRAMES, BRACES AND WALK-BOARDS
B. SAND PAPER, SCRAPERS AND PAINTING TOOLS
C. POWER TOOLS SUCH AS CIRCULAR SAW, CORDLESS SCREW GUN, TILE CUTTER / SAW
D. LEVELING SPIRIT, CLAMPS, PLIERS, UTILITY KNIFE (BOARD CUTTER), TROWELS AND LEVELING TOOLS
E. GENERATORS AND CONSTRUCTION LIGHTING
REQUIRED NUMBER OF
ACTIVITY ACTIVITY PARTY MAN-HOUR per DESIGNATED
NO. OF DAYS
ID DESCRIPTION RESPONSIBLE day AREAS
MANPOWER COMPLETED
Demolition of 8 – 10 hours/day
Engineer In-
Act.1 existing floor & 4 labors Starting at 3 PM
charge
wall tiles onwards
Removal of 8 – 10 hours/day
existing ceiling Engineer In-
Act. 2 Starting at 3 PM
tiles and charge
channels onwards
Act. 3